Loading...
HomeMy WebLinkAboutSconset 2020 Sand Delivery and Contribution Report 3_16_20January 2020 - January 2021 Sand Delivery and Contribution Report Baxter Road and Sconset Bluff Stabilization Project Nantucket, MA March 2021 Submitted by: Siasconset Beach Preservation Fund PO Box 2279 Nantucket, MA 02584 Prepared by: Epsilon Associates 3 Mill & Main Place, Suite 250 Maynard, MA 01754 In Association with : Cottage + Castle, Inc. 37 Old South Road, Unit #6 Nantucket, MA 02554 PRINCIPALS Theodore A Barten, PE Margaret B Briggs Dale T Raczynski, PE Cindy Schlessinger Lester B Smith, Jr Robert D O’Neal, CCM, INCE Michael D Howard, PWS Douglas J Kelleher AJ Jablonowski, PE Stephen H Slocomb, PE David E Hewett, LEED AP Dwight R Dunk, LPD David C Klinch, PWS, PMP Maria B Hartnett Richard M Lampeter, INCE Geoff Starsiak, LEED AP BD+C Marc Bergeron, PWS, CWS ASSOCIATES Alyssa Jacobs, PWS Holly Carlson Johnston Brian Lever 3 Mill & Main Place, Suite 250 Maynard, MA 01754 www.epsilonassociates.com 978 897 7100 FAX 978 897 0099 March 16, 2021 Nantucket Conservation Commission 2 Bathing Beach Road Nantucket, MA 02554 Subject: Annual Sand Delivery and Contribution Report File No. SE 48-2824, Sconset Bluff Geotextile Tube Project, Nantucket MA Dear Commissioners: On behalf of the Siasconset Beach Preservation Fund (“SBPF”), Epsilon Associates, Inc. submits the attached Annual Sand Delivery and Contribution Report (prepared as required in Special Condition 32.d). If you have any questions regarding this transmittal, please contact me at 978-897-7100 or ddunk@epsilonassociates.com. Sincerely, EPSILON ASSOCIATES, INC. Dwight R. Dunk, LPD, PWS, BCES Principal 21597/Sconset 1 2020 Annual Sand Delivery Report Epsilon Associates, Inc. ANNUAL SAND DELIVERY REPORT 1.0 Introduction The Baxter Road and Sconset Bluff Stabilization Project (the “Project”) was constructed in two phases. The first phase was constructed in late December 2013 and January 2014 via an Emergency Certification approval issued by the Nantucket Conservation Commission. The first phase consisted of the installation of three stacked tiers of 45-foot circumference geotextile tubes at the base of the eroding Sconset Bluff. The geotextile tube installation was approximately 852 feet long and extended along the toe of the bank from 87-105 Baxter Road. The second phase was constructed in October 2015 through February 2016 and included the installation of a fourth tier of geotextile tubes on lots 91-99, intermediate returns, end returns, and a surface runoff drainage system. With the returns included, the total project length is now 947 feet. The purpose of the annual sand delivery report is to present the sand mitigation volumes and corresponding delivery tickets for each “Sand Year” initially from April 1 through March 31 of any given year. SBPF has previously submitted detailed Sand Reports for the first six sand years associated with the Project: • November 2013 through March 31, 2014 (referred to as the “2014 Sand Year”) • April 1, 2014 through March 31, 2015 (referred to as the “2015 Sand Year”) • April 1, 2015 through March 31, 2016 (referred to as the “2016 Sand Year”) • April 1, 2016 through January 31, 2018 (referred to as the “2017 Sand Year”) • February 1, 2018 through April 30, 2018 (referred to as the “2018 Sand Year”) • May 1, 2018 through December 31, 2019 (referred to as the “2019 Sand Year”) This report presents information on sand deliveries during the period from January 1, 2020 through January 15, 2021 (referred to as the “2020 Sand Year”). 2.0 Sand Delivery Requirements The Project incorporates a substantial mitigation volume of 22 cubic yards/linear foot/year[cy/lf/yr]. Given the project’s length of 947 feet, the total annual mitigation volume required is currently 20,834 cy. As required by the Project’s Order of Conditions (SE48-2824), annually in Sept. – Nov. place sand to ensure a substantial volume of sand (10 – 15 cy/lf) is available at the onset of the winter storm season, place additional sand as needed during the winter and if the total volume is not placed before March 1, the balance shall be placed by March 31. Delivery tickets are to be provided annually to document the total volume of sand provided on a yearly basis. 