The meeting was called to order at 5:00 PM by Chairman Daniel W. Drake with tka; following
Commissioners present, Vice Chair Arthur D. Gasbamo, David C. Gray, Sr., Andrea N. Planzer
and Jeanette D. Topham.
The meeting took place in the 1" Floor meeting room at the Public Safety Facility, 4 Fairgrounds
Rd.
Airport employees present were Thomas M. Rafter, Airport Manager, David Sylvia, Training &
Compliance Coordinator, Noah Karberg, Environmental Coordinator, and Janine Torres, Office
Manager.
Mr. Drake announced the meeting was being recorded.
Mr. Drake asked for comments on the Agenda. Hearing none the Agenda was approved.
Mr. Gray made a Motion to approve the 9/10/13 minutes. Second by Ms. Planer and Passed
Unanimously.
Mr. Gasbarro made a Motion to approve the 8/15/13 Minutes. Second by Mr. Gray and Passed
Unanimously.
Mr. Gasbarro made a Motion to ratify the 9/18/13 Warrant. Second by Ms. Topham and Passed
Unanimously.
Public Comment
Carol Damon asked for an update on the mold found in the flat roof building. Mr. Rafter
responded the building was thoroughly inspected by a qualified contractor who reported the
building does not have a mold issue. Mr. Drake asked Mr. Rafter to follow up with the School
Department to see if they still may be interested in the building.
Pending Leases and Contracts
Mr. Rafter presented one (1) Lease and one (1) contract for approval noting the G J Smith Lease
is not ready for approval:
z ^'
/►
Thomas M. Rafter, A.A.E.,
Airport Manager A Commissioned w
Phone: (508) 325-5300
Daniel W. Drop, C"�man
Fax: (508) 325 -5306
Arthur D. Gasksrm, 45ce CFMir
David C. GrayAr. r O
Andrea N. Plmrzlr o m
Jeannette D. Togham—
3 m
AERPORT COMMISSION MEETING
September 24, 2013 ° 'v
m O
r
The meeting was called to order at 5:00 PM by Chairman Daniel W. Drake with tka; following
Commissioners present, Vice Chair Arthur D. Gasbamo, David C. Gray, Sr., Andrea N. Planzer
and Jeanette D. Topham.
The meeting took place in the 1" Floor meeting room at the Public Safety Facility, 4 Fairgrounds
Rd.
Airport employees present were Thomas M. Rafter, Airport Manager, David Sylvia, Training &
Compliance Coordinator, Noah Karberg, Environmental Coordinator, and Janine Torres, Office
Manager.
Mr. Drake announced the meeting was being recorded.
Mr. Drake asked for comments on the Agenda. Hearing none the Agenda was approved.
Mr. Gray made a Motion to approve the 9/10/13 minutes. Second by Ms. Planer and Passed
Unanimously.
Mr. Gasbarro made a Motion to approve the 8/15/13 Minutes. Second by Mr. Gray and Passed
Unanimously.
Mr. Gasbarro made a Motion to ratify the 9/18/13 Warrant. Second by Ms. Topham and Passed
Unanimously.
Public Comment
Carol Damon asked for an update on the mold found in the flat roof building. Mr. Rafter
responded the building was thoroughly inspected by a qualified contractor who reported the
building does not have a mold issue. Mr. Drake asked Mr. Rafter to follow up with the School
Department to see if they still may be interested in the building.
Pending Leases and Contracts
Mr. Rafter presented one (1) Lease and one (1) contract for approval noting the G J Smith Lease
is not ready for approval:
Wisentaner, Inc. — A twenty (20) year Lease with up to 2 — 5 year renewal options for a
half acre lot located at 74 Bunker Road for $19,166.40 annually with annual CPI
increases and an Annual Business Fee, effective September 15, 2013. Ms. Topham made
a Motion to approve, Second by Mr. Gasbarro and Passed Unanimously.
• G.J. Smith, Inc. — is requesting another modification and not ready for approval. Tenant
is planning a storage unit and has indicated he has received Planning Board approval.
Mr. Rafter indicated he has placed a call to the Planning Office to discuss. It is unclear
whether the Airport's MCD (Major Commercial Development) Permit allows for storage
facilities and is surprised the Planning Office wouldn't have notified the Airport.
• Victor Brandon Corp. — Change Order No I to the Re -Align & Widen South Apron
Taxiway Connector Contract, increasing the contract by $95,080.00, the cost to repaint
the taxiway edge makings on runway 15/33. Mr. Rafter noted the FAA Grant award
included this amount. Mr. Gasbarro made a Motion to approve Change Order No. I to
the Victor Brandon Contract for $95,080.00. Second by Mr. Gray and Passed
Unanimously.
