HomeMy WebLinkAboutWoodard and Curran Monthly Update September 17, 2013_201401230917015888TOWN OF NANTUCKET, MASSACHUSETTS
Monthly Update
WOODARD & CURRAN 1 of 4
SEPTEMBER 17, 2013
Projects
223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Began cost estimating for upgrades needed for Surfside WWTF
Submitted Scope of Work to MassDEP for re-rating Surfside infiltration bed effluent
loading
Obtained and reviewed Surfside beds monitoring well data
Final review of PAL report on FAA site
Continue Surfside WWTF capacity analysis
This Month:
Begin Surfside infiltration bed loading evaluation include site visit by hydrogeologist
Contract FAA site assessor to support town on land negotiations
Start FAA appraisal process
Schedule Projected completion date – December 31, 2013
Financial Phase 1 Budget - $348,630 Spent - $ 287,082.02
Town Action (s) Required:
Work with assessor on FAA site
225139 CWMP Update
Progress Last Month:
Continue with CWMP Update report writing
Continue coordination with Board of Health
Septage Management Plan – Pumping Program
Tight Tank Policy
ACO Process – Expansion potential
Town of Nantucket, Massachusetts
Project Update
September 17, 2013
WOODARD & CURRAN 2 of 4
Continue coordination with Natural Resources Department
Fertilizer
Annual Water Quality Program
Review TMDL plans
Hummock Pond MEP not yet completed
Additional Model Run Scenarios identified
Evaluate On-Site, I/A and WWTF options
Continue WWTF Energy Study
Amendment No. 1 approved – Public Outreach
This Month:
Hummock Pond MEP Draft – Modeling
Finalize Model Runs
Review TSD unconnected properties
Draft Stormwater Plan for Nantucket Harbor MEP
Estimate to Complete based on outstanding items
Draft Public Outreach Plan for Fall 2013
Manage FAA Appraisal process
Stormwater Master Plan CY2014 PEF
Schedule Projected completion date – December 2013
Financial Budget - $616,000 Spent: $ 345,002.41
Town Action (s) Required:
None at this time
226494 Jetties Support Update
Progress Last Month:
Continue with ACOE Coordination
Survey completion due early fall 2013
Continue coordination with Dave Fronzuto for local conditions
This Month:
Monitor ACOE Progress
Review survey results
Draft Schedule for completion
Town of Nantucket, Massachusetts
Project Update
September 17, 2013
WOODARD & CURRAN 3 of 4
Schedule Projected completion date – fall 2014 (Jetties reconstruction. W&C to continue oversight for
project duration))
Financial Budget - $20,000 Spent: $ 18,586.06
Town Action (s) Required:
None at this time
225140 Phase IIB Sewer and Water Main Rehabilitation Project
Progress Last Month:
Schedule meetings for September with impacted businesses, Steamship Authority and
various Town Administration entities.
Finalize construction schedule
This Month:
Construction Kickoff meeting was held September 11, 2013.
CC construction began mobilization on September 16, 2013. Construction to begin on
September 23, 2013 on Ash Lane and Ash Street.
W&C and the Town to conduct outreach to local businesses and residents,
communicate anticipated construction schedule.
Schedule Projected completion date – October 2014
Financial Engineering Budget - $1,118,320 Spent - $553,325.05
Construction Bid - $3,749,396.31 Spent - $ 1,546,523.24
Town Action (s) Required:
Process Amendment No. 3 for additional resident representation due to increase in construction
time.
Work with Woodard & Curran to coordinate with local businesses and residents during construction
Provide support as needed in field for utility identification.
225839 Surfside WWTF Assessment and Upgrades
Progress Last Month:
Corrosion Control – We have received the subconsultants draft report and we have
sent back with comments and questions.
Town of Nantucket, Massachusetts
Project Update
September 17, 2013
WOODARD & CURRAN 4 of 4
Headworks Screen – We have received quotes from vendors and layouts for us to
assess which screen and setup would be the best recommendation.
Vactor Unloading area – we have a concept laid out the design.
This Month:
Corrosion Control – We will be preparing the recommendation and probable estimated
costs for design and construction over the next 3 weeks.
Headworks Screen - Over the next 4 weeks we will be finalizing the probable cost
estimates for design and construction. We will need a structure around this equipment
therefore getting the costs together and a plan will take a little more time that is why
the 4 weeks.
Odor Control System – We will have the proposed plan and probable estimated costs
for design and construction in the next 4 weeks.
Vactor Unloading area – We will be preparing probable design and construction cost
estimates.
Schedule Projected completion date – December 2014
Financial Budget - $110,000 Spent - $61,081.01
Town Action (s) Required:
None for this month
What to look for this month:
Construction on Phase II B Water and Sewer Replacement to begin September 23, 2013