21597/Sconset 2 2020 Annual Sand Delivery Report Epsilon Associates, Inc. 3.0 Volume of Mitigation Sand Delivered The following ten tables document the sand delivery amounts. ♦ Tables 1-2 present a summary of the volume of sand delivered and contributed from December 2013 through January 15, 2021. Table 3 presents a comparison of the volume of sand eroded from the bluff in adjacent unprotected areas from July 2013 – June 2020. ♦ Table 4 presents the volume of sand delivered during the period from December 2013 – March 31, 2014, which includes construction of the initial Project. ♦ Table 5 presents the total volume of mitigation sand delivered during the period from April 1, 2014 – March 31, 2015. ♦ Table 6 presents the total volume of sand delivered during the period from April 1, 2015 – March 31, 2016, which includes supplementary construction of the fourth tier and returns. ♦ Table 7 presents the total volume of sand delivered during the period from April 1, 2016 – January 31, 2018. ♦ Table 8 presents the total volume of sand delivered during the period from February 1, 2018 – April 30, 2018. ♦ Table 9 presents the total volume of sand delivered during the period from May 1, 2018 – December 31, 2019. ♦ Table 10 presents the total volume of sand delivered during the period from January 1, 2020 through January 15, 2021. Each of these tables is discussed in further detail below. 3.1 Table 1. Summary of Sand Delivery Volume Lines 1-4 of Table 1 describe the total volume of sand delivered to the site, and separate this total into the following categories: mitigation sand, sand used on the bluff face, and sand used for construction (inside or behind the geotextile tubes). Neither sand placed on the bluff face nor sand used for construction is counted towards the mitigation requirement. Lines 5-11 of Table 1 provide a summary of the required mitigation volume. The base mitigation volume is determined by multiplying the 22 cy/lf/yr by the Project’s length (Line 5). This volume is then adjusted by subtracting out the surplus sand from the previous year and the amount of sand eroded from the bluff face. The surplus sand is calculated as that sand delivered the previous year that is in excess of the base mitigation requirements and that is still in the sand template at the end of the sand year (see Line 6-8). The bluff erosion volume accounts for that portion of the bluff face that continued to erode and is discussed further in Section 5.0 below. 21597/Sconset 3 2020 Annual Sand Delivery Report Epsilon Associates, Inc. Lines 13 and 14 of Table 1 presents the final calculation of whether the project’s mitigation requirement was met. Any surplus of sand delivered during one year, up to but not in excess of the amount remaining on the sand template on the beginning of the new sand year, is carried forward and counted towards the following year’s requirement. 3.2 Table 2. Summary of Sand Contribution Table 2 presents a summary of the volume on sand contribution for the period from December 2013 – December 31, 2020. Table 2 provides a breakdown of the sand contribution from the sand template, bluff face, construction, and the total contribution. Line 9 of Table 2 provides the total volume of sand contributed during the 2020 Sand Year. Line 10 provides the average of annual sand contribution from December 2013 – January 15, 2021. 3.3 Table 3. Bluff Volume Loss in Unprotected Areas Adjacent to Geotextile Tubes Tables 3a-c present a comparison of the volume of sand eroded from the bluff in adjacent unprotected areas from July 2013 – June 2020. Table 3a provided the bluff volume change from September 2019 – June 2020. During this period the unprotected bluffs to the north and the south of the geotextile tubes eroded approximately 4,623 cy which is equivalent to a distance-weighted average of 6.6 cy/lr/yr. Table 3b presents the bluff volume loss during the period of May 2013 – September 2019. Table 3c presents the bluff volume loss in the unprotected areas adjacent to the geotextile tubes from July 2013 – June 2020. 3.4 Table 4. Sand Delivery December 2013 – March 31, 2014 Table 4 presents the volume of sand delivered during the period from December 2013 – March 31, 2014, which includes construction of the initial Project. Table 4 provides a detailed breakdown of that portion of sand placed within and behind the geotextile tubes and presents the total volume of mitigation sand placed over, in front of, and at the ends of the geotextile tubes. All delivery tickets for the total volume delivered of 39,204 cy were previously submitted to the Conservation Commission, most recently as part of the 2015 Sand Report. 3.5 Table 5. Sand Delivery April 1, 2014 – March 31, 2015 Table 5 presents the total volume of mitigation sand delivered during the period from April 1, 2014 – March 31, 2015. Three separate deliveries were made over this period of time. All delivery tickets for the total volume of 14,428 cy were submitted as part of the 2015 Sand Report. 