HomeMy WebLinkAboutCapital Projects Presentation to BOS 10 07 2015Capital Projects Review
FY17 Capital project requests total $32,207,800 which is
an increase of $18,107,800 over the current Capital
Improvement Plan
2
CATEGORY
Current FY2017 Requests
FY2017 Req Per
Long-Term Cap
Plan FY17 Dollar Change to Long-Term Cap Plan
General Government
Beaches, Parks, & Ponds $0 $0 $0
Bike Paths & Sidewalks $2,395,800 $700,000 $1,695,800
Buildings $15,000,000 $4,100,000 $10,900,000
Non-Buildings Assets $7,175,000 $6,500,000 $675,000
Public Records $0 $0 $0
Real Estate $0 $0 $0
Road Improvements $5,640,000 $2,000,000 $3,640,000
Technology $325,000 $175,000 $150,000
Vehicles & Equipment $1,672,000 $625,000 $1,047,000
Fiscal Year Subtotal $32,207,800 $14,100,000 $18,107,800
less alt funding sources ($1,455,000)$0 ($1,455,000)
Nantucket Public Schools*$1,125,000 $1,700,000 ($575,000)
GOVT & SCHOOL TOTAL $31,877,800 $15,800,000 $16,077,800
Capital Projects Review
The FY17 requests for Bike Paths and Sidewalks
increased by $1,695,800 from the current Capital
Improvement Plan
3
PROJECT DEPT.
Current FY2017
Requests
FY2017 Req Per
Long-Term Cap
Plan
FY17 Dollar
Change to
Long-Term
Cap Plan
Prospect St Sidewalk: End of Existing Bike Path to Quaker Rd/Vestal Street DPW/PLUS $380,000 $380,000
Somerset Bike Path - Design DPW/PLUS $0 $500,000 ($500,000)
In-Town Bike Path Design (Supplemental funding)DPW/PLUS $200,000 $200,000 $0
In-Town Bike Path Ph2- Orange St-Spruce to Rotary-1800' TIP2021 (Land takings)DPW/PLUS $75,000 $75,000
In-Town Bike Path Ph3 Washington St to Town-2000' TIP 2020 (Land takings)DPW/PLUS $75,000 $75,000
Sparks Avenue Sidewalk Improvements DPW/PLUS $95,000 $95,000
Wauwinet Bike Path Design Grant (Local share if grant approved)DPW $70,800 $70,800
Repair/widening and adding sidealks downtown DPW $1,500,000 $1,500,000
sub total $2,395,800 $700,000 $1,695,800
less alt funding sources
Fiscal Year Total Request $2,395,800 $700,000 $1,695,800
Capital Projects Review
The FY17 requests for Public Buildings resulted in an
increase of $10,900,000 from the current Capital
Improvement Plan
4
PROJECT BUILDING
Current FY2017
Requests
FY2017 Req Per
Long-Term Cap
Plan
FY17 Dollar
Change to Long-
Term Cap Plan
New Female Quarters Fire $100,000 ($100,000)
2 Fairgrounds Road Municipal Building Construction Town Admin $10,000,000 $4,000,000 $6,000,000
Brant Point Shellfish Propagation Facility Rehabilitation/Restoration Natural Resources $1,300,000 $1,300,000
Nobadeer Farm Rd Fieldhouse Public Works $700,000 $700,000
Our Island Home Design Town Admin $2,500,000 $2,500,000
Childrens Beach Concession Town Admin $500,000 $500,000
Jetties Beach Concession Town Admin
$15,000,000 $4,100,000 $10,900,000
less alt funding sources - CPC funds ($875,000)($875,000)
Fiscal Year Total $14,125,000 $4,100,000 $10,025,000
Capital Projects Review
The FY17 requests in the Non Building Assets category
increased by $675,000 from the Capital Improvement
Plan
5
ASSET DEPT.
Current FY2017
Requests
FY2017 Req Per
Long-Term Cap
Plan
FY17 Dollar
Change to Long-
Term Cap Plan
Stormwater Improvements - Phase 2 (design & construction)DPW $6,500,000 $6,500,000 $0
F Street Bulkhead Marine/Public Safety $425,000 $425,000
Repairs/Improv. Children's Beach Boat Ramp Marine/Public Safety $150,000 $150,000
Town Fueling Station Town Admin $100,000 $100,000
Fiscal Year Total $7,175,000 $6,500,000 $675,000
Fiscal Year Total $7,175,000 $6,500,000 $675,000
Capital Projects Review
The FY17 requests in the Roads category increased by
$3,390,000 from the Capital Improvement Plan
6
PROJECT DEPT.
