Loading...
HomeMy WebLinkAbout2013_8_15 SBPF Submission_201405230855447710BAXTER ROAD AND SCONSET BLUFF STORM DAMAGE PREVENTION PROJECT NOTICE OF INTENT (DEP FILE NO. SE 048-2581) RESPONSES TO QUESTIONS FROM NANTUCKET CONSERVATION COMMISSION ASKED AT PUBLIC HEARING ON AUGUST 8, 2013 August 15, 2013 To assist the Commission and the public with the review of the NOI, SBPF is presenting specific responses to the topics that were covered at the public hearing on August 8, 2013. The format of this document is to present a brief summary of each comment or question in bold followed by a response in regular text. QUESTIONS/COMMENTS FROM CONSERVATION COMMISSION MEMBERS I. DESIGN Provide updated plans based on the 2013 LIDAR, including the new toe design and additional section views. See the revised plans included with this submission, which are based on the recent (2013) LIDAR survey and include the new toe design and additional section views. What is the southern extent of the Project Area? The southern extent of the Project area has been moved to 63 Baxter Road so as to include only those areas where the coastal bank is actively eroding. The revised Project area is 63-119 Baxter Road, as shown on the attached plans. What is the grain size data for the Project area? The Applicant previously performed a thorough sediment sampling effort for an approximately three-mile section of the eastern shore of Nantucket extending from Sesachacha Pond to just south of the Town sewer beds. A total of 248 sediment samples were collected at various cross-shore positions along thirty-six defined transects spaced approximately every 500-feet, and included the coastal bank (where present), coastal dune (where present), coastal beach, wave breaking zone, and offshore area. When these data were reviewed for the current revetment Project, it was determined that Transects L12 through L19 fell within the current Project area from 119 to 63 Baxter Road. Along each transect, bank samples were taken from the upper bank, middle bank, and lower bank. Transects L19 and L20 were located along a well-vegetated portion of the bank where no sediment was exposed; no Coastal Bank samples were collected along these transects. When grain size summary Nantucket Conservation Commission 2 Responses to August 8, 2013 Hearing characteristics were calculated just for those samples falling within the current Project area, the mean size for the coastal bank samples was 0.45 mm with an average silt content of 13.4%. Table 1 contains a summary of grain size results for the coastal bank within the Project area. Table 1 Coastal Bank Grain Size Summary for the Project Area Coastal Bank Mean grain size (mm) Silt (%) Minimum 0.18 0.4 Maximum 0.67 44.4 Mean 0.42 10.0 The results for the revetment Project area are very similar to both the summary statistics for the entire coastal bank and the summary statistics for the area from 99-55 previously considered for the marine mattress and gabion project. The mean grain size for the entire dataset of coastal bank samples was 0.42 mm with an average silt content of 12%. The mean grain size for the area from 99-55 Baxter Road previously considered for the marine mattress and gabion project is 0.45 mm with an average silt content of 13%. II. CONSTRUCTION Provide more details on the Construction Protocol.  Stone Delivery: All stone, including the filter layer will be delivered via barge directly to the beach. Initially, a landing (or “pier”) barge will beach itself at high tide, setting its spuds (temporary pilings) at its seaward end, and dropping a ramp onto the beach. The location of the landing barge will be determined by the Contractor and is expected to be within or adjacent to the high priority area located seaward of 99-105 Baxter Road. Delivery barges will tie off to the pier barge while the tug boat and/or anchor (crown) buoys keep the stern of the pier barge in place. All-terrain dump trucks will back onto the pier barge from the beach, and get loaded by an excavator aboard the barges. The excavator and the dumps will continue to work their way back until the delivery barge has been emptied. The all-terrain dumps will deliver the stone to either the active work area, or designated staging areas within the bounds of the project. The staging areas will be temporary and will change, so are not specifically mapped, and will be determined by the contractor.  Equipment Delivery: The equipment will mostly be delivered by barge, including: front end loaders, all terrain dumps, excavators and possibly a small crane. There will also be a Nantucket Conservation Commission 3 Responses to August 8, 2013 Hearing small all-terrain transport vehicle used for getting workers to and from Hoicks Hollow, where they will park their vehicles.  Equipment Fueling: All construction equipment will be fueled at Hoicks Hollow by a local fuel truck, as far landward of resource areas as feasible.  Revetment Installation: The toe of the revetment will be excavated in approximately 20' lengths at a time. There will be will be some minor cutting and filling required in order to achieve a relatively straight revetment, as shown on the section views. As the toe stones are being excavated, any excavated material in excess of what will be used for backfill will be used for filling behind the revetment in areas and smoothing the face of the bluff as required. Once the toe is excavated, the geofabric will be laid in place, followed by the filter layer stone and toe stones prior to backfilling. Driving steel sheathing will be used at the sections where material will need to be held back relative to the excavation. The sheathing will be removed after the toe is installed and the revetment area has been smoothed out and prepped. A second crew will lag behind by a section or two, and will install the above grade section of the revetment. The placement of the stone can be done with either a long reach excavator or a small crane. This will be variable based on the contractor selection and their preferred or available equipment.  