3.6 Table 6. Sand Delivery April 1, 2015 – March 31, 2016 Table 6 presents the total volume of sand delivered during the period from April 1, 2015 – March 31, 2016. Table 6 provides a detailed breakdown of the sand delivered for construction, sand delivered for mitigation, and sand delivered to the bluff face. All delivery tickets for the total volume of 22,485 cy delivered during the 2016 Sand year were provided in the 2016 Sand Report, including the 19,066.7cy delivered during the most recent construction period in November, December, and January and the 3,418 cy delivered in April 2015. 21597/Sconset 4 2020 Annual Sand Delivery Report Epsilon Associates, Inc. 3.7 Table 7. Sand Delivery April 1, 2016 – January 31, 2018 Table 7 presents the total volume of sand delivered during the period from April 1, 2016 – January 18, 2018. Deliveries occurred in the latter half of 2016, in May and December 2017, and in January 2018. All delivery tickets for the total volume delivered of 15,138 cy were submitted as part of the 2017 Sand Report. 3.8 Table 8. Sand Delivery February 1, 2018 – April 30, 2018 Table 8 presents the volume of mitigation sand delivered during the period from February 1, 2018 – April 30, 2018. Three separate deliveries were made over this period of time. All delivery tickets for the total volume delivered of 8,152 cy were submitted as part of the 2018 Sand Report. 3.9 Table 9. Sand Delivery from May 1, 2018 – December 31, 2019 Table 9 presents the total volume of sand delivered during the period from May 1, 2018 – December 31, 2019. Deliveries occurred between October 2018 to February 2019, and between October 2019 to December 2019. A table of all deliveries for the total volume delivered of 23,335 cy were submitted as part of the 2019 Sand Report. 3.10 Table 10. Sand Delivery from January 1, 2020 – January 15, 2021 Table 10 presents the total volume of sand delivered during the period from January 1, 2020 – January 15, 2021. Deliveries occurred in June, November, and December 2020, and in January 2021. A table of all deliveries for the total volume delivered of 10,656 cy are included in with this report. 3.11 Summary Table 1 shows that sand delivery requirements were met during the first three years of the Project1, with a surplus of sand delivered in the Project’s first two years. At the end of the Project’s fourth winter in 2017, SBPF proposed using an adaptive mitigation approach, whereby the sand template was refilled to 22 cy/lf/yr. (This adaptive mitigation approach was discussed with the Commission during the Project’s March 2018 Annual Review and is also described in the 2017 Sand Report). The UAV survey in June 2020 indicated there was approximately 16,793 cy within the template at the time of the survey. An additional 10,656 cy was delivered before January 15, 2021 bringing the total volume delivered to the sand template to be approximately 27,449 cy which correlates to approximately 29.0 cy/lf. There was an unknown amount of sand from the template used to re-cover exposed geotubes after storms in the fall of 2020 which reduced the actual volume of sand in the template to less than 27,449 cy. 1 As described in the 2017 Sand Report, a small deficit was apparent in spring 2016 after bluff erosion contribution values were recalculated and slightly reduced. 21597/Sconset 5 2020 Annual Sand Delivery Report Epsilon Associates, Inc. 4.0 Annual Aerial Survey of Bluff SBPF contracted AirShark to perform the annual aerial survey of the bluff in June 2020. AirShark is the same firm that previously performed the 2017, 2018 and 2019 aerial surveys. A separate report on the aerial survey is attached (the “Sconset Bluff June 2020 Aerial Survey Report” or the “2020 Survey Report”). 5.0 Changes in Bluff Volume Changes in Bluff Volume are also reported in the Sconset Bluff September 2019 Aerial Survey Report. To understand changes in the bluff volume since Project construction, the results of the 2020 survey were compared to the previous aerial surveys of the Project area that were conducted in September 2019, May 2018, August 2017, and July 2013. The July 2013 survey was conducted about 6 months prior to the installation of the geotextile tubes. 