Loading...
HomeMy WebLinkAboutBudget Update November 1, 2017The VERTEX Companies, Inc. Nantucket Fire Headquarters Project Budget History Description Budget June ’16 March ’17 November '17 Construction Budget $14,433,125 $15,707,000 $15,678,000 <--actual low bid number received 11/02/17 Designer Fees $976,000 $976,000 $976,000 $976,000 OPM Fees $458,860 $458,860 $458,860 $458,860 Other Soft Costs (FFE, etc.)$440,140 $440,140 $440,140 $508,362 <--escalated 10% a year for 1.5 years Soft Cost Contingency (2%)$37,500 $37,500 $37,500 $46,041 <--increased w/ inc. soft costs Const. Contingency (4.5%)$654,375 $654,375 $654,375 $0 Total Project Budget $17,000,000 $18,273,875 $18,244,875 $1,989,263 Less appropriation ($17,000,000)($17,000,000)($17,000,000) Plus paving & landscaping Included $750,000 Plus paving $700,000 Plus fencing $220,400 Plus add’l Design Fees Included $243,500 $243,500 Plus add'l OPM Fees $115,330 Shortfall $1,273,875 $2,238,375 ($13,731,507) Note: 1. The March '17 Construction Budget number was based on an estimate to build the project "modularly". The June '16 number was Maron's bid to build it conventionally. The October '17 figure is based on an escalated version of the June '16 bid figure. 3. Paving estimate uses 87,700 sf of paving that equates to ______ tons of asphalt installed at the Town's current unit price rate of _____ per ton, escalated 8% for next season's contract. 2. Fencing estimate is based on 300 lf of decorative fence with 36lf of sliging gate and 3.5 lf of man-gate; 1031 lf of chainlink fence with 21 lf of gates and 5' of man-gate.