HomeMy WebLinkAboutOIH Cost estimate DG Jones report Jan 2017Our Island Nursing Home
Nantucket, MA
(SD COST ESTIMATE)
Prepared for:
SMRT.
Andover, MA
Prepared by:
D G Jones International, Inc.
3 Baldwin Green Common, #202
Woburn, MA 01801
email : boston@dgjonesboston.com
Tel: 781-932-3131
Fax: 781-932-3199
January 5, 2017
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Summary, CM Type Contract
January 5, 2016
SUMMARY
Gross Floor Area (sf)34,611
Elements ($)$/sf %
A Substructure 1,293,580 37.37 7.81%
A10 Foundations 1,293,580 37.37 7.81%
A20 Basement Construction 0 0.00 0.00%
B Shell 3,710,902 107.22 22.42%
B10 Superstructure 1,241,979 35.88 7.50%
B20 Exterior Enclosure 1,344,853 38.86 8.12%
B30 Roofing 1,124,071 32.48 6.79%
C Interiors 2,605,306 75.27 15.74%
C10 Interior Construction 1,348,072 38.95 8.14%
C20 Stairs 0 0.00 0.00%
C30 Interior Finishes 1,257,234 36.32 7.59%
D Services 5,555,832 160.52 33.56%
D10 Conveying Systems 0 0.00 0.00%
D20 Plumbing 1,733,424 50.08 10.47%
D30 Heating, Ventilating and Air Conditioning (HVAC) 2,105,625 60.84 12.72%
D40 Fire Protection Systems 266,982 7.71 1.61%
D 50 Electrical Systems 1,449,800 41.89 8.76%
E Equipment and Furnishings 882,843 25.51 5.33%
E10 Equipment 420,385 12.15 2.54%
E 20 Furnishings 462,458 13.36 2.79%
F Special Construction and Demolition 0 0.00 0.00%
F10 Special Construction 0 0.00 0.00%
F20 Selective Demolition 0 0.00 0.00%
G Building Sitework 2,505,441 72.39 15.14%
G10 Site Preparation 483,500 13.97 2.92%
G20 Site Improvements 1,106,820 31.98 6.69%
G30 Site Civil/Mechanical Utilities 648,010 18.72 3.91%
G40 Site Electrical Utilities 267,110 7.72 1.61%
G90 Other Site Construction 0 0.00 0.00%
Sub Total Construction 16,553,903 478.28 100.00%
General Requirements/General Conditions 1,953,350 56.44
Bonds 0.90%166,565 4.81
Insurance 1.10%205,412 5.93
Permit Fee Excluded
Sales Tax Excluded
Escalation to mid-point of construction 4Q2018 7.12%1,344,201 38.84
Design Contingency 7.00%1,415,640 40.90
CM Fee 3.00%649,172 18.76
CM Contingency 3.00%579,412 16.74
Construction Contingency By Owner
LEED Documentation 50,000 1.44
Total Construction Cost 22,917,656 662.15
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 1 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Summary, GC Type Contract
January 5, 2016
SUMMARY
Gross Floor Area (sf)34,611
Elements ($)$/sf %
A Substructure 1,293,580 37.37 7.81%
A10 Foundations 1,293,580 37.37 7.81%
A20 Basement Construction 0 0.00 0.00%
B Shell 3,710,902 107.22 22.42%
B10 Superstructure 1,241,979 35.88 7.50%
B20 Exterior Enclosure 1,344,853 38.86 8.12%
B30 Roofing 1,124,071 32.48 6.79%
C Interiors 2,605,306 75.27 15.74%
C10 Interior Construction 1,348,072 38.95 8.14%
C20 Stairs 0 0.00 0.00%
C30 Interior Finishes 1,257,234 36.32 7.59%
D Services 5,555,832 160.52 33.56%
D10 Conveying Systems 0 0.00 0.00%
D20 Plumbing 1,733,424 50.08 10.47%
D30 Heating, Ventilating and Air Conditioning (HVAC) 2,105,625 60.84 12.72%
D40 Fire Protection Systems 266,982 7.71 1.61%
D 50 Electrical Systems 1,449,800 41.89 8.76%
E Equipment and Furnishings 882,843 25.51 5.33%
E10 Equipment 420,385 12.15 2.54%
E 20 Furnishings 462,458 13.36 2.79%
F Special Construction and Demolition 0 0.00 0.00%
F10 Special Construction 0 0.00 0.00%
F20 Selective Demolition 0 0.00 0.00%
G Building Sitework 2,505,441 72.39 15.14%
G10 Site Preparation 483,500 13.97 2.92%
G20 Site Improvements 1,106,820 31.98 6.69%
G30 Site Civil/Mechanical Utilities 648,010 18.72 3.91%
G40 Site Electrical Utilities 267,110 7.72 1.61%
G90 Other Site Construction 0 0.00 0.00%
Sub Total Construction 16,553,903 478.28 100.00%
General Requirements/General Conditions 1,655,390 47.83
Bonds 0.90%163,884 4.74
Insurance 1.10%202,105 5.84
Permit Fee Excluded
Sales Tax Excluded
Escalation to mid-point of construction 4Q2018 7.12%1,322,560 38.21
Design Contingency 7.00%1,392,849 40.24
GC Fee 3.00%638,721 18.45
Construction Contingency By Owner
LEED Documentation 50,000 1.44
Total Construction Cost 21,979,411 635.04
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 2 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Notes
January 5, 2016
Notes
1. Brief project description:-
- New Single story Nursing Home building complete with MEP and Sitework/Site Utilities.
2. The estimate is based on the following:-
- Union wage rates.
- CM type project.
- Receipt of 3# bona fide bids for each sub-contract.
- Single contract.
- Bid date of 1Q2018.
-Priced in "Today's Dollars" assumes construction start of 1Q2018
- Construction period.
New Construction - 18 Month
3. The gross floor areas are based on the following:-
- Measurement is taken to the outside face of the exterior wall, measured through all
stair wells, elevator shafts and ducts.
4. Story heights:-
- Varies.