Current FY2017
Requests
FY2017 Req Per
Long-Term Cap
Plan
FY17 Dollar
Change to Long-
Term Cap Plan
Mid-Island / School Area Roadway Acquisitions DPW/PLUS $100,000 $100,000 $0
Surfside Area Reconstruction Ph.2 DPW $1,000,000 $1,000,000 $0
Bartlett/Surfside Roundabout TIP 2017/2018 - Design DPW/PLUS $150,000 $150,000
Road Improvements/Maintenance - Island Wide DPW $900,000 $900,000 $0
First Way Improvement DPW $2,990,000 $2,990,000
Road takings-Friendship/Somerset DPW/PLUS $250,000 $250,000
Road takings-Winn St DPW/PLUS $250,000 $250,000 $0
Fiscal Year Total $5,640,000 $2,000,000 $3,390,000
Alt Funding: Sewer Enterprise Fund (First Way)
Fiscal Year Total $5,640,000 $2,000,000 $3,390,000
Capital Projects Review
The FY17 requests in the Technology category have
increased by $150,000 from the Capital Improvement
Plan
7
EQUIPMENT DEPT.
Current FY2017
Requests
FY2017 Req Per
Long-Term Cap
Plan
FY17 Dollar
Change to Long-
Term Cap Plan
Servers IS, Various $75,000 $75,000 $0
Network: Infrastructure IS $100,000 $100,000 $0
Permit tracking software Town Admin $150,000 $150,000
Fiscal Year Total $325,000 $175,000 $150,000
Capital Projects Review
The FY17 requests in the Vehicles category have
increased by $1,047,000 from the Capital Improvement
Plan
8
VEHICLE/EQUIPMENT DEPT Current FY2017 Requests FY2017 Req Per Long-Term Cap Plan
FY17 Dollar
Change to
Long-Term Cap Plan
Asphalt Recycler and Hot Box DPW $110,000 $110,000
10 Wheel Dump Truck (3)DPW $200,000 $200,000
Pick-up Truck With Plow DPW $60,000 $50,000 $10,000
Replacement 6 Wheel Dumptruck (4)DPW $190,000 $190,000
Van for Facilities DPW $42,000 $42,000
Engine E-3 (2002 Madaket)Fire $375,000 ($375,000)
Engine E-7 (1988)Fire $450,000 $450,000
Administration Trailer Fire $200,000 ($200,000)
Ambulance 1 (2007)Fire $270,000 $270,000
Ambulance 2 (2006)Fire $270,000 $270,000
Off-Road Ambulance Fire $80,000 $80,000
Fiscal Year Total $1,672,000 $625,000 $1,047,000
*Ambulance Reserve Fund ($540,000)($540,000)
**Potential Gift ($40,000)($40,000)Fiscal Year Total less alt funding source $1,092,000 $625,000 $467,000
Capital Projects Review
The FY17 requests from the Nantucket Public Schools
has decreased by $575,000 from the Long-Term Capital
Financing Plan
9
PROJECT Current FY2017 Requests FY2017 Req Per Long-Term Cap Plan
FY17 Dollar
Change to Long-Term Cap Plan
NHS Building Improvements NHS $250,000 $100,000 $150,000
NHS/CPS Window Replacement NHS/CPS $150,000 $150,000 $0
CPS Building Improvements CPS $0 $200,000 ($200,000)
NES Building Improvements NES $0 $100,000 ($100,000)
NES HVAC Upgrade NES $300,000 $350,000 ($50,000)
Upgrade/Replace Large HVAC NPS/CPS $0 $800,000 ($800,000)
NHS Auditorium upgrades NHS $125,000 $125,000
NHS/CPS Façade Repair and Paint NHS/CPS $250,000 $250,000
NES Grounds 4 Wheel Truck with Plow NES $50,000 $50,000
less alt funding sources $0
Fiscal Year Total $1,125,000 $1,700,000 ($575,000)
$1,125,000 $1,700,000 ($575,000)
Capital Projects Review
Projects for discussion:
Real Estate acquisition: Affordable Housing Trust; School
2 Fairgrounds Municipal Building: Timing; location; supplemental design funds
Baxter Rd alternate access construction: timing
Repurpose/use studies for:
20 South Water/1 East Chestnut/25 Federal
37 Washington St – Marine
Seasonal Housing: Where; timing
Current Projects:
Brant Point Boathouse
Children's Beach Concession
Our Island Home
10
Capital Projects Review
Projected impact to tax rate: (based on borrowing everything; subject to Prop 2 ½ approvals)
For a home valued at $1,684,585 the impact is projected to be $256.38
For a home valued at $1,092,299 the impact is projected to be $166.24
Tax rate impact calculated for the first year of debt
service, which is when the largest impact to the tax
rate will occur.
There has been no smoothing of the debt in this current calculation.
11
Capital Projects Review
Notes
Additional funding sources not yet factored in
Free Cash, Prior Year re-appropriations, Budgetary
Capital, Gift Funds (minimal), Real Estate sales account
Does not include Enterprise Fund Capital requests
Does not include General Fund portion of Sewer:
Monomoy/Plus $33,542,000
Madaket/Warrens Landing/Somerset $61,946,000
12
Capital Projects Review
Questions?
13