HomeMy WebLinkAboutProspect St Water Main Project Weekly SchedulePROSPECT ST. AREA WATERMAIN WORK SCHEDULE **SUBJECT TO CHANGE** ~WEEKLY SCHEDULE RUNS MONDAY – THURSDAY~ START DATE: 2/6/17  2/6/17 – Start at intersection of Milk St. & Mt. Vernon St., work at this location for 2 days  Continue South on Mt. Vernon St. for remainder of week  2/13/17 – Start on Mt. Vernon St. (roughly around house #18)  Continue South to Hummock Pond Rd. for remainder of week  2/15/17 – Start at intersection of Hummock Pond Rd. & Joy St.  Continue North on Joy St. for remainder of week  2/20/17 – Start at intersection of Mill Hill Ln. & New Mill St.  Continue North on New Mill St. for remainder of week  2/27/17 – Start at intersection of Milk St. & Mt. Vernon St.  Continue East on Milk St. to Prospect St. for remainder of week  3/6/17 – Start at intersection of Milk St. & Prospect St.  Continue East to intersection of Mill St. & Prospect St. for remainder of week  3/13/17 – CREW #1 – Services on Mt. Vernon St. for the week CREW #2 – Start at intersection of Mill St. & Prospect St. – Continue East on Prospect St. to intersection of South Mill St. & Prospect St. for remainder of week  3/20/17 – CREW #1 – Services on Joy St. and New Mill St. for the week CREW #2 – Start at intersection of South Mill St. & Prospect St. – Continue East to intersection of Prospect St. & Cemetery entrance for remainder of week  3/27/17 – CREW #1 – Paving prep on Milk St. and Mt. Vernon St. CREW #2 – Start at intersection of Prospect St. & Cemetery entrance, continue to intersection of Prospect St. & Atlantic Ave. for remainder of week  4/3/17 – CREW #1 – Services at intersection of Milk St. & Prospect St. – Continue East for remainder of the week CREW #2 – Start at intersection of Prospect St. & Atlantic Ave. – Continue West on Atlantic Ave. to Pleasant St. for remainder of week  4/10/17 – CREW #1 & #2 – Prospect St. – Services and paving prep  Continue East for remainder of the week  4/17/17 – CREW #1 & #2 – Start at intersection of Sparks Ave. & Surfside Rd.  Continue South on Surfside Rd. for remainder of the week  4/24/17 – Continue services, paving, and clean up