HomeMy WebLinkAboutOIH FY2016 Capital Submissions_201410090740435427Town of Nantucket
Proposed FY2016 Capital Project
Project Title: Design Services
Department: Our Island Home Contact Person: Rachel K Chretien
Department Priority: Low Medium High X
Funding Amount Requested: $ 500,000.00 For Fiscal Year(s): FY16
Funding Source(s): General Fund State Grant
Enterprise Fund X Other (please explain):
Project Description including location and source of cost estimate:
To provide for selecting a designer to prepare new or alter existing schematic and preliminary
design plans for Our Island Home.
Is the request for a new structure or equipment?
If the request is for replacement or renovation please explain the need.
Replacement facility.
Provide cost changes (if any) that will/could result from this request i.e. increase or
decrease maintenance costs, utilities, personnel etc.
Provide an estimate of revenues (if applicable) gained by this expenditure. Example: Artificial
turf field would enable field rental and lower the ground maintenance costs. Include the
estimated number of years to pay back this expenditure.
If relevant, provide any other justification for the project or equipment.
The facility has outdated, aging structure that is in need of overall renovation and replacements to
continue operations at a safe level for our residents and that meets current ADA, building, life
safety and other related codes. This project will provide for a new building(s) which will potentially
include long term care, home care and other services.
Town of Nantucket
Proposed FY2016 Capital Project
Project Title: Ambulette
Department: Our Island Home Contact Person: Ed King, Rachel Chretien
Department Priority: Low Medium High X
Funding Amount Requested: $ 60,000.00
Funding Source(s): General Fund State Grant
Enterprise Fund Other (please explain): Retained Earnings
Project Description including location and source of cost estimate:
Ambulette for resident transports
Is the request for a new structure or equipment? Yes, would utilize instead of larger van
If the request is for replacement or renovation please explain the need.
Provide cost changes (if any) that will/could result from this request i.e. increase or
decrease maintenance costs, utilities, personnel etc.
Constant changing of battery, potential decreased maintenance cost in the future.
Decreased fuel cost.
Provide an estimate of revenues (if applicable) gained by this expenditure. Example: Artificial
turf field would enable field rental and lower the ground maintenance costs. Include the
estimated number of years to pay back this expenditure.
n/a
If relevant, provide any other justification for the project or equipment.
Current van use is unable to use A.C without shorting out battery.
Narrow streets and traffic related issues are a huge concern with current van utilized. We have had
2 recent accidents just the past month and have to limit resident transportation during high season
months (usually church and home visits). Smaller van will enable transportation to these events to
continue with accident free transportation.
Town of Nantucket
Proposed FY2016 Capital Project
Project Title: Boilers and related systems
Department: Our Island Home Contact Person: Ed King, Rachel Chretien
Department Priority: Low Medium High X
Funding Amount Requested: $ 220,000.00
Funding Source(s): General Fund State Grant
Enterprise Fund Other (please explain): Retained Earnings
Project Description including location and source of cost estimate:
Replace existing boiler heating, domestic hot water heater and pumps. Replaced fuel oil circulation
pump and existing propane direct fired domestic hot water heaters.
All located at 9 East Creek Rd.
Is the request for a new structure or equipment?
If the request is for replacement or renovation please explain the need.
Yes, existing equipment is outdated, not energy efficient and exceeded useful service life.
Provide cost changes (if any) that will/could result from this request i.e. increase or
decrease maintenance costs, utilities, personnel etc.
Energy efficiency long term cost savings as outline in the Mechanical Engineer Assessment
Provide an estimate of revenues (if applicable) gained by this expenditure. Example: Artificial
turf field would enable field rental and lower the ground maintenance costs. Include the
estimated number of years to pay back this expenditure.
n/a
If relevant, provide any other justification for the project or equipment.
Current unit has been discontinued by manufacture making repairs and parts scarce. Also, current
unit has significant performance issues which in part is due to the building load is greater than what
the current system can handle (should’ve been upgraded when dining room addition added) and
therefore produces lack of sufficient heat.
Receive multiple resident complaints related to water temperatures; mostly during bathing.
Will need additional space for upgrade of system and will likely cause reconfiguration in neighboring
storage room.
