HomeMy WebLinkAbout2018-8-8ConCom Minutes for August 8 2018 adopted Aug. 22
CONSERVATION COMMISSION
PUBLIC MEETING N A N T U C }:; E2 Bathing Beach Road TOWN C L E R'
Nantucket, Massachusetts 02554
www.nantucket-ma.gov
Wednesday, August 8, 2018 2010 AUG 28 PM 3:35
4 Fairgrounds Road, Training Room — 4:00 p.m.
Commissioners: Andrew Bennett(Chair), Ashley Erisman (Vice Chair), Ernie Steinauer, David LaFleur,
Ben Champoux, Ian Golding, Joe Topham
Called to order at 4:02 p.m.
Staff in attendance: Jeff Carlson, Natural Resources Coordinator; Joanne Dodd, Natural Resources Office Administrator,
Terry Norton, Town Minutes Taker
Attending Members: Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Absent Members: None
Late Arrivals: None
Earlier Departure: None
Agenda adopted by unanimous consent
*Matter has not been heard
I. PUBLIC MEETING
A. Announcements
B. Appointment of Officers —
1. Champoux nominated Bennett for chair. Carried unanimously
2. Golding nominated Erisman as vice chair. Carried unanimously
C. Public Comment —
1 . Scott Martin, 12 Brant Point Road — The landscaper doing work at 10 Brant Point Road has been dumping
multiple truckloads of fill and spreading it in areas that are not impacted by construction. He is putting fill on top of
compacted areas. Asked the board to consider ways it can intervene in regard to grading violations in the future.
Don Bracken, Bracken Engineering, Inc., for 10 Brant Point Road — He will go out to look at what's going on. If
they are outside the scope of the permit he will instruct them to stop and get a permit.
Staff — Spoke to the property owner about the complaint; under the existing permit, the contour is not to be
changed.
II. PUBLIC HEARING
A. Notice of Intent
1. *Sconset Beach Preservation Fund — 59-119 Baxter Road (49&48 -various) Area SE48- (Cont. 08/22/2018)
2. *21 Crooked Lane, LLC —1 West Chester Street Ext. (41-480 portion) SE48-3064 (Cont. 09/05/2018)
3. Crichton House Holdings, LLC —133 Polpis Road (44-19.4) SE48-3084 (Cont. 08/22/2018)
4. The Nantucket Land Council — Nantucket Harbor (N/A) SE48-3092
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Documentation Site and topographical plans, photos, requisite departmental reports and correspondence.
Representative Emily Molden, Nantucket Land Council
Public None
Discussion (4:13) Molden — Were waiting for signoff from Massachusetts Natural Heritage (MNH); they have no concerns.
Staff Have everything needed to close.
Motion Motion to Close. (made by: Champoux) (seconded by: Topham)
Vote Carried unanimously
5. Paul J. Brody —11 E Street (60.2.1-4) SE48-3093 (Cont. 08/22/2018)
6. *Three Gully Road, LLC — 7 Gully Road (73.3.1-123) SE48-3099
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Documentation Site and topographical plans, photos, requisite departmental reports and correspondence.
Representative David M. Haines, Haines Hydrogeologic Consulting
Kevin Dale, Vaughan, Dale, Hunter and Beaudette P.C.
Public None
Discussion (4:14) Haines — This is for a single-family dwelling, septic upgrade, garage, and landscaping. Resource areas include a
coastal dune field, 100 -year flood elevation, and land subject to coastal storm flowage; the `Sconset Bluff was
determined not to be a coastal bank. All structures are outside the 50 -foot setback. Will establish the limit of
work with a silt fence.
Staff Have everything needed to close.
Motion Motion to Close. (made by: LaFleur) (seconded by: Champoux)
Vote Carried unanimously
Page 1of7
ConCom Minutes for August 8. 2018. adovted Aug. 22
7.
Juli
Hunter — 97 Sankaty Road (49-94) SE48-3100
Sitting
Bennett, Erisman, Steinauer, LaMeur, Champoux, Golding, Topham
Docum
entai
ion Site and topographical plans, photos, requisite departmental reports and correspondence.