5. General Requirements/General Conditions ia calculated later in this document.
6. Special Conditions for this project are included with General Requirements/General Conditions.
7. Escalation is based on the following:-
- Escalation is taken at 4% per annum to the mid-point of construction
New Construction - 4Q2018
8. Estimating Contingency is an allowance for future design modifications/additions, which alter the
cost of the building as the design progresses, this percentage reduces as the design develops. It
is based on a percentage of the sum of Sub-Total Construction, General Requirements/
Special Conditions and Escalation. For this level of estimate the following has been included:-
- 7.00%
9. Construction Contingency is an allowance for scope/design modifications made by the owner
during construction and also for any unforeseen circumstances. It is based on a percentage of
the sum of Sub-Total Construction, General Requirements/Special Conditions, Escalation
and Design Contingency. The following has been included:-
- By Owner
2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 3 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Notes
January 5, 2016
Notes (Cont'd)
10. This estimate has been prepared from the following design information:-
- Drawing Dated 12/15/2016.
- Design Narrative Dated 12/16/2016.
- Emails, meeting and telephone conversations with SMRT
11. The estimate includes the following:-
- See estimate.
12. The estimate excludes the following:-
- Utility company backcharges.
- Building permit fees.
- Design consultants fees.
- Loose furniture, fittings and equipment.
- Fire Pump.
- Sales Tax.
- Hazardous Material Removal.
-Communication Wiring and Devices - By Others.
-Security Wiring and Devices - By Others.
-Audio Visual (Wiring and Equipment) - By Others.
- Fixed furniture, fittings and equipment (except as detailed in the estimate).
- Decontamination of soil
- Removal of Contaminated Soil Material
-Casework in Patient Rooms - Excluded (FF&E)
-Exterior Transformer Excluded - By Utility Company
- Upgrading existing Sherburne Commons sanitary main
13. Allowances:-
- See Estimate.
14. Assumptions:-
- None.
15. Estimates by other firms:-
- See Estimate.
2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 4 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Notes
January 5, 2016
Notes (Cont'd)
16. Common abbreviations included in this estimate:-
- cd = construction documents.
- cf = cubic foot.
- cte = connect to existing.
- cy = cubic yard.
- dd = design development.
- ea = each.
- eo = extra over
- extg = existing
- flr = floor.
- gfa = gross floor area
- lb = pound.
- lf = linear foot.
- ls = lump sum.
- ly = linear yard.
mg = make good.
- opg = opening.
- rsr = riser.
- sd = schematic design.
- sf = square foot.
- sy = square yard.
- tn = ton.
17. Builders work in connection (BWIC) with conveying, mechanical and electrical systems
includes the following:-
- Drilling and coring.
- Chasing.
- Cutting and patching.
2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 5 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
Summary
A Substructure
A10 Foundations 1,293,580
A20 Basement Construction 0
B Shell
B10 Superstructure 1,241,979
B20 Exterior Enclosure 1,344,853
B30 Roofing 1,124,071
C Interiors
C10 Interior Construction 1,348,072
C20 Stairs 0
C30 Interior Finishes 1,257,234
D Services
D10 Conveying Systems 0
D20 Plumbing 1,733,424
D30 Heating, Ventilating and Air Conditioning (HVAC) 2,105,625
D40 Fire Protection Systems 266,982
D 50 Electrical Systems 1,449,800
E Equipment and Furnishings
E10 Equipment 420,385
E 20 Furnishings 462,458
F Special Construction and Demolition
F10 Special Construction 0
F20 Selective Demolition
G Building Sitework
G10 Site Preparation 483,500
G20 Site Improvements 1,106,820
G30 Site Civil/Mechanical Utilities 648,010
G40 Site Electrical Utilities 267,110
Sub-Total Building 16,553,903
A10 Foundations
Excavation
Excavate & stockpile material on site for:-
Foundation Footing: -
Typical perimeter frost wall continuous footing - 2' 0" x 12" deep 1,584 cy 12.29 19,464
Interior grade beam - 2' 0" x 1' 0" deep 500 cy 12.29 6,144
Column Footing, allow - 5'-0" x 5'-0" x 1' 0" Deep 1,615 cy 12.29 19,845
EO for rock, allow 5% of excavated material 185 cy 55.30 10,230
Water removal during excavation work 1 ls 2,792.65 2,793
Temporary support (allow)Not Required
Filling around foundations with excavated material - allow 3,314 cy 9.83 32,577
Stored excavated material on site for re-use Remove excavated material off site
Remove unsuitable material off site 385 cy 24.58 9,464
Imported structural fill Not Required
Perimeter drainage system 1,584 lf 18.43 29,196 129,713
Cast-in-Place Concrete
Foundation Footing: -
Typical perimeter frost wall continuous footing - 2' 0" x 12" deep 117 cy 202.75 23,722
Interior grade beam - 2' 0" x 1' 0" deep 37 cy 202.75 7,502
Foundation Wall: -
Perimeter Frost Wall - 10" thick 146 cy 202.75 29,602
Slab edge detail 1,584 lf 24.58 38,928
Column Footing, allow - 5'-0" x 5'-0" x 1' 0" Deep 231 cy 206.44 47,687