Pending Matters
120412 -3 Existing Bunker Lease Review - Mr. Rafter reported the Tenant has acknowledged
receipt of the Amendment to the Atlantic Aeolus Lease but has not yet responded.
021213 -2 Supplemental Agreement to the Other Transactional Agreement (OTA) —ATCT
Mr. Rafter reported although there was an ATM Article in 2008 for authorization to borrow up to
$4M, no borrowing took place. He is working with the Finance Department to pursue the
borrowing in the next cycle. He is also working with the FAA to determine the actual balance of
the earmark. The original OTA indicates a not to exceed balance of $29M; however reference is
made to other agreements that we cannot locate. MUNIS indicates a balance of $3.7M.
061113 -1 Bunker Area Environmental Permit Review — Mr. Rafter indicated a MESA permit
has been submitted to Natural Heritage.
062513 -3 Noise Abatement — Mr. Rafter reported final comments have been submitted to Jacobs
on the Noise Brochure. New APU use signs have been received however the high lift needed to
install the signs is temporarily out -of- service.
070913 -1 Memorandum of Understanding (MOM Update — Mr. Rafter reported not yet
having a draft for review.
081313 -5 MOD with SDO /OSD re Disadvantaged Business Enterprise (DBE) Program —
Mr. Rafter reported the initial concern over the agreement was that it would require the airport to
pay a percentage of DOT grant monies to the DBE program but didn't specify a formula or cap or
other controls. A conference call was held with MassDot indicated the airports had signed a
previous MOU in 2002; however that document included an attachment which gave the
information in question. MassDOT has agreed to add a similar attachment to the new MOU.
Subsequently, Hyannis Airport had requested some language changes as well. A new document
is expected addressing all the concerns.
GA/Administration Building Project Update
Mr. Rafter gave an update of the progress made since the last meeting: electrical shed has been
moved, temporary fence has been removed, entry doors we working and fast floor kitchen
counters have been installed. Plumbing work is still needed. Lockers have yet to be installed.
Curbing has been delivered but finish site work has not been started.
9.24.13 Airport Commission Minutes Page 2 of 5
Concern remains over slow progress being made. Mr. Rafter noted another schedule has been
received indicating an October 2& completion date. Mr. Drake asked that the revised schedule
be shared with the Commission.
Finance
Mr. Rafter reported the new LEO (Law Enforcement Officer) Reimbursement Agreement was
received from TSA indicating a $98,550 reimbursement award for the required service. This is
lower than last year's Agreement which was slightly over $100K.
The Finance Departments instruction on FY15 budget preparation is expected by the end of the
week. A tentative timeline for the budget process was distributed.
Mr. Drake reminded the Commission as a whole makes up the Airport's Finance Sub - Committee
and suggested the bulk of the next meeting be spent on the budget process to familiarize everyone
with the process. Everyone agreed.
Mr. Rafter reported receiving a draft Reimbursable Agreement from the FAA for the
PAPDREI S installation on RW 33. Mr. Rafter is requesting some additional language regarding
the reimbursement amount and timeline be included. 90% drawings were also received.
022613 -2 Master Plan and Sustainability Program Update — Mr. Rafter reported both the
Noise Brochure and Advisory Committee participants are being finalized. A Jacobs's in -house
meeting is planned for September 26th and they have been asked to review some concerns raised
at a Coastal Management Work Plan Group meeting concerning beach erosion and potential
impact to Runway 6.
Mr. Rafter will share the list of Advisory Committee participants when finalized.
062513 -1 Re -Align and Widen Taxiway (Delta) Connector Update — Mr. Rafter reported the
project is progressing on time within its thirty (30) day schedule. The old taxiway has been
removed and conduit is being laid. The relocated plants are being watered regularly.
Manager's Report
Projects Update
Mr. Rafter reported:
• Passenger Facility Charge (PFC): Consultant has provided preliminary documents
detailing the $7.5M of eligible project costs being applied for on the PFC application as
well as the draft letter notifying the users (airlines). The documents are currently under
review by the FAA. The projects included are the Terminal, the Taxiway Connector
project currently underway, the Master Plan and the PFC Consulting. The documents
project collection of a $4.50 PFC through 12/2024. Mr. Rafter will forward the
documents to the Commission. Once the FAA approves the documents, a date will be
set for the consultation meeting with the users and the letters will be sent. Mr. Drake
requested the Commission be notified as soon as that date is set to determine
Commission attendance and the possible need to post the meeting.
• Runway 6 PAPIBEILS: FAA held a pre - construction meeting and the decision was made
to postpone construction until October as opposed to simultaneous with the Taxiway
Connector project.
RFPBid Status
• Engineering RFQ is still under internal review.
• Fuel RFP is almost complete noting Diane O'Neill has been very helpful in working over
the weekend to provide comments.