5.1 Changes in Bluff Volume in Adjacent Unprotected Areas The results of the 2020 aerial survey were used to calculate the changes in the bluff volume from September 2019 to June 2020 for those unprotected areas immediately adjacent to the geotextile tube project (Figure 1). During review of the topography generated from this survey and the updated profile views, it was determined that the break in slope between beach and bluff (toe of the slope) generally varies between elevation +10 and +11 feet North American Vertical Datum of 1988 (“NAVD 88”) but is best represented by using elevation +11 feet NAVD 882. This contour was used to provide a constant toe elevation and for consistency across the survey area. Therefore, the change in the bluff volume in these unprotected areas was calculated from the toe of the bluff (elevation +11 feet NAVD 88) to the top of the bluff. ♦ For the north unprotected area, the section of the bluff within 802 feet immediately to the north of the geotextile tubes was used. ♦ For the south unprotected area, the section of bluff within 138 feet immediately to the south of the geotextile tubes was used. Areas farther south than this could not be used because they had coir or jute terraces installed so were not representative of the unprotected bluff. ♦ No areas with a bulge of sand from sand delivery activities at the accessway between 85 and 87 Baxter Road were used in the calculations. In particular, the size of the south unprotected area was reduced in 2019 (i.e. the northern boundary was moved farther south) to account for sand delivery activities and the associated accretion of sand on the bluff face extending farther south in 2019 than in previous years. 2 The conversion from Mean Low Water 92 to NAVD 88 is -1.88 feet. 21597/Sconset 6 2020 Annual Sand Delivery Report Epsilon Associates, Inc. As shown in Tables 3a-c, this analysis indicates that the unprotected areas immediately adjacent to the geotextile tubes eroded at the following rates: ♦ For the most recent year (September 2019 – June 2020), the unprotected areas eroded approximately 4,623 cy (Table 3a). This is equivalent to a distance-weighted average of 6.6 cy/lf/yr. ♦ For the period from geotextile tube installation to the previous reporting period (July 2013 – September 2019), the unprotected areas eroded approximately 41,000 cy (Table 3b). This is equivalent of a distance weighted average of 6.8 cy/lf/yr. As discussed in the 2019 Bluff Survey Report, the apparent accretion in the previous reporting period was within the vertical accuracy range and likely represents no changes. ♦ For the period from geotextile tube installation to present (July 2013 – June 2020), the unprotected areas eroded approximately 45,623 cy (Table 3c). This is equivalent to a distance-weighted average of 6.6 cy/lf/yr. The 2019-2020 estimate of the annual loss of sand from unprotected areas was calculated to be 6.6 cy/lf/yr. This annual loss from September 2019 to June 2020 is consistent with the less energetic winter storm season than in previous years. This loss is greater than the annual loss of the previous reporting period for reasons more thoroughly described in the 2019 Bluff Survey Report. The 2019-2020 estimate is equal to the annualized loss of sand from the geotextile tube installation in 2013 to the June 2020 survey of 6.6 cy/lf/yr. 5.2 Changes in Bluff Volume Above Geotextile Tubes The 2020 aerial survey was also used to calculate the changes in the bluff volume above the geotextile tubes for the period between September 2019 and June 2020. Based on this aerial survey the bluff above the geotubes eroded approximately 267 cy. As described in the 2020 Bluff Survey Report, the accuracy of the survey data was 2.3cm, which applied across this area correlates to approximately ±181 cy, or a distance weighted average of ±0.19 cy/lf.3 With a net loss of 267 cy, and an accuracy range of approximately ±181 cy, this suggests there was some loss of sediment off the bluff face above the template. Reviewing Figure 1, the locations of red are indicative of “gain” and represent maintenance activities at the Project area, specifically rebuilding of the end returns that were washed away during winter storms and general template maintenance to re-cover the geotubes. The template maintenance can also be seen with the creation of the windrows, visible as the relatively north- to-south narrow linear strips of “gain” shown along the westerly edge of the template. 3 The vertical accuracy was used to calculate the sand volume and presented as a volume rather than vertical accuracy based on comments from Greg Berman on the 2019 Annual Report. 