HomeMy WebLinkAboutFire Dept FY2016 Capital Submissions_201410090740429021Nantucket Fire & Rescue
10 Year Capital Plan 8/01/2014
FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY-2019 FY-2020 FY 2020
Apparatus Yr . In Service
Ladder Truck 2006 FY 2026
Tender 1 / E-6 1988 $240,000 FY 2040
Engine 1 2009 FY 2024
Engine 2 2006 FY 2026
Tender 2 1989 $240,000 FY 2043
Engine 3 2002 FY 2037
Engine 4 2011 FY 2027
Engine 5 Tuck 1981
Engine 7 1981 $375,000 FY 2026
Rescue 1 2004 FY 2029
Fire Alarm Truck 2006 FY 2026
Brush breaker Tuck 1971
Ambulance 1 2007 $180,000 FY 2028
Ambulance 2 2006 $180,000 FY 2026
Ambulance 3 2001 $165,000 FY 2024
Command C2 2005 $35,000 FY 2025
Command C1 2004 $35,000 FY 2024
Utility Truck 2004 FY 2021
Fire Prev/Ins C5 1998 Rep/w/C1 $35,000 FY 2028
Fire Supr/Ins C4 2005 FY 2021
Totals $200,000 $240,000 $35,000 $375,000 $240,000 $255,000 $180,000
Nantucket Fire & Rescue
10 Year Capital Plan 8/01/2014
FY 2015 FY 2016 FY 2017 FY 2018
Buildings-Construction
Staion 1 Administration Trailer $150,000
Demolition Gararge St 1 $35,000
Crew Quarters St 1 $75,000
Station 2 Exterrior Construction $135,000
Station 3 Exterrior Paint $25,000
Station 4
Totals CPC $260,000 $25,000
FY-2019 FY-2019 FY 2020
FY 2026
FY 2040
FY 2024
FY 2026
FY 2043
FY 2037
FY 2027
FY 2026
FY 2029
FY 2026
FY 2028
FY 2026
FY 2024
FY 2025
FY 2024
FY 2027
FY 2028
FY 2020
Town of Nantucket
Proposed FY2016 Capital Project
Project Title: Scott Air Packs
Department: Fire Department Contact Person: Mark McDougall
Department Priority: Low Medium High X
Funding Amount Requested: $ 50,000
Funding
Source(s): General Fund X State Grant
Enterprise Fund Other (please explain):
Project Description including location and source of cost estimate:
60 Scott 30 minuet firefighting air tank. Distributer pricing from the state bid list.
Is the request for a new structure or equipment?
Request is for the replacement of firefighting air tanks that will be out of date in CY 2016.
If the request is for replacement or renovation please explain the need.
This request is for replacement of 60 air tanks that are coming up on their expiration date.
These air tanks are used for entering many types of hazardous environment such as
structure fires and areas with a high level of corbon monoxide. This purchase is
considered highest priority.
Provide cost changes (if any) that will/could result from this request i.e. increase or
decrease maintenance costs, utilities, personnel etc.
No increase or decrease in maintenance, utilities or personnel costs.
Provide an estimate of revenues (if applicable) gained by this expenditure. Example:
Artificial turf field would enable field rental and lower the ground maintenance costs.
Include the estimated number of years to pay back this expenditure.
No revenues gained.
If relevant, provide any other justification for the project or equipment.
N/A
Town of Nantucket
Proposed FY2016 Capital Project
Project Title: Administration Vehicle-Deputy Chief
Department: Fire Department Contact Person: Mark McDougall
Department Priority: Low Medium X High
Funding Amount Requested: $ 35,000
Funding
Source(s): General Fund X State Grant
Enterprise Fund Other (please explain):
Project Description including location and source of cost estimate:
Request is for a new vehicle that will be used as an administration, command emergency
response unit. Manufacturers Pricing $35,000.
Is the request for a new structure or equipment?
New Vehicle.
If the request is for replacement or renovation please explain the need.
Replacement of a 2005 Chevy Tahoe with 65000 miles, this vehicle will be traded in for the
replacement.
Provide cost changes (if any) that will/could result from this request i.e. increase or
decrease maintenance costs, utilities, personnel etc.
Maintenance $500 to $800 annual.
Provide an estimate of revenues (if applicable) gained by this expenditure. Example:
Artificial turf field would enable field rental and lower the ground maintenance costs.
Include the estimated number of years to pay back this expenditure.
No revenues gained.
