HomeMy WebLinkAboutWoodard and Curran Monthly Update October 7, 2013_201401231106509371TOWN OF NANTUCKET, MASSACHUSETTS
Monthly Update
WOODARD & CURRAN 1 of 4
OCTOBER 7, 2013
Projects
223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Begin Surfside infiltration bed loading evaluation included site visit by hydrogeologist
Contracted FAA site assessor to support Town on land negotiations
Started FAA appraisal process
This Month:
Meet with Town Appraisers and GSA Appraisers (might be delayed due to Federal
Government shutdown)
Continue with Surfside Discharge Bed Reload Evaluation
Complete Surfside WWTF Capacity Analysis
Schedule Projected completion date – December 31, 2013
Financial Phase 1 Budget - $348,630 Spent - $290,480
Town Action (s) Required:
Work with assessor on FAA site
225139 CWMP Update
Progress Last Month:
Reviewed Town Sewer District unconnected properties
Drafted Stormwater recommendations for Nantucket Harbor
Initiated FAA Appraisal process
Filed Stormwater Master Plan CY2014 PEF
This Month:
Review of Hummock Pond MEP Draft – Modeling
Plan for Public Meeting to present results of Hummock Pond MEP Draft
Town of Nantucket, Massachusetts
Project Update
October 7, 2013
WOODARD & CURRAN 2 of 4
Finalize Model Runs with SMAST
Review of Draft Stormwater Plan for Nantucket Harbor MEP with DPW Director
Review of Draft Public Outreach Plan for Fall 2013 with DPW Director
Continue with Report Compilation
Schedule Projected completion date – December 2013
Financial Budget - $616,000 Spent: $ 355,652
Town Action (s) Required:
Send copy of approved Amendment No. 1
226494 Jetties Support Update
Progress Last Month:
Continue with ACOE Coordination
Survey completed.
Continue coordination with Dave Fronzuto for local conditions
This Month:
Actual design to start fall 2013
Prepare agenda for meeting with Town, SSA and Hyline to discuss construction
scheduling in late October, early November 2013
Schedule Projected Jetties Reconstruction Bid-Winter 2014
Projected Contractor Bid Award early May 2014.
Financial Budget - $20,000 Spent: $ 18,586
Town Action (s) Required:
Working on amendment to original contract to complete this work
Town of Nantucket, Massachusetts
Project Update
October 7, 2013
WOODARD & CURRAN 3 of 4
225139 Miacomet Pond Flood Mitigation Study
Progress Last Month:
Contract signed by Board of Selectmen
This Month:
Internal Kick off meeting for project team
Data Collection and Compilation.
Schedule Projected completion date – March 21, 2014
Financial Engineering Budget - $125,800 Spent - $0
Town Action (s) Required:
Provide Woodard & Curran copies of historical documents
225140 Phase IIB Sewer and Water Main Rehabilitation Project
Progress Last Month:
Held meeting on 9/11 to kickoff second season of Phase IIB construction
Additional water work added by Wannacomet on Fair St., Ash St., Madison
Alley
Directional drill discussed for Ash St., Ash Lane to minimize impacts from
utility trenches to existing roadway.
Mobilization and use of the Jetties as a staging area began on 9/17
Construction on Ash Street and Ash Lane began week of 9/23
This Month:
Work to continue on Ash Lane through 10/7, and move onto Academy Lane and Gay
Street for sewer and water replacement during week of 10/14.
Meetings to be scheduled and held with Steamship Authority and various Town
Administration entities to discuss schedule, and traffic diversion plans.
Schedule Projected completion date – October 2014
Financial Engineering Budget - $921,700 Spent - $615,542
Construction Bid - $3,749,396.31 Spent - $, 1,546,523.24
Town of Nantucket, Massachusetts
Project Update
October 7, 2013
WOODARD & CURRAN 4 of 4
Town Action (s) Required:
Work with Woodard & Curran to coordinate with local businesses and residents during construction
Provide support as needed in field for utility identification
225839 Surfside WWTF Assessment and Upgrades
Progress Last Month:
Corrosion Control/Headworks Screen/Odor Control System and Vactor Unloading
area– Completed draft recommendation and probable estimated costs for design and
construction for discussion and finalization with DPW Director and Surfside WWTF
Chief Operator.
This Month
Attend meeting with DPW Director and the Surfside WWTF Chief Operator to review
the recommendations and probable costs for the Corrosion Control, Headworks
Screen, Odor Control System and Vactor unloading area.
Schedule Projected completion date – December 2014
Financial Budget - $110,000 Spent -$66,829
Town Action (s) Required:
Attend meeting on recommendations for treatment plant upgrades
What to look for this month:
Construction on Phase II B Water and Sewer Replacement on Ash Street and Academy
Lane