21597/Sconset 7 2020 Annual Sand Delivery Report Epsilon Associates, Inc. 6.0 Volume of Sand in Template The volume of sand in the template was calculated by determining the total volume of the template at the time of the 2020 aerial survey and subtracting out the known volume of sand within the geotextile tubes and returns located above beach level. The total volume of sand above the beach level was 28,506 cy and the total volume of sand in the geotubes is 11,713 cy. This yields a sand cover volume in June 2020 of approximately 16,793. This was prior to the delivery of an additional 10,656 cy between June 2020 and January 15, 2021. As described in Section 3.11, this results in an estimate of approximately 27,449 cy of sand available for the 2020-2021 storm season. Calculations were also performed on that portion of the sand template that is located above the fourth tier. Per the Project’s Order of Conditions, the sand on the top of the fourth tier is not counted as mitigation sand. This volume is calculated as approximately 1,974 cubic yards. It is anticipated that sand on top of the sand template, including san don top of the fourth tier, will continue to be pushed down to re-cover the geotextile tubes as needed. Therefore, the volume above the fourth tier will become available through time. 7.0 Volume of Sand Contributed to Littoral System Table 2 presents the approximate volume of sand contributed to the littoral system. The amount contributed is that portion of the sand delivered to the site that is no longer in place in the sand template and therefore is deemed to have been contributed to the littoral system. As has been previously notes, the mitigation sand is delivered to the top of the geotextile tubes and then is pushed over to cover the face of the tubes. On an as-needed basis after erosion events, the sand on top of the geotextile tubes is pushed from the top of the tubes to the face of the tubes whenever needed to re-cover exposed geotextile tubes. Table 2 provides a reasonable estimate of how much mitigation sand has been contributed off the template and into the littoral system over the past seven years, which totals 91,279 cy. For each of the seven sand years (Sand Year 2014, Sand Year 2015, Sand Year 2017, Sand Year 2018, Sand Year 2019, and Sand Year 2020), this estimate was calculated by the following steps shown in Table 2: 1. Beginning with the volume of sand in the sand template at the start of each year (this was estimated in Sand Years 2014 – 2016 and measured in Sand Years 2017 – 2020); 2. Adding the total amount of mitigation sand delivered each year (this is a known amount for each Sand Year); 3. Subtracting the volume of sand in the sand template at the end of each sand year (this was estimated in Sand Years 2014 – 2016 and measured in Sand Years 2017 – 2020); 21597/Sconset 8 2020 Annual Sand Delivery Report Epsilon Associates, Inc. 4. Adding the bluff volume eroded (this is a known total from 2013 through 2017 and was apportioned to Sand Years 2015 and 2016 as described in Section 5.1 of the 2017 Sand Report); 5. Adding the volume of sand contributed during construction (this is known from 2013); and 6. Determining the total volume of sand contributed (both as a total volume and as a rate expressed in cy/lf/yr), including as an average rate from 2013 – 2020. A review of Tables 2 and 3a-c indicates that the sand template has consistently contributed more sand than the unprotected bluff to the north and south of the project: ♦ During the first six years, the unprotected bluff contributed an average of 6.8 cy/lf/yr, while the sand template contributed an average of 13.8 cy/lf/yr. ♦ During the most recent year, the unprotected bluff contributed 6.6 cy/lf/yr, while the sand template contributed 16.9 cy/lf/yr. While it was a calmer storm year, this volume contributed by the template is the result of various Project activities associated with the re-covering of the geotubes post-storm events, rebuilding the end returns, and to push excess sand off the template to remove sand containing topsoil from the template. ♦ Over the nearly seven years from July 2013 – January 2021, the unprotected bluff contributed an average of 6.6 cy/lf/yr compared to 14.3 cy/lf/yr of sand contributed an average off the template (although more than this has been delivered to the site). Tables Line Sand Amounts 12/13-3/31/14 4/1/14-3/31/15 4/1/15-3/31/16 4/1/16-1/31/18 2/1/18-4/30/18 5/15/18-12/31/19 1/1/20-1/15/21 1 Total Volume Delivered for Geotube Construction (See Line 5 in Table 4 and Line 5 in Table 6)12,653 0 2,931 0 0 0 0 2 Total Volume Delivered for Mitigation (see Tables 4-10)23,951 14,429 15,085 15,138 8,152 23,335 10,656 3 Total Volume Delivered to Bluff Face (Not Counted as Mitigation; See Ln 10 in Tbl 4 & Ln 12 in Tbl 6)2,600 0 4,469 0 0 0 0 4 Total Volume Delivered by Truck (Sum Lines 10-12)39,204 14,429 22,485 15,138 8,152 23,335 10,656 5 Required Mitigation Volume (22 cy/lf * Project Length of 852' for 3 tiers, 