Representatim
David M. Haines, Haines Hydrogeologic Consulting
Paul Santos, Nantucket Surveyors
Public
None
Discus
'on (
:19) Haines — This is to construct a pool, half of which is in the buffer to a bordering vegetated wetland. Water
table is at 13.5 and pool at 18 so will need a waiver for the 2 -foot separation from water table. Excess material
will be removed from the site or stored outside the buffer zone. A siltation fence will mark the limit of work.
All work is within an existing lawn. There will be no alteration to the existing shrub line. Pool equipment will
be stored inside the cabana. All work is outside the 50 -foot buffer. All discharge will be pumped outside the
buffer zone.
Erisman — Asked if the garage studio on the plan is existing or proposed.
Santos — The garage/studio is existing.
Staff
Have everything needed to close.
Motion
Motion to Close. (made by: Champoux) (seconded by: Topham)
Vote
Carried unanimously
8.
Mad
et Sunsets Realty Trust —10 Sheep Pond Road (63-27) SE48-3096
Sitting
Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Documentat
Dn Site and topographical plans, photos, requisite departmental reports and correspondence.
Repres
tati
a Don Bracken, Bracken Engineering, Inc.
Public
None
Discuss
on (4
24) Bracken — This is to move the existing house 75 feet away from the coastal bank. The current house location
and garage will be filled. The existing septic is outside the 100 -foot buffer.
Erisman — Asked what the revegetation of the vacated area will be.
Bracken — It will be allowed to grow back naturally. The well was moved when the septic was relocated.
Staff
Have everything needed to close.
Motion
Motion to Close. (made by: LaFleur) (seconded by: Champoux)
Vote
Carried unanimously
9.
02 N
7auwinet Road Nominee Trust —102 Wauwinet Road (11-24.2) SE48-3097
Sitting
Bennett, Erisman, Steinauer, LaMeur, Golding, Topham
Docum
ntati
n Site and topographical plans, photos, requisite departmental reports and correspondence.
Represe
tati
Don Bracken, Bracken Engineering, Inc.
Public
None
Discuss'
Dn (4
7) Bracken — This is to relocate the driveway to the north; that eliminates the need for an easement on the
abutter's property. The proposed driveway is 25 feet from the wetland area to the south; a silt fence will mark
limit of work.
Erisman — Asked if construction crews will utilize the existing driveway, there should be a silt fence along that
driveway to prevent parking within the buffer zone.
Bracken — He can run a silt fence on both sides of the existing drive around the comer along the culvert.
Staff
Have everything needed to close.
Motion
Motion to Close. (made by: Topham) (seconded by: LaFleur)
Vote
Carried 6-0 //Champoux recused
10. 17
St,
rbuck, LLC — 37 Starbuck Road (60-37) SE48-3104
Sitting
Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Documentation
Site and topographical plans, photos, requisite departmental reports and correspondence.
Representative
Paul Santos, Nantucket Surveyors
Public
None
Discussi
n (4:
3) Santos — To the north is conservation land; to the southwest also used to be conservation land but is now
open ocean. The main structure is pre -1978 with secondary structure, both to be moved away from the eroding
bank into envelopes outside ConCom jurisdiction. The septic is in an upland area but he has left room for it to
be relocated outside the 100 -foot buffer should it be compromised. The work within ConCom jurisdiction is to
pick it up and move the structures; the main dwelling is about 15 feet from the eroding bank. Erosion has
averaged 13 feet a year since 1998. We are looking at putting some sacrificial sand at the base of the slope to
stabilize it during work.
Champoux — Asked about the foundations.
Santos — The main house currently has a full basement. The hole will be filled after the move.
Erisman — Asked how much sacrificial sand would be used.
Santos — Explained how the bank has been eroding and how he plans to temporarily stabilize it.
Staff
Have everything needed to close.
Motion
Motion to Close. (made by: Champoux) (seconded by: LaFleur)
Vote
Carried unanimously
Page 2 of 7
ConCom Minutes for August 8 2018 adopted Aug. 22
11. 11 Meadow Lane, LLC —11 Meadow Lane (41-448 Lot 6 B) SE48-3098
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Documentation Site and topographical plans, photos, requisite departmental reports and correspondence.