Pier/Pilaster - 22" x 22" x 36" 290 cy 206.44 59,867 207,308
Formwork
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 6 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
Foundation Footing: -
Typical perimeter frost wall continuous footing - 2' 0" x 12" deep 3,168 sf 12.29 38,928
Interior grade beam - 2' 0" x 1' 0" deep 1,000 sf 12.29 12,288
Foundation Wall: -
Typical perimeter frost wall continuous footing - 2' 0" x 12" deep 9,504 sf 13.82 131,383
Column Footing, allow - 5'-0" x 5'-0" x 1' 0" Deep 1,538 sf 13.21 20,316
Pier/Pilaster - 22" x 22" x 36" 1,689 sf 13.21 22,311 225,227
Concrete Reinforcement (Re-bar)
Foundation Footing: -
Typical perimeter frost wall continuous footing - 2' 0" x 12" deep 13,493 lb 1.54 20,725
Interior grade beam - 2' 0" x 1' 0" deep 4,259 lb 1.54 6,542
Foundation Wall: -
Typical perimeter frost wall continuous footing - 2' 0" x 12" deep 16,069 lb 1.54 24,682
Column Footing, allow - 5'-0" x 5'-0" x 1' 0" Deep 28,843 lb 1.54 44,303
Pier/Pilaster - 22" x 22" x 36" 36,308 lb 1.54 55,769 152,021
Other Items
Dampproofing to exterior face for foundation wall 4,752 sf 4.30 20,437
Rigid insulation to face of foundation/retaining wall 4,752 sf 3.07 14,598 35,036
A1030 Slab-on-Grade
Excavation
Excavate & stockpile material on site for
4" concrete slab 1,361 cy 12.29 16,724
EO for rock, allow 5% of excavated material 68 cy 55.30 3,760
Water removal during excavation work 1 ls 1,027.52 1,028
Temporary support (allow)Not Required
Filling around foundations with excavated material - allow 233 cy 9.83 2,290
Stored excavated material on site for re-use Remove excavated material off site
Remove material off site 1,196 cy 24.58 29,393
Imported structural fill Not Required
Compacted sand/gravel below sog 833 cy 43.01 35,826 89,021
Cast-in-Place Concrete
4" concrete slab 427 cy 184.32 78,705
Saw cut control joint (1.25" deep) 34,611 sf 0.61 21,265
Finish concrete slab 34,611 sf 0.92 31,897 131,867
Formwork
4" concrete slab 528 sf 7.99 4,217 4,217
Concrete Reinforcement (WWF - Welded Wire Fabric)
4" concrete slab 34,611 sf 1.41 48,909 48,909
Other Items
Moisture Mitigation System
Carpet Tile, solution dyed premium nylon 23,967 sf 4.92 117,803
Porcelain Tile - 12" x 24" (Bathing) 420 sf Not Required
Porcelain Tile - 12" x 24" (Staff/Visitor Toilet) 348 sf Not Required
Porcelain Tile, small-module (Resident Bath) 2,560 sf Not Required
Sheet Vinyl, heat-weld seams 2,697 sf 4.92 13,256
Sheet Vinyl, slip-retardant, heat-welded seams (Kitchen/Med Room/Pantry) 1,345 sf 4.92 6,611
Sheet Vinyl, wood-look, heat-weld seams (Salon) 152 sf 4.92 747
Walk-off Mat Carpet Tile 108 sf Not Required
Vapor barrier under sog (15mil) 34,611 sf 1.04 36,150
Rigid insulation under sog (R-5) 34,611 sf 2.76 95,692 270,260
A10 Foundations Total 1,293,580 1,293,580
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 7 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
A20 Basement Construction
Included with Foundations
Basement Construction - By Others NIC
A20 Basement Construction Total 0 0
B10 Superstructure
B1010 Structural Framing
Structural Steel members
Floor Framing Not Required
Light gage steel roof trusses 34,611 sf 18.43 637,950
Structural steel - allow 3 lb's/sf 52 ton 4,546.56 236,421
Allow for structural steel connections, fittings, etc. allow 7.5% of structural steel 4 ton 4,546.56 18,186
Moment connection Not Required
Base plate 77 ea 430.08 33,079
EO for shop paint and field touch-up paint after steel installation 1 ls 7,129.03 7,129 932,765
B1020 Floor and Roof Decking
Suspended floor deck Not Required
Roof decks
Type R3 - 1 1/2" deep, type WR, 18 ga galvanized steel roof deck 9,636 sf 3.99 38,482
Type R3 - 1 1/2" deep, type WR, 18 ga galvanized steel roof deck (pitched 8:12) 32,687 sf 3.99 130,539
Type R3 - 1 1/2" deep, type WR, 18 ga galvanized steel roof deck at canopy 1,300 sf 3.99 5,192 174,213
Miscellaneous Structural Items
Moisture mitigation system to floor slabs Included with finishes
Loose steel to elevator hoistway, allow Not Required
AESS steel Not Required
Steel to Patient Lifts 40 ea 1,136.64 45,466
Steel supports for mechanical equipment 3 ton 4,546.56 13,640
Miscellaneous steel frames, assemblies, etc 5 ton 4,546.56 22,733
Relieving angles at exterior wall Not Required
Lintels over windows Not Required 81,838
B1030 Structural Fireproofing
Structural Fireproofing
Fire protection (allow, gfa)Not Required
Intumescent paint to exposed steel, allow Not Required
Firestopping (allow, gfa) 34,611 sf 1.54 53,162 53,162
B10 Superstructure Total 1,241,979 1,241,979
B20 Exterior Enclosure
B2010 Exterior Wall
Exterior wall backup system
Metal stud back-up exterior wall 19,405 sf 7.99 154,992
5/8" densglass sheathing 19,405 sf 2.27 44,113
Air/vapor barrier 19,405 sf 5.22 101,341
3" rigid insulation 19,405 sf 3.50 67,958
Batt insulation 19,405 sf 1.54 29,806
5/8" GWB 19,405 sf 2.89 56,035
Exterior Finish
Masonry Veneer Base Not Required
Wood Shingle Siding - Natural White cedar shakes 19,405 sf 18.43 357,673
Exterior Wall System - Canopy Structure 157 sf 37.42 5,874 817,792