947' for 4 tiers w/ret.)18,744 18,744 20,834 20,834 20,834 20,834 20,834 Surplus Sand From Prior Year 6 Surplus Delivered in Prior Year (From Line 13 in Preceding Column)0 5,207 3,029 -583 -6,278 -18,960 -16,459 7 Volume on Template at Start of Sand Year 0 5,900 8,500 15,000 17,000 10,200 33,020 8 Countable Surplus Present in Sand Template (Line 6; Not to Exceed Line 7)0 5,207 3,029 -583 -6,278 -18,960 -16,459 9 Volume on Template at End of Sand Year 5,207 8,500 15,000 17,000 10,200 33,020 27,449 Bluff Erosion 10 Net Contribution from Erosion of Bluff Face (pre-veg & during 4th tier const.; see Table 6)0 2,138 2,138 0 0 0 0 11 Adjusted Required Mitigation Volume (Line 5 - Line 8 - Line 10)18,744 11,400 15,667 21,417 27,112 39,794 37,293 12 Total Volume Delivered for Mitigation (Line 2 above)23,951 14,429 15,085 15,138 8,152 23,335 10,656 13 Mitigation Surplus or Deficit (-) ( Line 12 - Line 11)5,207 3,029 -583 -6,278 -18,960 -16,459 -26,637 14 Mitigation Surplus or Deficit (-) to Refill Template to 22 CY/LF 755 -10,634 12,186 6,615 Table 2. Summary of Sand Contribution in Cubic Yards (CY), December 2013 - January 15, 2021 Line Sand Amounts 12/13-3/31/14 4/1/14-3/31/15 4/1/15-3/31/16 4/1/16-5/31/17 6/1/17-5/14/18 5/15/18-12/31/19 1/1/20-1/15/21 1 Volume on Template at Start of Sand Year (Line 7 in Table 1)0 5,900 8,500 15,000 17,000 10,200 33,020 2 Total Volume Delivered for Mitigation (Line 2 in Table 1; Lines 1 through 4 in Table 10)23,951 14,429 15,085 10,550 12,741 23,335 10,656 3 Volume on Template at End of Sand Year (Line 9 in Table 1)5,900 8,500 15,000 17,000 10,200 33,020 27,449 4 Total Volume Contributed from Sand Template (Line 1 + 2 - Line 3)18,051 11,829 8,585 8,550 19,541 515 16,227 5 Total Volume Contributed from Sand Template (cy/lf/yr)21.2 13.9 9.1 8.9 20.3 0.5 16.9 6 Net Contribution from Erosion of Bluff Face (Line 10 in Table 1)0 2,138 2,138 0 0 0 0Construction Contribution 7 Contribution from Construction (Line 8 in Table 4)3,707 0 0 0 0 0 0 Total Annual Sand Contribution 8 Total Volume Contributed 21,758 13,966 10,723 8,550 19,541 515 16,227 9 Total Volume Contributed in cy/lf/yr 25.5 16.4 11.3 8.9 20.3 0.5 16.9 10 Average of Annual Sand Contribution from 2013-2020 (cy/lf/yr)14.3 Template Sand Contribution Bluff Face Contribution Note: 2020 Sand Template was measured in June, 2020. Minor template maintenance was performed during Fall months following storms. Mitigation Volume Summary Sconset Bluff and Baxter Road Geotextile Tube Project, 87-105 Baxter Road, Nantucket, MA Table 1. Summary of Sand Delivery in Cubic Yards (CY), December 2013 - January 2021 Sand Delivery Summary Base Required Mitigation Volume Mitigation Volume Adjustments Page 1 of 5 Line Area Volume Eroded (CY)Length (Feet)Duration (Years) Annual Change (CY/LF/YR) 1 North Unprotected Area 4,418 802 0.75 7.3 2 South Unprotected Area 205 138 0.75 2.0 3 Total Bluff Erosion for Adjacent Unprotected Areas (Distance-weighted average)4,623 6.6 Line Area Volume Eroded (CY)Length (Feet)Duration (Years)Annual Change (CY/LF/YR) 1 North Unprotected Area 35,423 802 6.0 7.4 2 South Unprotected Area 5,577 192 6.0 4.8 3 Total Bluff Erosion for Adjacent Unprotected Areas (Distance-weighted average)41,000 6.8 Line Area Volume Eroded (CY)Length (Feet)Duration (Years) Annual Change (CY/LF/YR) 1 North Unprotected Area 39,841 802 7.0 7.1 2 South Unprotected Area 5,782 192 7.0 4.3 3 Total Bluff Erosion for Adjacent Unprotected Areas (Distance-weighted average)45,623 6.6 Table 3a. Bluff Volume Loss in Unprotected Areas Adjacent to Geotextile Tubes, September 2019 - June 2020 Table 3b. Bluff Volume Loss in Unprotected Areas Adjacent to Geotextile Tubes, July 2013 - September 2019 Table 3c. Bluff Volume Loss in Unprotected Areas Adjacent to Geotextile Tubes, July 2013 - June 2020 Note: As described in the 2019 Bluff Survey Report, the apparent accretion was within the vertical accuracy range and likely represent no net change ; therefore, a value of 0 was used for the 2019 Sand Year to calculate the 7-year annual rate of change. Note: The volumes provided in the above table is a comparison of the unprotected areas from the September 2019 survey to the June 2020 survey Note: As described in the 2019 Bluff Survey Report, the apparent accretion was within the vertical accuracy range and likely represents no change; therefore, a value of 0 was used for the 2019 Sand Year to calcualte the annual rate of change over the previous six years. Page 2 of 5 Line Sand Delivery Amounts Cubic Yard (CY)/ Linear Foot (LF) Project Length (LF)Total CY 1 Inside Tier 2 Geotube 5 852 3,834 2 Inside Tier 3 Geotube 5 835 