HomeMy WebLinkAboutProspect St Water Main Project Weekly SchedulePROSPECT ST. AREA WATERMAIN
WORK SCHEDULE
**SUBJECT TO CHANGE**
~WEEKLY SCHEDULE RUNS MONDAY – THURSDAY~
START DATE: 2/6/17
2/6/17 – Start at intersection of Milk St. & Mt. Vernon St., work at this location for 2 days
Continue South on Mt. Vernon St. for remainder of week
2/13/17 – Start on Mt. Vernon St. (roughly around house #18)
Continue South to Hummock Pond Rd. for remainder of week
2/15/17 – Start at intersection of Hummock Pond Rd. & Joy St.
Continue North on Joy St. for remainder of week
2/20/17 – Start at intersection of Mill Hill Ln. & New Mill St.
Continue North on New Mill St. for remainder of week
2/27/17 – Start at intersection of Milk St. & Mt. Vernon St.
Continue East on Milk St. to Prospect St. for remainder of week
3/6/17 – Start at intersection of Milk St. & Prospect St.
Continue East to intersection of Mill St. & Prospect St. for remainder of week
3/13/17 – CREW #1 – Services on Mt. Vernon St. for the week
CREW #2 – Start at intersection of Mill St. & Prospect St. – Continue East on Prospect St.
to intersection of South Mill St. & Prospect St. for remainder of week
3/20/17 – CREW #1 – Services on Joy St. and New Mill St. for the week
CREW #2 – Start at intersection of South Mill St. & Prospect St. – Continue East to
intersection of Prospect St. & Cemetery entrance for remainder of week
3/27/17 – CREW #1 – Paving prep on Milk St. and Mt. Vernon St.
CREW #2 – Start at intersection of Prospect St. & Cemetery entrance, continue to
intersection of Prospect St. & Atlantic Ave. for remainder of week
4/3/17 – CREW #1 – Services at intersection of Milk St. & Prospect St. – Continue East for
remainder of the week
CREW #2 – Start at intersection of Prospect St. & Atlantic Ave. – Continue West on
Atlantic Ave. to Pleasant St. for remainder of week
4/10/17 – CREW #1 & #2 – Prospect St. – Services and paving prep
Continue East for remainder of the week
4/17/17 – CREW #1 & #2 – Start at intersection of Sparks Ave. & Surfside Rd.
Continue South on Surfside Rd. for remainder of the week
4/24/17 – Continue services, paving, and clean up