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 8 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
Roof Screen
Mechanical equipment roof screen system Not Required
B2020 Exterior Window
Storefront System 483 sf 98.30 47,481
Exterior Window System
Exterior window system - 3' 0" x 6' 0" high 127 ea 2,211.84 280,904
Louver System
Exterior Louver System - 2' 6" x 2' 6" high 4 ea 614.40 2,458
Exterior Louver System - 2' 6" x 3' 6" high 8 ea 913.92 7,311
Exterior Sun Shade system, allow Not Required 338,153
B2030 Exterior Doors
Exterior doors complete w/frames and hardware
Automatic sliding entry systems - 8' 2" x 7' 8" high 1 ea 13,778.84 13,779
Exterior SL door - 3' 0" x 7' 0" high 4 ea 2,451.46 9,806
Exterior Glazed DL door - 6' 0" x 7' 0" high 6 ea 7,741.44 46,449
Exterior Glazed SL door - 3' 0" x 7' 0" high 4 ea 4,515.84 18,063 88,097
General Items
Allow for:-
Staging/Scaffolding 22,269 sf Included w/rates above
Exterior wall flashings 3,265 lf 11.06 36,108
Exterior wall caulking and sealant 3,265 lf 3.26 10,632
Exterior wall wood blocking 9,795 lf 4.30 42,126
Expansion, control & isolation joints 216 lf 55.30 11,944 100,810
B20 Exterior Enclosure Total 1,344,853 1,344,853
B30 Roofing
B3000 Roof Coverings
Asphalt Shingles Roofing (Sloped 8:12)
Asphalt Shingles Roofing 32,687 sf 6.76 220,912
Self-adhering rubberized asphalt membrane shingle underlayment 32,687 sf 5.22 170,705
Ice & water shielding 6,056 sf 9.83 59,533
¾" plywood sheathing 32,687 sf 2.40 78,323
R-30ci polyisocyanurate insulation 32,687 sf 3.50 114,472
Un-insulated roof covering at canopies 1,300 sf 24.21 31,470
Flat Roofing System
EPDM roofing 9,636 sf 7.37 71,044
Air/vapor barrier membrane 9,636 sf 5.22 50,323
Tapered roofing insulation 9,636 sf 6.14 59,204
Exterior roof sheathing 9,636 sf 2.40 23,089
Perimeter detail - Parapet roof detail 70 lf 239.62 16,773
Perimeter detail 1,514 lf 30.72 46,510 942,358
Exterior Soffit Overhang
Exterior Soffit overhang system - Roof perimeter 1,584 sf 36.86 58,393
Exterior Soffit overhang system - Canopies 1,235 sf 36.86 45,527 103,920
B3020 Roof Openings
Skylight System, allow 4 ea 9,216.00 36,864 36,864
General Items
Roof accessories, allow
Miscellaneous flashings 1,514 lf 9.83 14,883
Sealant 1,514 lf 2.46 3,721
Blocking 4,542 lf 4.92 22,325 40,929
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 9 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
B30 Roofing Total 1,124,071 1,124,071
C10 Interior Construction
Partitions
Interior drywall partitions
General Interior Wall 13,680 sf 11.06 151,290
Corridor Interior Wall 14,015 sf 12.90 180,827
Furred Interior Wall 1,430 sf 9.83 14,057
Interior Wall - Between rooms 9,170 sf 15.36 140,851
Interior Wall - Wet Walls 3,560 sf 18.43 65,618
Interior Wall - Galss wall 288 sf Incl. w/Interior glazing
Allow for additional Partitions not shown 4,214 sf 16.11 67,904
Interior glazing
Interior Wall - Galss wall 288 sf 79.87 23,003
Interior Glazing, allow 1% of interior wall area 421 sf 79.87 33,626
Sealant at openings 16,818 lf 1.54 25,832
Blocking at openings 8,409 lf 3.26 27,382 730,392
C1020 Doors
Interior doors complete w/frame, hardware, paint, etc: -
Automatic sliding entry systems - 8' 2" x 7' 8" high 1 ea 13,778.84 13,779
SL Doors (General) - 3' 0" x 7' 0" high 55 ea 1,935.36 106,445
SL Doors (Small House Entry Door) - 3' 0" x 7' 0" high 4 ea 2,826.24 11,305
SL Paitent Rm Doors - 3' 0" x 7' 0" high 40 ea 2,580.48 103,219
SL Paitent Toilet Rm Doors - 3' 0" x 7' 0" high 40 ea 2,322.43 92,897
DL Doors - 6' 0" x 7' 0" high 5 ea 4,644.86 23,224
Allow for
Access Doors 1 ls 1,228.80 1,229
Glazed Doors 14 leaf 774.14 10,838
Fire Rated Doors 9 leaf 614.40 5,530
Sealant at openings 2,487 lf 1.54 3,820
Blocking at openings 2,487 lf 3.26 8,098 380,384
Fittings
Visual Display Surfaces
Marker board (Allow 4' 0" x 4' 0" h) at:-
Conference 1 ea 491.52 492
Hoteling Office 1 ea 491.52 492
Med Room 4 ea 491.52 1,966
Toilet Enclosures Not Required
Bathroom Accessories
Toilet/Shower (Resident Rooms) 40 ea 1,658.88 66,355
Toilet Room (Staff/Visitor Toilet) 4 ea 1,044.48 4,178
Bathing 4 ea 1,658.88 6,636
Mirror
Mirror - Assumed 3' x 4' high (Salon) 2 ea 811.01 1,622
Interior Trim
Dining 206 lf 22.12 4,556
Hearth 388 lf 22.12 8,582
Lobby/Gathering 572 lf 22.12 12,652
Wood wainscot trim (Entry) 567 sf 36.86 20,902
Wood wainscot trim (Lobby/Gathering) 162 sf 36.86 5,972
Fascia and end caps 69 lf 24.58 1,696
Cultured Stone Wall Cladding (Hearth) 4 ea 8,500.00 34,000
Handrails (Circulation corridors) 474 lf 73.73 34,947
Building Signage, allow
Door signage 104 ea 122.88 12,780
Interior Directional Signage 1 ls 6,379.50 6,379
Exterior Building Signage 1 ls 10,632.50 10,632
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 10 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
Wood Lockers Excluded
Fire extinguisher complete w/cabinet & mounting hardware, allow 10 ea 141.31 1,413
Fire extinguisher complete w/ mounting hardware, allow 10 ea 104.45 1,044 237,296
C10 Interior Construction Total 1,348,072 1,348,072