3,758 3 Bench Behind Tier 2 Geotube 3 852 2,556 4 Bench Behind Tier 3 Geotube 3 835 2,505 5 Total Sand For Geotube Construction (Sum Lines 1-4)12,653 6 Template on Top 22 852 18,744 7 Template at Ends 1,500 8 Sand Contributed to Littoral System During Construction 3,707 9 Total Mitigation Volume (Sum Lines 6-8)23,951 10 Total Volume Delivered to Bluff Face (Not Counted as Mitigation)2,600 11 Total Sand Delivered (Sum Lines 5, 9, and 10)39,204 Line Sand Delivery Amounts Cubic Yard (CY)/ Linear Foot (LF) Project Length (LF)Total CY 1 April 2014 7.1 852 6,015 2 Jan 2015 5.3 852 4,477 3 Feb 2015 4.6 852 3,936 4 Total Sand Delivered (Sum Lines 1-3)14,429 Mitigation Volume Bluff Face Volume Table 4. Sand Delivered December 2013 - March 31, 2014 Geotube Construction Total Sand Delivered Table 5. Sand Delivered April 1, 2014 - March 31, 2015 Mitigation Volume Page 3 of 5 Line Sand Delivery Amounts Cubic Yard (CY)/ Linear Foot (LF) Project Length (LF)Total CY Fourth Tier (3) 120' long x 45' circumference tubes(1) 75' long x 45' circumference tubeTotal of 435 linear feetNorthern Returns (4) 25' long x 30' circumference tubesTotal of 100 linear feet Northern Intermediate Returns(1) 35' long x 30' circumference tube(1) 45' long x 30' circumference tubeTotal of 80 linear feet Southern Returns (1) 65' long x 30' circumference tube(1) 70' long x 30' circumference tube(1) 75' long x 30' circumference tube(1) 80' long x 30' circumference tubeTotal of 290 linear feet Southern Intermediate Returns(1) 35' long x 30' circumference tube(1) 45' long x 30' circumference tubeTotal of 80 linear feet 6 Total Sand For Geotube 4th Tier and Returns Construction (Sum Lines 1-5)2,931 7 November and December 2015 (immediately post-construction)15,085 8 Total Mitigation Volume 15,085 9 Total Volume Delivered to Bluff for Vegetation (April 2015)3,418 10 Total Volume Delivered to Bluff to Fill Gully South of Viewing Area (Nov/Dec 2015)931 11 Total Volume Delivered to Bluff to Fill Gully at Viewing Area (Jan 2016)12012Total Volume Delivered to Bluff Face (Not Counted as Mitigation)4,469 13 Total Sand Delivered (Sum Lines 6, 8, and 12)22,485 Mitigation Volume Bluff Face Volume (Not Counted as Mitigation) Total Sand Delivered 5 2.0 80 160 3 2.0 80 160 4 2.0 290 580 Geotube Construction - 4th Tier and Returns 2 2.0 100 200 1 4.21 435 1831 Table 6. Sand Delivered April 1, 2015 - March 31, 2016 Page 4 of 5 Line Sand Delivery Amounts Cubic Yard (CY)/ Linear Foot (LF) Project Length (LF)Total CY 1 August through December 2016 1,230 2 May 2017 9,320 3 December 2017 2,090 4 January 2018 2,499 5 Total Sand Delivered (Sum Lines 1-4)15,138 Line Sand Delivery Amounts Cubic Yard (CY)/ Linear Foot (LF) Project Length (LF)Total CY 1 February 2018 40 2 March 2018 5,506 3 April 2018 2,606 5 Total Sand Delivered (Sum Lines 1-3)8,152 Line Sand Delivery Amounts Cubic Yard (CY)/ Linear Foot (LF) Project Length (LF)Total CY 1 October 2018 2,204 2 November 2018 3,156 3 January 2019 4,120 4 February 2019 2,683 5 October 2019 5,400 6 November 2019 4,266 7 December 2019 1,506 8 Total Sand Delivered (Sum Lines 1-7)23,335 Line Sand Delivery Amounts Cubic Yard (CY)/ Linear Foot (LF) Project Length (LF)Total CY 1 June 2020 1,350 2 November 2020 1,800 3 December 2020 5,454 4 January 2021 2,052 5 Total Sand Delivered (Sum Lines 1-4)10,656 Table 9. Sand Delivered May 1, 2018 - December 31, 2019 Mitigation Volume Table 7. Sand Delivered April 1, 2016 - January 31, 2018 Mitigation Volume Table 8. Sand Delivered February 1, 2018 - April 30, 2018 Mitigation Volume Table 10. Sand Delivered January 1, 2020 - January 15, 2021 Mitigation Volume Page 5 of 5 Sand Delivery Table Cottage + Castle Ventures, Inc. Sconset Beach Preservation Trust2021-2021 Sand Season Delivery Schedule Truck Delivery Date Loads Per Load CYD's Total CYD's Hours Amount Source Delivery Vendor Delivery Location AH Invoice Number Invoice Date Delivery Qtr 656 6/17/2020 18 18 324 1,800.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 361 7/29/2020 Q2, 2020 97 6/17/2020 7 18 126 675.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 361 7/29/2020 Q2, 2020 500 6/17/2020 19 18 342 1,950.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 361 7/29/2020 Q2, 2020 207 6/17/2020 11 18 198 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 361 7/29/2020 Q2, 2020 473 6/17/2020 20 18 360 2,100.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 361 7/29/2020 Q2, 2020 083 11/20/2021 12 18 216 8.00 1,200.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 2020 473 11/20/2021 11 18 198 7.50 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 2020 097 11/20/2020 11 18 198 7.00 1,050.