Representative Paul Santos, Nantucket Surveyors
Public None
Discussion (4:42) Santos — This is for work within the 100 -foot buffer to a wetland on an existing developed residential area.
The property has been subdivided into two lots; the work is to remove the existing dwelling and redevelop one
of the new parcels. There is a small corner of the pool and a guest house within the buffer. The property is
serviced by Town water and sewer. A test pit in the guesthouse location showed groundwater at 10 feet so he
has applied for a waiver for 2 -foot groundwater separation; the pool is only seven feet deep and mostly outside
the 100 -foot buffer and the guesthouse foundation will be a crawl space.
Champoux — Asked if he's withdrawing the waiver; he thinks it would be best if he did.
Santos — He'll withdraw the waiver request.
Erisman — Asked about a siltation fence.
Santos — It will mark the 50 -foot buffer, which is the limit of work. The wetland is actually the edge of a ditch.
Staff He's requesting a waiver for something that's not jurisdictional; didn't include it in the draft order.
Have everything needed to close.
Motion Motion to Close. (made by: Topham) (seconded by: LaFleur)
Vote Carried unanimously
12. Kimberly Henry — 59 Squam Road (13-17.2) SE48-3103
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding
Documentation Site and topographical plans, photos, requisite departmental reports and correspondence.
Representative Paul Santos, Nantucket Surveyors
Public None
Discussion (4:50) Santos — This is an existing developed lot; work is within 100 feet of the isolated vegetated wetland. The flags
have been confirmed; the area is mapped under Massachusetts Endangered Species Act (MESA). Proposing a
primary dwelling, secondary dwelling, office, and pool, with no work within the 50 -foot no -build zone. Site is
vegetated with a series of maps and MESA has ruled no take. The existing septic is located outside ConCom
jurisdiction.
Erisman — It should be conditioned that all lighting is directed away from the wetlands.
Champoux — Asked if elevation 33 will be carried to the back.
Santos — The house is at elevation 38.
Champoux — Going from 38 to 29 creates a significant slope and prospect for erosion; there should be a
dedicated vegetated buffer on the slope.
Bennett — The will also need something for roof runoff.
Santos — He tested an area that could be a recharge area. There are no groundwater issues.
Discussion about seeing a grading plan before closing.
Santos — Asked for a 2 -week continuance.
Staff Suggested a swale at the bottom of the slope to catch runoff.
Motion Continued for 2 weeks by unanimous consent.
Vote N/A //Topham recused
13. Tack 3, LLC — 26 Washington Street (42.3.2-23) SE48-3109
Sitting Bennett, Erisman, Steinauer, LaReur, Champoux, Golding, Topham
Documentation Site and topographical plans, photos, requisite departmental reports and correspondence.
Representative Art Gasbarro, Nantucket Engineering & Survey
Public None
Discussion (4:59) Gasbarro — This is for lifting and renovation of the structure. The original order of conditions expired during
the Chapter 91 process; they need a current order. This is a velocity zone and the structure will need to be quite
high to allow flood waters to pass under.
Golding — The ridge shows at 34 feet.
Staff Have everything needed to close.
Motion Motion to Close. (made by: Champoux) (seconded by: Steinauer)
Vote Carried unanimously
14. *Lauretta Lane Nominee Trust — 3 & 5 Lauretta Lane (14-53 & 90) SE48-3101
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Documentation Site and topographical plans, photos, requisite departmental reports and correspondence.
Representative Art Gasbarro, Nantucket Engineering & Survey
Public None
Discussion (5:01) Gasbarro — This is for residential redevelopment within the buffer to a bordering vegetated wetland and
isolated vegetated wetland. MNH signed off on the work within their area; most work is outside ConCom
jurisdiction. The existing dwelling will be moved completely out of the buffer, the vacated area will be restored.
Work within ConCom jurisdiction is for the move and restoration. It will be a net benefit by increasing
separation. The I/A septic will also be outside jurisdiction.
Erisman — The plants should all be native species. Would prefer something other than black pine.