C20 Stairs
Stair Construction
No Work Required Not Required
C20 Stairs Total 0 0
C30 Interior Finishes
C3010 Interior Wall Finish
Interior Wall Finish
Paint to Wall 56,484 sf 1.11 62,467
Ceramic Wall Tile, full height at plumbing wall - 6" x 12" (Staff/Visitor Toilet) 382 sf 28.88 11,031
Decorative Ceramic Wall Tile (Kitchen) 609 sf 28.88 17,586
Porcelain Wall Tile, full height - 4" x 8" (Resident Bath) 12,208 sf 18.43 225,018
Porcelain Wall Tile, half height - 4" x 8" (Bathing) 779 sf 18.43 14,359
Porcelain Wall Tile, half height - 4" x 8" (Salon) 262 sf 18.43 4,829
Cultured Stone Wall Cladding (Hearth) Included w/Fittings
Specialty Wall Finish
Accent Wall Covering, allow 25% of wall areas (Den) 593 sf 5.69 3,374
Accent Wall Covering, allow 25% of wall areas (Entry/Corridor) 2,533 sf 5.69 14,411
Accent Wall Covering, allow 25% of wall areas (Equip) 273 sf 5.69 1,553
Accent Wall Covering, allow 25% of wall areas (Hearth) 762 sf 5.69 4,335
Accent Wall Covering, allow 25% of wall areas (Lobby/Gathering)1,501 sf 5.69 8,540
Protective Wall Covering, allow 25% of wall areas (Dining) 541 sf 9.89 5,351
Protective Wall Covering, full height (Linen/Laundry/Soiled) 4,893 sf 9.89 48,401 421,255
C3020 Interior Floor Finish
Interior Floor Finish
Carpet Tile, solution dyed premium nylon 23,967 sf 7.51 179,976
Porcelain Tile - 12" x 24" (Bathing) 420 sf 18.43 7,741
Porcelain Tile - 12" x 24" (Staff/Visitor Toilet) 348 sf 18.43 6,414
Porcelain Tile, small-module (Resident Bath) 2,560 sf 18.43 47,186
Sheet Vinyl, heat-weld seams 2,697 sf 9.24 24,922
Sheet Vinyl, slip-retardant, heat-welded seams (Kitchen/Med Room/Pantry) 1,345 sf 10.14 13,635
Sheet Vinyl, wood-look, heat-weld seams (Salon) 152 sf 9.24 1,405
Walk-off Mat Carpet Tile 108 sf Included w/Furnishings
Leveling/Protection to interior floors 31,597 sf 1.23 38,826
Moisture mitigation Allowance Included w/Concrete Slab
Interior Base Finish
Integral Wall Base 355 lf 7.25 2,574
Porcelain Tile Base - 6" x 24" (Bathing) 164 lf 19.66 3,224
Porcelain Tile Base - 6" x 24" (Staff/Visitor Toilet) 161 lf 19.66 3,165
Porcelain Tile Base (Resident Bath) 1,285 lf 19.66 25,264
Rubber Wall Base - 4" high (Coved-toe profile) 1,004 lf 4.93 4,947
Rubber Wall Base - 4" high (Straight profile) 105 lf 4.93 517
Wood Wall Base - 4" high 2,726 lf 12.29 33,497
Wood Wall Base - 6" high 2,564 lf 14.75 37,808 431,103
C3030 Interior Ceiling Finish
Ceiling Finish
ACT ceiling system, fine texture - 2' x 2' 5,385 sf 6.45 34,740
Suspended GWB ceiling system & epoxy paint 4,308 sf 13.36 57,542
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 11 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
Suspended GWB ceiling system & paint 21,904 sf 12.60 275,885
GWB Soffit (Allow 1' 0" high)
GWB soffit system (Dining) 284 lf 15.74 4,471
GWB soffit system (Hearth) 260 lf 15.74 4,093
GWB soffit system (Kitchen) 172 lf 16.70 2,872
GWB soffit system (Lobby/Gathering) 239 lf 15.74 3,763
Light cove (Hearth/Dining) 320 lf 55.30 17,695
Light cove (Lobby/Gathering) 69 lf 55.30 3,815 404,877
C30 Interior Finishes Total 1,257,234 1,257,234
D10 Conveying Systems
D1010 Elevator an Lifts
No Work Required Not Required
D10 Conveying Systems Total 0 0
D20 Plumbing
Plumbing Fixtures
WC - Floor mounted Water Closet, tank style (HC) 4 ea 1,413.12 5,652
LAV - Lavatory (Counter mounted) 4 ea 1,105.92 4,424
Paitent Toilet Rm
WC - Floor mounted Water Closet, tank style (HC) 40 ea 1,474.56 58,982
LAV - Lavatory (Counter mounted) 40 ea 1,228.80 49,152
Shower 40 ea 1,167.36 46,694
UR - Wall Hung Waterless Urinal Not Required
Bathtub at bathing rooms 4 ea 2,273.28 9,093
Kitchen Sinks 4 ea 1,904.64 7,619
Hair washing station (Rough-in only) 1 ea 737.28 737
Other Sinks 6 ea 1,290.24 7,741
Mop Sinks 4 ea 1,044.48 4,178
EWC - Electric Water Cooler 2 ea 1,136.64 2,273
Floor Drain 20 ea 552.96 11,059
Floor Drain - Patient Rooms Sloped to shower drain
Plumbing Equipment
Water heaters 1 ea 63,776.49 63,776
Backflow preventer 1 ea 4,250.00 4,250
Thermostatically actuated mixing valve 1 ea 3,850.00 3,850
Domestic hot water pump 1 ea 15,673.71 15,674
Central 500 gal grease interceptor 1 ea 8,171.52 8,172
Plumbing Fixture Piping
Piping 11,893 lf 39.94 474,939
Piping Fittings 1 ls 175,081.47 175,081
Piping Valves & Accessories 1 ls 159,749.00 159,749
Piping Insulation 6,541 lf 12.29 80,374
Allow for
Central vacuuming system 1 ls 148,854.99 148,855
Service to Laundry 1 ls 4,055.04 4,055
Service to Central Kitchen 1 ls 18,192.38 18,192
Underground pipework 2,379 lf 18.43 43,850
Gas installation 34,611 sf 0.61 21,265 1,429,688
Medical Gas to Patient Rooms
Medical Gas to Patient Rooms
Equipment, allow 1 ls 50,417.13 50,417
Piping and outlets at Patient Rooms
Outlets (allow 1 drop per room - 3# medical gas outlets) 40 ea 331.78 13,271
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 12 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
Piping 2,400 lf 36.86 88,474
Piping Fittings 1 ls 32,614.91 32,615
Piping Valves & Accessories 1 ls 29,758.71 29,759 214,535
Storm Water System
Rainwater systems