If relevant, provide any other justification for the project or equipment.
N/A
Town of Nantucket
Proposed FY2016 Capital Project
Project Title: Sconset Fire Station Restoration
Department: Fire Department Contact Person: Mark McDougall
Department Priority: Low Medium High X
Funding Amount Requested: $ 150,000.00
Funding
Source(s): General Fund State Grant
Enterprise Fund Other (please explain): CPC Application
Project Description including location and source of cost estimate:
Exterior work to be completed consists of but not limited to the demolition and
replacement of the masonry steps in the front of the building. Replacement/restoration of
exterior doors, windows, sidewall and trim as needed. Prep work and painting of the
complete exterior of the building. Demolition of the old bulked to be replaced with a new
cedar bulked. Contractor pricing/estimates are generalized due to problems such as long
time deterioration that may have taken place in certain areas of the building. Such as under
exterior trim and within the window casings/framing.
Is the request for a new structure or equipment?
Request is for restoration work that is needed on the existing building.
If the request is for replacement or renovation please explain the need.
Request is for restoration that is needed due to the age and condition of the building.
Provide cost changes (if any) that will/could result from this request i.e. increase or
decrease maintenance costs, utilities, personnel etc.
Maintenance costs in the future will continue. This should be lesser amounts of funding due
to shorter periods between follow-up maintenance schedules once the building is restored.
Provide an estimate of revenues (if applicable) gained by this expenditure. Example:
Artificial turf field would enable field rental and lower the ground maintenance costs.
Include the estimated number of years to pay back this expenditure.
N/A
If relevant, provide any other justification for the project or equipment.
N/A
Town of Nantucket
Proposed FY2016 Capital Project
Project Title: Nantucket Public Safety Facility – New Fire Station
Department: Fire Department Contact Person: Mark McDougall
Department Priority: Low Medium High X
Funding Amount Requested:
$14,740,000.00
Funding
Source(s): General Fund State Grant
Enterprise Fund Other (please explain): ATM/ Capital Expense
Project Description including location and source of cost estimate:
Completion of plan design and construction of a new fire station located at 4 Fairgrounds
Road. This is a preliminary opinion of probable cost based on industry standards relating to
the hours and material recommended to complete such a project.
Is the request for a new structure or equipment?
Request is for a complete new building for the purpose of housing the majority of fire
administration, personnel and apparatus.
If the request is for replacement or renovation please explain the need.
Construction of a new fire station located at 4 Fairgrounds Road is the next step to full
completion of the Nantucket Public Safety Facility. This plan needs to advance due to lack
of crew/female quarters, administration office/filing space and apparatus space to safely
operate and store equipment.
Provide cost changes (if any) that will/could result from this request i.e. increase or
decrease maintenance costs, utilities, personnel etc.
Utility costs should be transferred over from the closing of the old building to the
completion and operation of the new building. Due to new construction maintenance should
be minimal for several years out.
Provide an estimate of revenues (if applicable) gained by this expenditure. Example:
Artificial turf field would enable field rental and lower the ground maintenance costs.
Include the estimated number of years to pay back this expenditure.
No revenues gained.
If relevant, provide any other justification for the project or equipment.
N/A
FY 2017 - 2025 Proposed Capital Requests
DEPARTMENT:
Item Additional Description Estimated Cost
FY 2017 New Engine 7 Year-1981 Replacement of old Engine 7 $375,000
New Administration Trailer Demolition of old garage/placement of Admin Tr $150,000
New Crew/Female Quarters Renovation of old administration space $100,000
FY 2018 New Tanker 2 Year-1989 Replacement of old Tanker 2 $240,000
Paint Madaket Station Re-paint exterior of the Madaket Station $25,000
FY 2019 New Ambulance 2 Year-2006 Replacement of old Ambulance 2 $180,000
New Fire Prevention Vehicle-1998 Replacement of old Fire Prevention Vehicle $40,000
FY 2020 New Ambulance 1 Year-2007 Replacement of old Ambulance 1 $180,000
FY 2021 New Brush/Utility Truck Year-2004 Replacement of old Utility Truck $40,000
New Fire Alarm Supra Vehicle-2005 Replacement of old Fire Alarm Supra Vehicle $40,000
FY 2022
FY 2023
FY 2024 New Engine 1 Year-2009 Replacement of old Engine 1 $525,000
New Administration Vehicle-2014 Replacement of Chiefs Vehicle $45,000
FY 2025 New Administration Vehicle -TBD Possible replacement for FY-2016 = ?$45,000
Nantucket Public Safety Facility - Fire Dept
Preliminary Opinion of Probable Project Cost February, 2013
Item Description Sub Total Cost
Sitework Cost $250,000
Building Construction Cost
Main Bldg 22215 Sq.Ft.$8,441,700 @$380/SF
$8,691,700
Pricing Contingency 5%$434,600
General Conditions, 10%$912,600
Insurance, Bonds 2.70%$271,100
Overhead 2%$206,200
Profit 5.5%$578,400
Estimating Mark-ups $2,402,900
Estimated Construction (GC) Cost February '13 $11,094,600
Owner's Costs
Arch.& Eng.Fees $706,000
Rreimbursables/add.services $50,000
Project Management $388,000
Furnishings, Furniture & Equipment $160,000
Communications Equipment $0 ?