Page 3 of 7
ConCom Minutes for August 8. 2018. adopted Aue. 22
Gasbarro — The revegetation is all outside the 25 -foot buffer. He doesn't want to agree to a change to a plan
that is not his. Black Pine is not an invasive species and is salt tolerant.
Steinauer — Black pine spread likes crazy; it acts like an invasive species. It also tends to die quite young.
Erisman — Black pine is a problem in that it is spreading bore beetles.
Gasbarro — He will continue this to talk to the landscape architect Asked for 2 -week continuance.
Staff None
Motion Continued for 2 weeks by unanimous consent.
Vote N/A
B. Amended Orders of Conditions
1. anColson — 9 Hallowell Lane (30-14) SE48-2916
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Docum mtab on Site and topographical plans, photos, requisite departmental reports and correspondence.
Repres tati e Art Gasbarro, Nantucket Engineering & Survey
Public None
Discuss on ( 09) Gasbarro — The portion of the work here is upgrade of the septic and distance to groundwater, he proposing
to use an open -drip -line system. This is within the buffer to a coastal dune. He opened the leach pits and they
were dry; however, he will install tubes eight inches below the surface. This is not a nitrogen sensitive zone.
Staff Recommend this be closed and issued.
Motion Motion to Close and Issue. (made by: Steinauer) (seconded by: Topham)
Vote Carried unanimously
III. PUI ILIC MEETING
A Winor Modifications
1. 31azi r — 57 Madaket Road (41-201.2) SE48-3069
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Docum tati n Site and topographical plans, photos, requisite departmental reports and correspondence.
Represe tati None
Public None
Discussion (5 12) None
Staff This was for construction of an addition; they are applying to reduce the size of the deck.
Motion Motion to Issue as a minor modification. (made by: Champoux) (seconded by: LaFleur)
Vote Carried unanimously
B. Certilcates of Compliance
1. can I Jurphy & Dara Murphy Foundyller — 9 Massachusetts Avenue (60-83) SE48-2406
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff This was for the installation of a tight tank. It was installed in compliance. No on-going conditions.
Recommend it be issued.
Discussi n (5: 3) None
Motion Motion to Issue. (made by: Steinauer) (seconded by: Champoux)
Vote Carried unanimously
2. Nanti icket Conservation Foundation — Madequecham Valley Road Area (77,89,90-2,7,1) SE48-2482
3. Nancket Conservation Foundation — 299 Milestone Road (72-8) SE48-2118
4. Namn cket Conservation Foundation — 2 Squidnet Way (Various) SE48-2475
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff All three of these were large-scale invasive species projects. Recommend issue with on-going methodology
requirements and monitoring reports. Read off specific condition numbers for each project
Discussion (5: 5) None
Motion Motion to Issue for SE48-2482, SE48-2118, and SE48-2475 as recommended. (made by: Steinauer)
(seconded by: Golding)
Vote Carried unanimously
5. Ilaul er, LLC —165 Wauwinet Road (7-1.1) SE48-2932
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff Completed in compliance. Recommend issue with ongoing Condition 22.
Discussi (5:9) None
Motion Motion to Issue as recommended. (made by: Champoux) (seconded by: LaFleur)
Vote Carried unanimously
6. Gleed Thompson & Marian G. Thompson —1A Crow's Nest Way (12-24) SE48-2502
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff This is invalidating this order; work was not done.
Discussion (5: ) None
Motion Motion to Invalidate order. (made by: Champoux) (seconded by: Topham)
Vote Carried unanimously
Page 4 of 7
ConCom Minutes for August 8 2018 adopted Aug. 22
7. Gordan Gund — 3,5,7,11 & 15 Tristram Avenue (31-9,8,7,5,37&2 Respectively) SE48-2692
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff For repair of revetments and other bulkhead related work. Work is in compliance. Recommend issue with
ongoing Conditions 19, 20, 21, 22, 23, 24, 25, 26, 27, and 28. Most relates to monitoring, nourishment, and
reporting.
Discussion (5:20) None
Motion Motion to Issue with ongoing Conditions 19, 20, 21, 22, 23, 24, 25, 26, 27, and 28. (made by: Steinauer)
(seconded by: Champoux)
Vote Carried unanimously
8. Cronyn — 88 Quidnet Road (12-104&109) SE48-2783
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff He verified the system with the Board of Health. Nothing is ongoing.