Roof drain to flat roof 6 ea 675.84 4,055
Piping 240 lf 36.86 8,847
Piping Fittings 1 ls 3,261.49 3,261
Piping Valves & Accessories 1 ls 2,975.87 2,976 19,140
General
Hydrants, clean outs,etc 1 ls 1,500.00 1,500
Allow for seismic restraint & vibration isolation 1 ls 1,250.00 1,250
Permit fees Not Required
Test & balance 1 ls 33,322.27 33,322 36,072
Sub Bid Total 1,699,436 1,699,436
Builders work in connection with Plumbing @ 2% 1 ls 33,988.71 33,989
General Contractor's overhead and profit CM Fee Carried in Summary 33,989
D20 Plumbing Total 1,733,424 1,733,424
D 30 Heating, Ventilating, and Air Conditioning (HVAC)
Equipment
Energy recovery units (ERU’s) 4 ea 63,795.00 255,180
Condensing boiler (500 MBH) 1 ea 61,440.00 61,440
Boiler Pumps 2 ea 3,993.60 7,987
Air cooled condensing units 4 ea 23,040.00 92,160
VRF Terminal Units 69 ea 2,764.80 190,771
Perimeter heating system 554 lf 153.60 85,094
Building exhaust system, allow 0.5 cfm/sf 1 ls 42,531.23 42,531
Expansion tank 1 ea 4,331.52 4,332
Air separator 1 ea 3,717.12 3,717
Unit Heater 10 ea 1,228.80 12,288 755,501
Ductwork
Galvanized steel ductwork w/accessories, fittings, hangers, etc (22ga):-
Supply/Return/Exhaust System 20,767 lb 11.37 236,041
Duct Fittings/Waste 5,192 lb 11.37 59,014
Insulation to supply/return duct 11,357 sf 4.92 55,822
EO for stainless steel ductwork Not Required
EO for black steel to Kitchen ductwork 1 ls 14,502.30 14,502
Diffusers/grilles/registers 87 ea 430.08 37,417
Dampers, allow:-
Volume 87 ea 153.60 13,363
Fire 5 ea 307.20 1,536
Smoke 5 ea 1,044.48 5,222 422,919
Pipework
Refrigerant piping (Including insulation) 4,344 lf 30.72 133,448
Hot Water piping 2,893 lf 49.15 142,197
Condensate Piping 1,035 lf 27.65 28,616
Allow for: -
Pipe Fittings 1 ls 93,468.70 93,469
Piping Accessories 1 ls 74,774.96 74,775
Piping Insulation 2,893 lf 12.29 35,549 508,053
Automatic Control System
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 13 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
Building Management System (BMS) 1 ls 326,047.22 326,047 326,047
General
Commissioning by Third Party 1 ls 5,031.30 5,031
Allow for seismic restraint & vibration isolation 1 ls 6,310.25 6,310
Test & balance 1 ls 40,477.22 40,477 51,819
Sub Bid Total 2,064,338 2,064,338
Builders work in connection with HVAC @ 2% 1 ls 41,286.76 41,287
General Contractor's overhead and profit CM Fee Carried in Summary 41,287
D 30 Heating, Ventilating, and Air Conditioning (HVAC) Total 2,105,625 2,105,625
D40 Fire Protection Systems
Fire Protection Systems
Wet sprinkler system (gfa) 34,611 sf 4.30 148,855
EO for dry system 3,461 sf 12.29 42,529
Fire Pump, allow 1 ea 51,609.60 51,610
Standpipes will be located within each egress stairwell Included w/rate above
Fire Hose Valve Cabinet 3 ea 3,502.08 10,506
Allow for seismic restraint 1 ls 3,115.00 3,115
Permit fees Not Required
Test and balance 1 ls 5,132.29 5,132 261,747
Sub Bid Total 261,747 261,747
Builders work in connection with F. Protection @ 2% 1 ls 5,234.94 5,235
General Contractor's overhead and profit @ 5% CM Fee Carried in Summary 5,235
D40 Fire Protection Systems Total 266,982 266,982
D50 Electrical Systems
Equipment, Panelboards, etc.
Emergency Generator - 350KVA 1 ls 193,536.00 193,536
Emergency Power Distribution 34,611 sf 1.54 53,162
Normal Power Distribution
MDP - 1200A 1 ea 32,440.32 32,440
Other Panles 34,611 sf 1.84 63,795 342,934
Feeders
Electrical feeders 34,611 sf 2.00 69,222 69,222
Small Power
Small Power 34,611 sf 3.07 106,325
Electrical power to
HVAC Equipment 1 ls 58,022.45 58,022
Plumbing Equipment 1 ls 11,489.28 11,489
Automatic sliding entry systems 2 ea 614.40 1,229
Patient Lifts - Required at all rooms 40 ea 1,044.48 41,779
Other Miscellaneous Equipment 1 ls 10,632.50 10,632 229,477
Lighting
Lighting System
Light fixtures w/lamps, conduit, wiring, etc complete 34,611 sf 11.06 382,770
Lighting controls 34,611 sf 1.84 63,795 446,565
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 14 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
Fire Alarm
Fire Alarm System, allow 34,611 sf 2.64 91,439 91,439
Security system (Pathways & Outlet Box ony)
Security system, allow
Conduit and pull string 34,611 sf 0.61 21,265
Wiring and Equipment Excluded - By Others 21,265
Communications systems (Pathways & Outlet Box ony)
Head-end Equipment By Others
Communications systems, allow
Conduit and pull string 34,611 sf 0.74 25,518
Wiring and Equipment Excluded - By Others 25,518
Nurse Call System
Nurse Call System, allow
Conduit and pull string 34,611 sf 0.61 21,265
Wiring and Equipment 34,611 sf 2.46 85,060 106,325
Audio Visual (Empty Conduit System)
Audio Visual, allow (Conduit and pull string)
Communications systems, allow
Conduit and pull string 34,611 sf 0.18 6,379
Wiring and Equipment By Others 6,379
General
Allow for:-
Lightning protection (gfa) 34,611 sf 0.61 21,265
Grounding (gfa) 34,611 sf 0.37 12,759
Seismic bracing 1 ls 8,358.24 8,358
Commissioning by Third Party 1 ls 4,218.31 4,218
Permit fees Not Required
Testing 1 ls 29,299.25 29,299 75,900
Sub Bid Total 1,415,025 1,415,025
