HomeMy WebLinkAboutWoodard and Curran Monthly Update December 12, 2013_201401231106486871TOWN OF NANTUCKET, MASSACHUSETTS
Monthly Update
WOODARD & CURRAN 1 of 4
DECEMBER12 2013
Projects
223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Meet with Town Appraisers
Continue with Surfside Discharge Bed Reload Evaluation
Evaluated options for providing additional aeration capacity for future needs
Requested additional process data to address Town’s concern with anoxic tank
capacity at future conditions
This Month:
Continue to evaluate options for providing additional aeration capacity for future needs
Evaluate additional process data that was requested
Schedule Projected completion date – December 31, 2013
Financial Phase 1 Budget - $348,630 Spent - $ 326,339
Town Action (s) Required:
Work with assessor on FAA site
Provide additional process data to be requested by Woodard & Curran
225139 CWMP Update
Progress Last Month:
Review of Hummock Pond MEP Draft – Modeling Scenarios
Plan for SMAST Public Meeting to present results of Hummock Pond MEP
Draft When Received
SMAST Initiating Model Runs in Nantucket Harbor
Town of Nantucket, Massachusetts
Project Update
December 12,, 2013
WOODARD & CURRAN 2 of 4
Review Draft Stormwater Plan for Nantucket Harbor
Review of Draft Public Outreach Plan for Fall/Winter 2013 with DPW Director
Continue with Report Compilation
Coordinated and participated in a site visit to meter equipment power usage as part of
the Energy Efficiency Study.
Responded to SPWG List of Questions
This Month:
Coordinate and participate in a site visit to meter equipment power usage as part of
the Energy Efficiency Study. Tentatively scheduled for November 20 & 21 or
December 4 & 5.
Compile and Review Draft Report Sections
Develop cost benefit estimates for Energy Efficiency Study
Review of Draft Stormwater Plan for Nantucket Harbor MEP with DPW Director
Schedule Projected completion date – December 2013
Financial Budget - $616,000 Spent: $ 422,351
Town Action (s) Required:
Provide recent electric bill for Surfside WWTF for the Energy Study
226494 Jetties Support Update
Progress Last Month:
All Activities on Hold During Government Shutdown
This Month:
Prepare agenda for meeting with Town, SSA and Hyline to discuss construction
scheduling in late October, early November 2013
Coordinate With ACOE on Design Schedule
Schedule Projected Jetties Reconstruction Bid-Winter 2014
Projected Contractor Bid Award early May 2014.
Financial Budget - $20,000 Spent: $ 18,630
Town Action (s) Required:
None
Town of Nantucket, Massachusetts
Project Update
December 12,, 2013
WOODARD & CURRAN 3 of 4
224428 Miacomet Pond Watershed Study
Progress Last Month:
Kick off meeting with Town
Site Visit to watershed
Continued data collection and compilation
This Month:
Watershed delineation
Additional data collection and compilation, including input from Planning Board
Visit to island to review Planning Board’s documents, interview stakeholders, and
conduct additional verification of locations within watershed
Schedule Projected completion date – March 21, 2014
Financial Engineering Budget - $125,800 Spent - $6,530
Town Action (s) Required:
Provide Woodard & Curran copies of relevant documents
225140 Phase IIB Sewer and Water Main Rehabilitation Project
Progress Last Month:
Sewer and water construction on Academy Lane is complete, trenches to be patched
with binder paving, pending final paving next season. Sewer main construction on Fair
Street is mostly complete, with services to be installed in the first week of December.
Additional sewer main replacement added on Lyon Street per DPW request.
Meetings held with Steamship Authority to discuss schedule, and traffic diversion
plans. Steamship Authority to circulate notice of Broad Street schedule to truck
drivers.
This Month:
Sewer and water construction to be completed on Fair Street. Water construction will
be completed on Westminster Ave.
Project site will be cleaned in preparation for the Christmas holiday at the end of the
month.
Contractor shutdown from December 20, 2013 to January 6, 2014
Schedule Projected completion date – October 2014
Financial Engineering Budget - $1,070,720 Spent - $716,277
Town of Nantucket, Massachusetts
Project Update
December 12,, 2013
WOODARD & CURRAN 4 of 4
Construction Bid - $3,504,911 (including change orders), Spent - $2,171,427
Town Action (s) Required:
Work with Woodard & Curran to coordinate with local businesses and residents during construction
Provide support as needed in field for utility identification
225839 Surfside WWTF Assessment and Upgrades
Progress Last Month:
Revised screenings assessment to develop conceptual layout and cost for complete
headworks replacement.
Provided Corrosion Control Study Report for comment
This Month
Evaluate incorporating vactor dump station into headworks
Develop plan for additional operational assistance to pilot running the plant with one
train of the advanced treatment system off-line.
Schedule Projected completion date – December 2014
Financial Budget - $110,000 Spent -$ 90,400
Town Action (s) Required: None
Review and provided comments on the Corrosion Control Study Report
What to look for this month:
Construction on Phase II B Water and Sewer Replacement on Westminster St. and Fair St.