Discussion (5:23) Jeff Blackwell, Blackwell & Assoc. — This was for a septic system upgrade to I/A.
Motion Motion to Issue. (made by: Steinauer) (seconded by: Champoux)
Vote Carried unanimously
C. Orders of Condition
1. Nantucket Conservation Foundation, Inc. — Pest House Pond (43-155) SE48-3090
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff This was the sliver -nitrate algaecide and phragmites management. He conditioned use of clip and drip and
monitoring. The pipe & to be closed at least 48 hours post treatment. Condition 20 addresses application of
chemicals and Condition 23 requires 24 -hours notice prior to chemical application. Their proposed reporting
requirements and monitoring protocols were incorporated into the permit.
Discussion (5:24) None
Motion Motion to Approve as drafted. (made by: G61ding) (seconded by: Champoux)
Vote Carried unanimously
2. The Nantucket Land Council (NLC) — Nantucket Harbor (N/A) SE48-3092
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff This is the eel grass restoration project. It is a straightforward; he will attach to the order the protocol NLC
submitted. Reviewed the waivers to be issued as they are unusual: work in a sensitive area, the harbor and
closing the area to shellfishing. He will change Condition 19 to "present the annual report."
Discussion (5:29) Golding — Under Condition 19, asked the annual report be written and verbal.
Motion Motion to Approve as amended. (made by: Golding) (seconded by: Steinauer)
Vote Carried unanimously
3. Three Gully Road, LLC — 7 Gully Road (73.3.1-123) SE48-3099
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff Straightforward and no waivers.
Discussion (5:33) None
Motion Motion to Approve as drafted. (made by: Champoux) (seconded by: Steinauer)
Vote Carried unanimously
4. Juliet Hunter — 97 Sankaty Road (49-94) SE48-3100
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff Included a condition of no chemical use three weeks prior to draining the pool and the pool to be drained
outside jurisdiction.
Discussion (5:33) None
Motion Motion to Approve as drafted. (made by: Golding) (seconded by: LaFleur)
Vote Carried unanimously
5. Madaket Sunsets Realty Trust —10 Sheep Pond Road (63-27) SE48-3096
Sitting Bennett, Erisman, Steinauer, LaReur, Champoux, Golding, Topham
Staff Conditioned that all material be removed from the site; will add `irrigation equipment.'
Discussion (5:36) Golding — Wants irrigation included in the removal.
Motion Motion to Approve as amended. (made by: Steinauer) (seconded by: Golding)
Vote Carried unanimously
6. 102 Wauwinet Road Nominee Trust —102 Wauwinet Road (11-24.2) SE48-3097
Sitting Bennett, Erisman, Steinauer, LaFleur, Golding, Topham
Staff Will add Condition 19 requiring the silt fencing along the existing road.
Discussion (5:39) Erisman — Wants the additional silt fence.
Motion Motion to Approve as amended. (made by: Erisman) (seconded by: Topham)
Vote Carried 6-0// Champoux recused
Page 5 of 7
I ConCom Minutes for August 8 2018 adopted Aug.22
7. 37 tarbuck, LLC — 37 Starbuck Road (60-37) SE48-3104
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff Condition 20 will include removal of irrigation equipment. Condition 21 addresses removal of the existing
foundation. He will add Condition 22 requiring a sand volume report
Discuss on ( 41) Erisman — Sand alone doesn't offer a lot of stability; wants a sand nourishment report
Motion Motion to Approve as amended. (made by: LaFleur) (seconded by. Champoux)
Vote Carried unanimously
8. 111 leadow Lane, LLC —11 Meadow Lane (41-448 Lot 6 B) SE48-3098
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff This has the Same pool condition as 97 Sankaty Road about chemicals and draining. He will add Condition 20
preventing work within the 50 -foot buffer.
Discuss on (5:44) None
Motion Motion to Approve as amended. (made by: Champoux) (seconded by: Steinauer)
Vote Carried unanimously
9. Ta 3, LLC — 26 Washington Street (42.3.2-23) SE48-3102
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff This is the same order as previously issued with a new date. Nothing has changed.