Builders work in connection with Electrical @ 2% 1 ls 34,775.65 34,776
General Contractor's overhead and profit @ 5% CM Fee Carried in Summary 34,776
D50 Electrical Systems Total 1,449,800 1,449,800
E10 Equipment
Commercial Equipment
Food Service Equipment Not Required
Other Equipment
Loading dock equipment, allow Not Required
Patient Lifts - Required at all rooms 40 ea 6,758.40 270,336
Miscellaneous Equipment 1 ls 12,288.00 12,288 282,624
Residential Appliances
High End Residential Fixtures in Stainless Steel Finish
Food prep 4 ea 1,843.20 7,373
Dishwasher 4 ea 2,703.36 10,813
Fridge/freezer combos 8 ea 4,915.20 39,322
Range/oven 4 ea 4,608.00 18,432
Range hood 4 ea 3,256.32 13,025
Microwave oven 4 ea 1,536.00 6,144
Residential Appliances
Washer (Laundry) 4 ea 3,133.44 12,534
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 15 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
Dryer (Laundry)4 ea 2,826.24 11,305 118,948
Salon Equipment
Salon chair 1 ea 3,022.85 3,023
Hair washing station 1 ea 1,536.00 1,536
Wall-mounted dryer 2 ea 2,826.24 5,652 10,211
Projector Screens
Projector Screens, allow 1 ls 8,601.60 8,602 8,602
E10 Equipment Total 420,385 420,385
E20 Furnishings
Roller Shades
Mecho Perforated Shades
Manual roller shades (Living/Dining) 169 sf 9.83 1,661
Manual roller shades (Resident Rooms) 1,753 sf 9.83 17,233
Manual roller shades (Exterior windows) 847 sf 9.83 8,326
Fabric Draperies
Fabric draperies, allow full height (Living/Dining) 228 sf 8.60 1,961
Fabric draperies, allow full height (Resident Rooms) 2,103 sf 8.60 18,089 47,271
Casework
Bathing, allow 6 lf per system
Custom wood base cabinet 24 lf 430.08 10,322
Custom wood wall cabinet 24 lf 301.06 7,225
Solid surface countertop 24 lf 196.61 4,719
Backsplash 40 lf 36.86 1,475
Clean Utility/Linen
PLAM base cabinet 32 lf 368.64 11,796
PLAM wall cabinet 32 lf 239.62 7,668
Solid surface countertop 32 lf 196.61 6,291
Backsplash 24 lf 36.86 885
Shelving, allow 4# tier 44 lf 98.30 4,325
Dining
Millwork, allow 12' 0" x 8' 0" high 4 ea 12,288.00 49,152
Kitchen
Island w/Quartz countertop 96 lf 895.49 85,967
Custom wood base cabinet 24 lf 430.08 10,322
Custom wood wall cabinet 60 lf 301.06 18,063
Quartz countertop 24 lf 221.18 5,308
Backsplash 24 lf 36.86 885
Laundry
PLAM base cabinet 40 lf 368.64 14,746
PLAM wall cabinet Not Required
Solid surface countertop 40 lf 196.61 7,864
Backsplash 56 lf 36.86 2,064
Med Room
Custom wood base cabinet 36 lf 430.08 15,483
Custom wood wall cabinet 36 lf 301.06 10,838
Quartz countertop 36 lf 221.18 7,963
Backsplash 52 lf 36.86 1,917
Pantry
Shelving, allow 4# tier 68 lf 98.30 6,685
Salon
Custom wood base cabinet 15 lf 430.08 6,451
Custom wood wall cabinet 15 lf 301.06 4,516
Solid surface countertop 15 lf 196.61 2,949
Backsplash 19 lf 36.86 700
Soiled Utility
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 16 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
PLAM base cabinet 32 lf 368.64 11,796
PLAM wall cabinet 32 lf 239.62 7,668
Solid surface countertop 32 lf 196.61 6,291
Backsplash 48 lf 36.86 1,769
Shelving, allow 4# tier 44 lf 98.30 4,325
Shelf & coat rod 21 lf 49.15 1,032
Casework in Patient Rooms Excluded - FF&E
Fire place 4 ea 12,288.00 49,152
Miscellaneous Casework, allow 1 ls 21,265.00 21,265 409,879
Entry Mats
Walk-off Mat Carpet Tile 108 sf 49.15 5,308 5,308
E20 Furnishings Total 462,458 462,458
F10 Special Construction
No work in this Element
F10 Special Construction Total 0 0
F20 Selective Demolition
No work in this Element
F20 Selective Demolition Total 0 0
G10 Site Preparation
Remove and Dispose
Demolition of residence 40,000 cf 0.43 17,203
Demolition of garage 7,500 cf 0.31 2,304
Demolition of Patio/pool area 2,400 sf 6.14 14,746
General Site Clearing 236,569 sf 0.12 29,070
Extra over, clear pitch pine/scrub oak woodlands 153,770 sf 0.37 56,686
Extra over driveways 13,000 sf 0.92 11,981
Allow for
Hazardous Material Removal 1 ls Excluded
Miscellaneous demolition 1 ls 6,758.40 6,758
Terminating & capping extg utilities 1 ls 3,072.00 3,072
Protecting & maintaining in operation extg fire main & hydrants serving 1 ls Not Required
Removal of rubbish off site 1 ls 13,070.06 13,070 154,889
Temporary work
Construction fence 2,454 lf 14.13 34,678
EO DL gate 1 ea 1,167.36 1,167
Site Entrance and access road during construction 1 ls 9,093.12 9,093
Sediment & erosion control along temporary swale 2,454 lf 6.14 15,077 60,016
Earthwork
Strip topsoil & store on site, avg 3' 6" deep 236,569 sf 0.12 29,070
Cut Site to achieve new proposed grade levels and store for reuse 10,952 cy 7.99 87,478
Fill areas of site with excavated material to achieve new grade levels 10,952 cy 6.76 74,020
Remove surplus excavated material off site Not Required
EO for excavating rock 548 cy 59.60 32,636
Import fill due to bad materials at building location Excluded
Grade over entire site to achieve final levels 153,770 sf 0.18 28,343
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 17 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
Proof Roll/Compact Building Slab-On-Grade area 34,611 sf 0.37 12,759