9.24.13 Airport Commission Minutes Page 3 of 5
Operations Update
• Mr. Rafter provided a draft of the Airport's Annual Report due to the Town on Friday.
Mr. Drake has provided his feedback and any other comments are needed as soon as
possible.
• The FAA CIP (Capital Improvement Plan) meeting is scheduled for October 106 in
Hyannis. Jacobs will be onsite October 1" for a preliminary meeting.
• Continuing to draft a fuel incentive program and hope to have for the next meeting.
• A webins r took place to review the RFP for the Carbon Neutral program. An
internal/legal review will be the next step. An Article will be required at ATM for this.
• Fire training took place on Monday and two personnel will be attending advanced ARFF
training in Pittsburgh next week.
Statistics
• Operations are down 6.02% for August and down 9.8% over last Fiscal Year. Air Carrier
operations are up slightly while Air Taxi and GA operations are down slightly. Mr.
Sylvia added the total operations for August were 17,761 compared to 18,899 in August
2012.
• Enplanements for August were 35,758, up 8.85% over August 2012 at 32,852. Mr.
Rafter noted the continuing trend of fewer operations but increased passengers indicates
larger aircraft with fewer trips or full planes with fewer trips noting JetBlue's increase in
both the Boston market as well as the NY market.
• Freight for the month of August was 311,070 Ibs, down 10.48% from last August.
Discussion moved to the significant decrease in GA Operations. Mr. Rafter noted some
additional analysis is needed to determine if it is mostly corporate jet traffic seeing that fuel sales
have declined. Additionally small GA traffic has also decreased. Mr. Rafter intends to look at
some incentives that may entice some traffic back.
Mr. Gray asked if the decrease in fuel sales was related to the landing fees. Mr. Rafter responded
possibly but noted revenue as a whole has increased. Mr. Rafter added the first phase of the fuel
incentive program will be towards commercial operators.
To respond to Mrs. Topham, Mr. Rafter noted fuel prices are compared to area airports but the
Nantucket has added delivery costs to factor in.
Sub - Committee Reports
Ms. Topham shared the minutes from the Town's Personnel Compensation Review Committee
meeting of 8/14/13 noting the next meeting is scheduled for October 10 °i. The last meeting on
9/16/13 convened in Executive Session to meet with Labor Counsel who presented strategies for
collective bargaining negotiations. Mr. Drake asked if the Committee will be advising the Town
on collective bargaining strategy to which Ms. Topham responded not really, each Department
will still be responsible for the negotiations. Mr. Drake thought perhaps the same presentation
could be given to the Commission prior to upcoming negotiations. Mr. Drake suggested
everyone look at the minutes provided and share comments or questions at the next meeting.
Commissioner's Comments
Mr. Gray noted the crosswalk in front of the terminal has some loose bricks.
Mr. Gray remarked of issues that have risen for the flight students trying to obtain an airport ID
badge. Mr. Rafter indicated a TSA representative met with Mr. Tallman to review options. Mr.
Tallman plans on modifying the Security Plan in order to accommodate the students.
9.24.13 Airport Commission Minutes Page 4 of 5
Public Comment
None.
Mr. Gasbarro made a Motion to enter into Executive Session, not to reconvene in open session,
to pursuant to M.G.L. c.30A, §21(a) clause 3 and 6, to consider the purchase, exchange, lease or
value of real property and to discuss pending litigation to Garin v. Town. The Chair has
determined that an open session may have a detrimental effect on the negotiating and/or litigation
position of the Airport Commission, and Clause 3, to discuss strategy with respect to threatened
litigation with respect to the completion of the GA Building. The Chair has determined that an
open session may have a detrimental effect on the litigation position of the Airport Commission.
Second Mr. Gray and Passed by the following roll -call vote:
Mr. Drake — Aye
Mr. Gasbarro —Aye
Ms. Topham — Aye
Mr. Gray —Aye
Ms. Planar —Aye
Meeting adjourned at 5:38 PM.
Respectfully submitted,
tia a ..
R. v
4M Ja,,n. Tortes, Recorder
Muster List of Documents
September 24, 2013 Agenda including Exhibit 1
August 27, 2013 Draft Minutes
September 10, 2013 Draft Minutes
Wisemmmer Inc. Lease
G.J. Smith Lease
Victor Brandon Corp Change Order No 1 to Taxiway Connector Contract
Architectural Consulting Group August 2013 Monthly Summary Report GA Bldg (Handout)
TON FY2015 Budget Timeline including 9/24/13 Email from M. Anguelov to Rafter (Handout)
Airport Manager Annual Report FY2013 (Handout)
August 2013 Airport Statistics
TON Personnel Compensation Review Committee 9/16/13 Agenda and 8/14/13 Minutes
9.24.13 Airport Commission Minutes Page 5 of 5