Discussion (5 47) None
Motion Motion to Approve as drafted. (made by: Steinauer) (seconded by: Champoux)
Vote Carried unanimously
D. Exte ision Requests
1. Ed and G. Bayliss — 52 Eel Pont Road - Lot 1 (32-25) SE48-2821
2. Edv and G. Bayliss — 52 Eel Point Road - Lot 2 (32-25) NAN-122
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff These are linked; work has started but won't be completed by the deadline date; asking for a lyear extension.
Discuss' n (5:48) None
Motion Motion to Issue a 1 -year extension. (made by: Steinauer) (seconded by: LaFleur)
Vote Carried unanimously
E. Othe r Business
1. Approval of Minutes 07/25/2018: Adopted by unanimous consent.
2. Mondoring Report: Pocomo Neighbors — 47,53,55,57,61,63,67,69 Pocomo Road SE48-2874
Discussi n Art Gasbarro, Nantucket Engineering & Survey — In respect to the top of bank, there is some deviation in the line
(5:50) of that area in the order of a foot or two. At the far east and far west end, noted no particular change. There are
two properties in the middle of this that are not protected. A large bolder near the end has settled, which changed
the top of the bank about five feet. Extra sand was piled at the end with a fiber mat over it; he asked that the mat
be removed as that sand is to be readily available. An area of beach that lost vegetation, owners identified it and
replanting with beach grass is included in the plan. 900 cubic yards (CY) of sand were added to cover the rolls. For
the entire project, we provided 1250 CY of sand. Cobble beach still exists; there is no material difference. The
project is meeting the performance standards and condition of the order. A point of concern is using the
Proprietors Road for the sand delivery; he has been asked to look at using Pocomo Point, which would require an
amended order. Reviewed some of the concerns about using the Proprietors Road; there is no destabilization.
There is some erosion at the two properties that are unprotected; further surveys will show some settling of the
bank to the natural angle of repose.
Obert Shapiro, 57 Pocomo Road — As an abutter to this project, he has suffered consequences. Erosion occurred
adjacent to the mat -covered sand; his property lost beach grass, which was replanted. At first he thought the
roprietors Road was appropriate but he didn't expect a permanent sand chute. Asked the commission to consider
in amendment that moves sand delivery to Pocomo Point. He cannot live with the current set up. Over 40 years
hey lost less than eight feet of the bank; in one year they lost three to four feet adjacent to the sand delivery point
risman — She walks that beach and in the winter it is now narrow. She is concerned allowing trucks and heavy
quipment on the beach would damage the beach and decrease the beach further.
tall— Suggested a site visit so the commission can take a look at the situation with the report in hand.
olding — The sand delivery point is on the west side of Mr. Shapiro's property. Asked if there is evidence of end
tour there.
hapiro — The far ends of the array taper into the adjacent bluff; next to the sand chute, there is no tapering or
oftening.
sbarro — The only point he noticed scour was the area of the rock.
Ft"
all— He will schedule a site visit and put this back on the agenda under monitoring reports.
Page 6 of 7
ConCom Minutes for August 8 2018 adopted Aug. 22
3. Enforcement Actions
a. Sachacha Pond
Sitting Bennett, Erisman, Steinauer, LaFleur, Champoux, Golding, Topham
Staff Department of Public Works was cleaning up after their road repair work but were a little over zealous. He will
send out photos and take a look. If necessary the commission will have to issue an enforcement action.
Discussion (6:13) Golding — They cut through the vegetation on the pond side; that vegetation is gone.
4. Reports:
a. None
5. Commissioners Comment
a. Golding — He's puzzled about when SBPF is coming before the commission to extend the permit for the exiting tube;
it expires in September. Staff — That is rolling into the new application. At the August 22 meeting, we will set the dates
for special hearings on the extended array. The meetings will have a set end time; perhaps two hours.
6. Administrator/Staff Reports
a. None
Adjourned at 6:21 p.m. by unanimous consent.
Submitted by:
Terry L. Norton
Page 7 of 7