Town of Nantucket
Proposed FY2016 Capital Project
Project Title: Central Heat Recovery and thermo sets
Department: Our Island Home Contact Person: Ed King, Rachel Chretien
Department Priority: Low Medium High X
Funding Amount Requested: $ 190,000.00
Funding Source(s): General Fund State Grant
Enterprise Fund Other (please explain): Retained Earnings
Project Description including location and source of cost estimate:
Replace existing central heat recovery unit and individual thermo sets at 9 East Creek Rd.
Is the request for a new structure or equipment?
If the request is for replacement or renovation please explain the need.
Yes, existing equipment has exceeded useful service life and deemed critical to replace
Provide cost changes (if any) that will/could result from this request i.e. increase or
decrease maintenance costs, utilities, personnel etc.
Energy efficiency long term cost savings as outline in the Mechanical Engineer Assessment
Provide an estimate of revenues (if applicable) gained by this expenditure. Example: Artificial
turf field would enable field rental and lower the ground maintenance costs. Include the
estimated number of years to pay back this expenditure.
n/a
If relevant, provide any other justification for the project or equipment.
Current unit has been discontinued by manufacture making repairs and parts scarce. Damper and
bypass are not operational. Also, current unit has significant performance issues including lack of
heating ability on cold days and no air conditioning produced during humid hot days. We have had
two DPH reportable events related to building temperature due to this.
Town of Nantucket
Proposed FY2016 Capital Project
Project Title: Roof – Solar Shingles
Department: Our Island Home Contact Person: Ed King, Rachel Chretien
Department Priority: Low Medium High X
Funding Amount Requested: $ 207,000.00
Funding Source(s): General Fund State Grant
Enterprise Fund Other (please explain): Retained Earnings
Project Description including location and source of cost estimate:
Removed existing shingles of entire building and generator shed at 9 East Creek Road. Install new
winter guard and CertainTeed Landmark TL shingles. New copper drip edge and copper vent stacks
plus miscellaneous flashing.
Is the request for a new structure or equipment? No
If the request is for replacement or renovation please explain the need.
Yes, replacement of existing roof and related items due to increase in leaks and ‘lost’ shingles
during high wind conditions.
Provide cost changes (if any) that will/could result from this request i.e. increase or
decrease maintenance costs, utilities, personnel etc.
n/a
Provide an estimate of revenues (if applicable) gained by this expenditure. Example: Artificial
turf field would enable field rental and lower the ground maintenance costs. Include the
estimated number of years to pay back this expenditure.
n/a
If relevant, provide any other justification for the project or equipment.
Previously needed to patch portion of North wing roof in early 2013 with emergency waiver from
storm damage. Remainder of roof is just as weak and susceptible to damage.
*Roof estimate is $180,000. Added 15% onto estimate for Solar Shingles
FY 2017 - 2025 Proposed Capital Requests
DEPARTMENT: OUR ISLAND HOME
FY 2017 Item Additional Description Estimated Cost
New Facility Construction of new facility 15,000,000.00$
Resident Room upgrades
Furniture, beds, closets, painting, additional outlets.
Furniture is 18+yrs old 200,000.00$ *
Electronic Medical Records New or Upgrade of current software 75,000.00$
Already approved at ATM but
may need to increase $ as pushed
out implementation
Storm windows & treatments
Replace all exterior storm windows and interior
window treatment 90,000.00$ *
AC Units
DPH requires AC in all resident areas (currently only in
core area) plus replacement of all old units 100,000.00$ *
FY 2018
Bathroom upgrades
Tub/Shower rooms, all sinks, toilets, tubs, flooring &
tile work 325,000.00$ *
Cooridor & Resident doors
all doors tied to the fire system, most are 30% warped
and don't seal as required *
FY 2019
Exterior Trim & Side Wall 275,000.00$ *
FY 2020
Kitchen renovation
Steamtable, light fixtures, walk-in, stove & other
related equipment 80,000.00$ *
Laundry Equipment Washers & Dryers 50,000.00$ *
FY 2021
Sprinkler System upgrades *
Suspended ceiling upgrades *
FY 2022
FY 2023
FY 2024
FY 2025 Generator *
* = will not need if
construction of new
building begin FY17
FY2031 Fuel Tank