Sediment Delivery: Sediment will be transported via dump truck from one or more local contractor’s pit(s) off Milestone Road to the delivery location on Baxter Road (see following paragraph), where it will be dumped into a hopper, then transported via conveyor belts to the edge of the coastal bank. The conveyor belts at the top of the bank will dump into a chute (made of 3-foot diameter ADS drainage pipe) for transport down to the lower bank (see Figure 1). The chutes will be positioned a foot or two above the face of the coastal bank using bracing made of pressure-treated wood to protect bank vegetation. These chutes are light enough to be quickly installed and removed during seasonal sediment delivery. Sediment will then be positioned by a front-end loader or skid steer. Five sediment delivery locations will be established along the side of Baxter Road, as shown on Figure 1. Temporary structural turf pull-over areas will be installed at four of these locations; no structural turf is required at the northernmost delivery location near 119 Baxter Road due to the large paved area already present. In the instance of successive storms, sand will be delivered via ADS pipe from above until there is sufficient material at the northern end of the structure for a skid steer to ramp up to the platform at the top of the revetment. This way the skid steers can access other areas of the revetment to disperse sand as required. Nantucket Conservation Commission 4 Responses to August 8, 2013 Hearing  Demobilization: Upon completion of phase one and two, the landing barge will be removed from the nearshore by tugs pulling it off at high tide. The equipment used for the construction will be aboard the landing barge upon departure. PUBLIC QUESTIONS/COMMENTS MEPA should be asked if they have jurisdiction over the Project. MEPA jurisdiction over projects is defined in the MEPA regulations review thresholds at 301 CMR 11.03. For projects subject to wetlands review, the project trigger is the requirement for a state permit (Superseding Order of Conditions) and that certain thresholds are exceeded. Any alteration of coastal bank triggers MEPA review if a Superseding Order of Conditions is required. Thus, if a local Order of Conditions is appealed to DEP, the applicant would be required to file an Environmental Notification Form (ENF) with MEPA. The other potential MEPA trigger is for the category of State-listed Species under MGL 131A (Massachusetts Endangered Species Act). Since the project has decided to not include work on lots south of 63 Baxter Road, there will be no work in either Priority Habitats for State-Protected Species or Estimated Habitats for Rare Wildlife (see Figure 9 in Attachment B of the NOI). Owners need to sign the NOI application. All participating property owners from 63-119 Baxter Road have signed the NOI application, other than the property owner at 71 Baxter Road who has elected not to participate in the project. The revetment at 71 Baxter Road will be installed on Town property; that part of the proposed vegetation on the upper bank which is on private property will not be installed. The Third Party consultant is not looking at the effects of the rocks on littoral drift. What happens if you lose the barrier beach in front of Sesachacha Pond? This area is Piping plover habitat. If you cause erosion, it affects their habitat. Sand will be added in front of the revetment and downdrift of the revetment to mitigate for the sand that would otherwise have been supplied by the coastal bank without the revetment. This sand will be carried by littoral drift to the north at a rate that will be similar to the current rate. Shoreline monitoring transects which extend in front of Sesachacha Pond and northward to Quidnet, Squam and Wauwinet (see Figure 10, Attachment B in the NOI) will be monitored and compared to control locations to determine if the project is causing accelerated erosion; if necessary, mitigation will be provided. If the revetment is causing acceleration of shoreline erosion downdrift of the structure, immediately adjacent areas would experience that erosion first before it would be experienced much farther downdrift at Sesachacha Pond or even farther north at Quidnet, Squam or Wauwinet. Densely-spaced shoreline monitoring transects immediately downdrift and adjacent to the revetment would measure any accelerated erosion due to the revetment, allowing mitigation Nantucket Conservation Commission 5 Responses to August 8, 2013 Hearing to be provided before any acceleration of shoreline erosion would be apparent as far north as Sesachahca Pond, Quidnet, Squam, or Wauwinet. !. !. !. !. !.BAXTER ROADSANKATY ROADI SABEL L E'S WAYISOBELS WAYSANKATY HEAD ROADPOLPIS ROAD BAYBERRY LANE 85 99 97 87 73 83 101 105 109 81 79 93 91 77 117 75 115 113 119 107 107A 53 63 51B 59 69 61 55 51A 71 67 65 Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP,swisstopo, and the GIS User Community G:\Projects\Lighthouse\2013\NOI\sediment_delivery\locations.mxd Figure 1Sediment Delivery Locations Baxter Road and Sconset Bluff Storm Damage Prevention Project Nantucket, MA LEGEND Basemap: 2011 Aerial Imagery, ESRI Participating Property Parcel Boundary !.Hopper Location Structural Turf Location Conveyor Belt for Sediment Delivery Chute for Sediment Delivery Coastal Bank Coastal Dune °0 150 30075Feet1 inch = 300 feetScale1:3,600 top of coastal bank toe of coastal bank