Water removal during excavation works 1 ls 4,290.12 4,290 268,595
G10 Site Preparation Total 483,500 483,500
G20 Site Improvements
Site Paving
Asphalt paving at vehicular drives and parking lot 52,006 sf 5.53 287,572
Portland Cement Concrete Sidewalks 7,715 sf 7.99 61,621
Trail path, gravel 4,470 sf 2.15 9,612
PC paver to resident garden 2,438 sf 18.43 44,928
PC paver to porch area garden 1,161 sf 18.43 21,400
Transformer Pad 56 sf 18.43 1,032
Generator pad 213 sf 18.43 3,926
Granite Curb 3,250 lf 39.32 127,795
Curb cut, w/detectable warning 6 ea 153.60 922
Pavement Marking
4" Wide white pavement stripe 1,080 lf 1.27 1,367
Stop stripe 20 lf 2.53 51
Handicap parking symbol 4 ea 44.30 177
Striping 359 sf 0.68 243
STOP symbol 2 ea 44.30 89
Wheel stop 2 ea 158.21 316 561,051
Site Improvements
Bench, teak, 6' 0" long 8 ea 1,105.92 8,847
Bicycle Racks, allow 6 ea 1,413.12 8,479
Trash Containers, allow 6 ea 675.84 4,055
Bollards 10 ea 153.60 1,536
Access gate, vehicular, 26' wide, sliding 1 ea 36,864.00 36,864
Access gate, Extra Over for pier 2 ea 3,072.00 6,144
Fence to resident garden, 6' 0" ornamental 110 lf 184.32 20,275
Extra over for gate, predestrian 2 ea 1,044.48 2,089
Fence to porch garden, 6' 0" ornamental 147 lf 184.32 27,095
Extra over for gate, predestrian 4 ea 1,044.48 4,178
Porch (4# included w/building)Included/bldg
Canopy at main entrance Included/bldg
Extra over for columns 2 ea 1,843.20 3,686
Site Signs, traffic/directional 10 ea 184.32 1,843
Allow additional site improvements not shown, etc to resident gardens 1 ls 150,000.00 150,000
Allow for attitional site furniture 1 ls 6,144.00 6,144 281,236
Site Landscaping
Seeding/Loam 65,000 sf 0.80 51,917
Loam seed disturbed areas (site area - everything) 41,023 sf 0.80 32,766
Mulch/Loam to planting beds 30,596 sf 2.46 75,193
Undisurbed area of site 82,799 sf No work
Planting
Trees, vegetative buffer w/Sherburne, shade 3.5" cal 16 ea 1,167.36 18,678
Trees, vegetative buffer w/Sherburne, evergreen 10' 16 ea 1,044.48 16,712
Trees, shade 3.5" cal 16 ea 1,167.36 18,678
Trees, evergreen 10' 15 ea 1,044.48 15,667
Trees, resident garden 14 ea 798.72 11,182
Shrubs, 3 gal 100 ea 122.88 12,288
Allow for additional planting 1 ls 11,452.97 11,453 264,533
G20 Site Improvements Total 1,106,820 1,106,820
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 18 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Estimate - New location
January 5, 2016
Description Qty Unit Rate Amount Total
G30 Site Civil/Mechanical Utilities
Site Utilities
Storm System
Parking Area
Stormwater Management System (bio retention basin) 5,484 sf 22.12 121,297
Subsurface water chambers 6 ea 6,758.40 40,550
Storm - Catch Basin 7 ea 2,764.80 19,354
Yard drain to resident garden 4 ea 1,044.48 4,178
Storm - Manhole 10 ea 5,959.68 59,597
Storm - Storm line 1,338 lf 73.73 98,648 343,624
Fire /Water Service
Fire Line - Service extended from existing 100 lf 89.09 8,909
Water Line - Service extended from existing 100 lf 89.09 8,909
Connect to existing water line 2 ea 2,457.60 4,915
Hydrants, allow 4 ea 921.60 3,686
Thrust blocks 10 ea 276.48 2,765 29,184
Sanitary Service
MH, on extg Sherbourne Commons main 1 ea 7,987.20 7,987
MH, allow 5 ea 6,451.20 32,256
Pumping chamber w/pumps 1 ea 153,600.00 153,600
Force main, 4" 400 lf 49.15 19,661
Sanitary from building, 6" 50 lf 55.30 2,765
Upgrade extg Sherbourne Commons main, excluded Excluded 216,269
Gas Service
Gas Service - Piping by Gas Company by Gas Company
General Items
Connect to existing services 4 ea 1,536.00 6,144
Trenching and backfill to utility lines 1,988 lf 24.58 48,857
Police detail for utility connections 40 hour 98.30 3,932 58,933
G30 Site Civil/Mechanical Utilities Total 648,010 648,010
G40 Site Electrical Utilities
Site Electrical Utilities
Transformer By Electrical Utility
Primary Service - Conduit and Ductbank Only (connect to existing transformer) Existing
Secondary Service - Conduit and Ductbank Only 300 lf 153.60 46,080
Emergency Service - Conduit and Ductbank Only 261 lf 153.60 40,090
Electrical chamber, allow 3 ea 3,072.00 9,216
Tel/data service - Conduit and Ductbank Only 300 lf 122.88 36,864
Tel/data chamber, allow 3 ea 3,072.00 9,216
Primary Service - Wiring lf By Electrical Utility
Secondary Service - Wiring 300 lf Included with Electrical
Emergency Service - Wiring 261 lf Included with Electrical
Tel/data service - Wiring 300 lf 60.83 18,248
Connect to extg utility lines 2 ea 1,536.00 3,072
Site Lighting
Pole Light 14 ea 5,222.40 73,114
Bollard Light 28 ea 1,044.48 29,245
Police detail for utility connections 20 hour 98.30 1,966 267,110
G40 Site Electrical Utilities Total 267,110 267,110
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 19 d g jones international inc
Our Island Nursing Home, Nantucket, MA
SD Cost Estimate: Gross Floor Area
January 5, 2016
Gross Floor Areas
GFA (sf)Perimeter (lf)
New Location
Level 1 34,611 1,584
Total 34,611
cmcg\mydocs\projects\2004\2015-040 Our Island Home - Nantucket (SD 1.2017).xlsx 20 d g jones international inc