HomeMy WebLinkAboutWoodard and Curran Monthly Update November 6, 2013_201401230917008701TOWN OF NANTUCKET, MASSACHUSETTS
Monthly Update
WOODARD & CURRAN 1 of 4
NOVEMBER 6, 2013
Projects
223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Met with Town Appraisers
Continued with Surfside Discharge Bed Reload Evaluation
Revised flow and load projections to include the Miacomet needs area flow and loads
and revised the Surfside WWTF Capacity Analysis
This Month:
Revise the Surfside WWTF Capacity Analysis
Evaluate options for providing additional aeration capacity for future needs
Request and evaluate additional process data to address Town’s concern with anoxic
tank capacity at future conditions
Schedule Projected completion date – December 31, 2013
Financial Phase 1 Budget - $348,630 Spent - $ 309,216
Town Action (s) Required:
Work with assessor on FAA site
Provide additional process data to be requested by Woodard & Curran
225139 CWMP Update
Progress Last Month:
Reviewed Hummock Pond MEP Draft – Modeling Scenarios
Plan for SMAST Public Meeting to present results of Hummock Pond MEP
Draft When Received
SMAST Initiated Model Runs in Nantucket Harbor
Town of Nantucket, Massachusetts
Project Update
November 6, 2013
WOODARD & CURRAN 2 of 4
Reviewed Draft Stormwater Plan for Nantucket Harbor
Reviewed Draft Public Outreach Plan for Fall/Winter 2013 with DPW Director
Continued with Report Compilation
Responded to SPWG List of Questions
This Month:
Coordinate and participate in a site visit to meter equipment power usage as part of
the Energy Efficiency Study. Tentatively scheduled for November 20 & 21 or
December 4 & 5.
Compile and Review Draft Report Sections
Review of Draft Stormwater Plan for Nantucket Harbor MEP with DPW Director
Schedule Projected completion date – December 2013
Financial Budget - $616,000 Spent: $ 381,920
Town Action (s) Required:
None
226494 Jetties Support Update
Progress Last Month:
All Activities on Hold During Government Shutdown
This Month:
Prepare agenda for meeting with Town, SSA and Hyline to discuss construction
scheduling in late October, early November 2013
Coordinate With ACOE on Design Schedule
Schedule Projected Jetties Reconstruction Bid-Winter 2014
Projected Contractor Bid Award early May 2014.
Financial Budget - $20,000 Spent: $ 18,614
Town Action (s) Required:
None
Town of Nantucket, Massachusetts
Project Update
November 6, 2013
WOODARD & CURRAN 3 of 4
224428 Miacomet Pond Watershed Study
Progress Last Month:
Internal Kick off meeting for project team
Data Collection and Compilation
This Month:
Kick off meeting with Town
Additional data collection and compilation
Watershed delineation
Field investigations
Schedule Projected completion date – March 21, 2014
Financial Engineering Budget - $125,800 Spent - $1,279
Town Action (s) Required:
Provide Woodard & Curran copies of relevant documents
225140 Phase IIB Sewer and Water Main Rehabilitation Project
Progress Last Month:
Worked to continue on Ash Lane through 10/7, and moved onto Academy Lane and
Gay Street for sewer and water replacement during week of 10/14.
Met with Steam Ship Authority held on 10/30/13 to coordinate truck deliveries and
minimize conflicts during construction on Broad Street. Woodard & Curran to work
with Steamship Authority to issue notices informing of upcoming construction.
This Month:
Sewer and water construction is ongoing on Academy Lane, and will move on to
Westminster Lane.
Water and sewer construction to begin on Fair Street week of 11/11/13.
Schedule Projected completion date – October 2014
Financial Engineering Budget - $921,700 Spent - $660,529
Construction Bid - $3,504,911 (including change orders), Spent - $1,609,817
Town Action (s) Required:
Work with Woodard & Curran to coordinate with local businesses and residents during construction
Provide support as needed in field for utility identification
Town of Nantucket, Massachusetts
Project Update
November 6, 2013
WOODARD & CURRAN 4 of 4
225839 Surfside WWTF Assessment and Upgrades
Progress Last Month:
Attended meeting with DPW Director and the Surfside WWTF Chief Operator to review
the recommendations and probable costs for the Corrosion Control, Headworks
Screen, Odor Control System and Vactor unloading area.
This Month
Revise screenings assessment to develop conceptual layout and cost for complete
headworks replacement.
Evaluate incorporating vactor dump station into headworks
Provide Corrosion Control Study Report for comment
Develop plan for additional operational assistance to pilot running the plant with one
train of the advanced treatment system off-line.
Schedule Projected completion date – December 2014
Financial Budget - $110,000 Spent -$ 81,100
Town Action (s) Required: None
What to look for this month:
Construction on Phase II B Water and Sewer Replacement on Westminster St. and Fair St.