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 2020 083 11/23/2021 13 18 234 8.50 1,275.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 2020 473 11/23/2020 11 18 198 7.50 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 2020 097 11/23/2020 9 18 162 6.50 975.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 2020 083 11/30/2020 13 18 234 8.50 1,275.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 202047311/30/2020 11 18 198 7.50 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 202009711/30/2020 9 18 162 6.50 975.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 202008312/3/2020 11 18 198 7.50 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 202047312/3/2020 12 18 216 8.00 1,200.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 202009712/3/2021 12 18 216 8.00 1,200.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 202008312/8/2020 9 18 162 6.50 975.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 202047312/8/2020 13 18 234 8.50 1,275.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 202009712/8/2020 11 18 198 7.50 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 202008312/12/2020 14 18 252 9.00 1,350.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 202047312/12/2020 10 18 180 7.50 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 202009712/12/2020 7 18 126 6.00 900.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 399 1/8/2021 Q4, 202047312/14/2020 12 18 216 8.50 1,275.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 202009712/14/2020 9 18 162 6.50 975.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 2020 473 12/16/2020 11 18 198 7.50 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 2020 097 12/16/2020 11 18 198 7.00 1,050.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 2020 473 12/17/2020 10 18 180 7.50 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 2020 097 12/17/2020 9 18 162 7.00 1,050.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 2020 473 12/18/2020 13 18 234 9.00 1,350.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 2020 097 12/18/2020 8 18 144 6.00 900.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 2020 473 12/19/2020 10 18 180 7.50 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 2020 097 12/19/2020 11 18 198 8.00 1,200.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 2020 473 12/21/2020 12 18 216 8.50 1,275.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 2020 097 12/21/2020 9 18 162 7.00 1,050.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 2020 473 12/22/2020 13 18 234 9.00 1,350.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 2020 097 12/22/2020 8 18 144 6.50 975.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 202047312/23/2020 12 18 216 8.50 1,275.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 202009712/23/2020 12 18 216 7.00 1,050.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 402 1/12/2021 Q4, 202047312/28/2020 7 18 126 6.00 900.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q4, 202009712/28/2020 10 18 180 7.50 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q4, 202047312/30/2020 9 18 162 7.00 1,050.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q4, 202009712/30/2020 8 18 144 6.50 975.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q4, 20204731/1/2021 7 18 126 6.00 900.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 20210971/1/2021 9 18 162 7.00 1,050.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 20214731/2/2021 10 18 180 7.50 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 20210971/2/2021 8 18 144 6.50 975.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 20214731/5/2021 9 18 162 7.00 1,050.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 20210971/5/2021 10 18 180 7.50 1,125.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 20214731/6/2021 8 18 144 6.50 975.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 2021 097 1/6/2021 6 18 108 5.50 825.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 2021 473 1/9/2021 9 18 162 7.00 1,050.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 2021 097 1/9/2021 9 18 162 7.00 1,050.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 2021 473 1/11/2021 6 18 108 5.50 825.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 2021 097 1/11/2021 8 18 144 6.50 975.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 2021 473 1/12/2021 8 18 144 6.50 975.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 20210971/12/2021 7 18 126 6.00 900.00 Industrial Road/Purchased Town Sand AH Construction To Bluff 412 2/19/2021 Q1, 2021Total592 10,656 376.00 64,050.00 57