223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Continued under Madaket Amendment No. 1 assessing alternative routes and
identification of construction challenges for each proposed route.
Continued work with Madaket site surveys – Massachusetts Historical Commission
(PAL). Reviewing scope and budget for botanist oversight as required by NHESP.
This Month:
Continue assessing alternative routes
Continue Massachusetts Historical Commission site survey
Surfside assessment to begin October 2012.
Schedule Projected completion date – December 31, 2012 (Unchanged)
Financial Phase 1 Budget - $348,630 Spent - $ 136,000
225139 CWMP Update
Progress Last Month:
Incorporating BOH records into GIS
Working on HP MEP
Met with Sewer Planning work group and developed schedule moving forward
Finalized updated needs/study areas map
Working to develop existing/build out flows in Town Sewer District
Developing flows/loads in existing needs areas
Finalized BOH ACO
Town of Nantucket, Massachusetts
Project Update
October 1, 2012
WOODARD & CURRAN 2 of 3
This Month:
Continue public outreach
Finalize flows and loads from updated needs/study areas
Finalize SMAST Water Quality contract to Town – Sesechacha
Work with BOH to implement Septic ACO template
Worked with Town’s Energy Consultant and NatGrid for NatGrid to continue
evaluations for energy efficiencies.
Working with Marine & Coastal Resources – Hummock Pond MEP
Schedule Projected completion date – December 2013
Financial Budget - $571,000 Spent: $112,100
Town Action (s) Required:
Develop mission statement with members of CWMP Sewer Planning Work Group,
setup schedule and format for Group and Public meetings, develop list of CWMP
topics for discussion
Town to review and confirm maps of needs areas.
225140 Phase IIB Sewer Rehabilitation Project
Progress Last Month:
Prepared updated Probable Construction Cost Estimate for DPW and Wannacomet
Water Company.
Continued field investigations and survey for design
Continue to coordinate with Wannacomet Water Company
Continued preparation of draft specifications.
Submitted Notice of Intent and attended Conservation Commission meeting and
received Order of Conditions for project.
Finalized Street and Sidewalk Committee meetings
Submitted Project Notification form to Massachusetts Historical Commission
Attended September 12, 2012 Board of Selectmen meeting
Completed survey of Fair Street
Submitted 30% plans and specifications to MADEP for review under the SRF program
requirements.
This Month:
Attendance at October 15, 2012 Neighborhood Meeting
Town of Nantucket, Massachusetts
Project Update
October 1, 2012
WOODARD & CURRAN 3 of 3
Schedule Projected completion date – December 2014
Bidding process to begin October 31, 2012
Financial Budget - $921,700 Spent - $128,900
Town Action (s) Required:
Finalize memo summarizing Street and Sidewalk Committee meetings.
225140 Sheep’s Pond Road Support
Progress Last Month:
Finalized Scope of Work and received Notice to Proceed for support associated with
Natural Heritage and Endangered Species permitting and survey.
Began Botanical Review for project area.
This Month:
Continue and finalize Botanical Review for project area.
Schedule Projected completion date – December 2012
Financial Budget - $7,000 Spent - $4,500
What to look for this month:
Phase IIB survey work along Westminster Ave., Hussey St. and to continue.
Additional Services
Developed an approach to assist DPW Director with Surfside/Siasconset operations
and plant facilities challenges and submitted proposal to the Town.