Land Survey done
Geotechnical Investigation done
Hydrant Test done
Third Party Review (structural)$5,000
Insurance, Legal, Advertising $10,000
Reproduction / Mailing $15,000
Material Testing $25,000
Owner's Construction Contingency (5% of All Costs)$623,000
Estimated Owner's Design Phase Costs $1,982,000
Total Project Cost $13,076,600
Costs through Bidding
A/E Fees $476,000
Reimbursables/Add serv.$24,000
Project Management (OPM)$50,000
Third Party Review $5,000
Insurance, Legal, Advertising $10,000
Reproduction / Mailing $15,000
Contingency $20,000
$600,000
February, 2013
Nantucket Central Fire Station (@ 4FG)
Preliminary Opinion of Probable Project Cost September, 2014
Item Description Sub Total Cost
Sitework Cost
Basic Infrastructure complete at 4FG $250,000
Building Construction Cost
Main Bldg - Trade Costs 22,215 square feet $8,441,700
Subtotal Direct Trade Costs:$8,691,700
Construction Cost Mark-ups
Pricing Contingency 5%$434,600
General Conditions, 10%$912,600
Insurance, Bonds 2.70%$271,100
Overhead 2%$206,200
GC Profit 5.5%$578,400
Escalation through Bidding (Spring 2016)$1,385,300
Subtotal Construction Cost Mark-ups:$3,788,300
Estimated Construction Cost Spring of 2016:$12,480,000
Owner's Indirect Costs
Arch.& Eng.Fees $796,000
Rreimbursables/add.services $60,000
Project Management $437,000
Furnishings, Furniture & Equipment $200,000
Communications Equipment shared w/ PD
Land Survey done for 4FG
Geotechnical Investigation done for 4FG
Hydrant Test done for 4FG
Third Party Review (structural)$5,000
Insurance, Legal, Advertising $10,000
Material Testing $25,000
Reproduction / Mailing $25,000
Owner's Project Contingency (5% of All Costs)$702,000
Estimated Owner's Design Phase Costs:$2,260,000
Total Anticipated Project Cost:$14,740,000
Nantucket Central Fire Station (Optional 3ac. Site)
Preliminary Opinion of Probable Project Cost September, 2014
Item Description Sub Total Cost
Sitework Cost
Site Infrastructure and Development $1,250,000
Building Construction Cost
Main Bldg - Trade Costs 22,215 square feet $8,441,700
Subtotal Direct Trade Costs:$9,691,700
Construction Cost Mark-ups
Pricing Contingency 5%$484,600
General Conditions, 10%$1,017,600
Insurance, Bonds 2.70%$302,200
Overhead 2%$229,900
GC Profit 5.5%$644,900
Escalation through Bidding (Spring 2016)$1,544,700
Subtotal Construction Cost Mark-ups:$4,224,000
Estimated Construction Cost Spring of 2016:$13,915,700
Owner's Indirect Costs
Arch.& Eng.Fees $890,000
Rreimbursables/add.services $65,000
Project Management $487,500
Furnishings, Furniture & Equipment $200,000
Communications Equipment $150,000 Allowance
Land Survey $22,500 Allowance
Geotechnical Investigation $12,300 Allowance
Hydrant Test $1,500
Third Party Review (structural)$5,000
Insurance, Legal, Advertising $10,000
Material Testing $25,000
Reproduction / Mailing $25,000
Owner's Project Contingency (5% of All Costs)$790,500
Estimated Owner's Design Phase Costs:$2,684,300
Total Anticipated Project Cost*:$16,600,000
Note: * Site acquisition cost not included