HomeMy WebLinkAboutWoodard and Curran Monthly Update August 17, 2012_201401231106485153TOWN OF NANTUCKET, MASSACHUSETTS Monthly Update WOODARD & CURRAN 1 of 3 AUGUST 17, 2012 Projects 223970 Madaket Wastewater Treatment Facility & Collection System Phase 1 - Preliminary Design Phase Progress Last Month: Continued under Madaket Amendment No. 1 assessing alternative routes and identification of construction challenges for each proposed route. Continued work with Madaket site surveys – Massachusetts Historical Commission (PAL). Reviewing scope and budget for botanist oversight as required by NHESP. This Month: Continue assessing alternative routes Continue Massachusetts Historical Commission site survey Schedule Projected completion date – December 31, 2012 (Unchanged) Financial Phase 1 Budget - $348,630 Spent - $ 131,780 Town Action (s) Required: DPW Director discussions with consultant and Town Staff on viability of alternative routes, construction impacts, development and sewer district impacts. 225139 CWMP Update Progress Last Month: Developed summer associations/ civic groups/ environmental, etc. organizations meeting schedule/assign presenters/prepare agendas. Conducted BOH records review Conducted UMass Field Station Representative meeting Attended Hummock Pond Neighborhood Association meeting Assisted Town in formulating criteria for Sewer Planning work group Town of Nantucket, Massachusetts Project Update August 17, 2012 WOODARD & CURRAN 2 of 3 This Month: Continue attending and presenting at summer meetings Finalize maps of needs areas Submit SMAST Water Quality contract to Town – Sesechacha Work with BOH to advance Septic ACO template Schedule Projected completion date – December 2013 Financial Budget - $571,000 Spent: $82,900 Town Action (s) Required: Develop mission statement with members of CWMP Sewer Planning Work Group, setup schedule and format for Group and Public meetings, develop list of CWMP topics for discussion Town to review and confirm maps of needs areas. 225140 Phase IIB Sewer Rehabilitation Project Progress Last Month: Finalized and signed subconsulting contract with Blackwell & Associates Inc. for survey update. Began field investigations and survey for design Drafted Design Basis Report Began preparation of draft specifications. Began preparation of Notice of Intent Met with Street and Sidewalk Committee representative on July 25, 2012 Met with Historical District Agent on July 25, 2012 This Month: Finalize Design Basis Report Continue coordination with DPW, Wannacomet Water Company, Streets and SidewalksCommittee, Conservation Commission and Historic District Commission Begin development of project plans Schedule Projected completion date – December 2013 Town of Nantucket, Massachusetts Project Update August 17, 2012 WOODARD & CURRAN 3 of 3 Financial Budget - $921,700 Spent - $61,387 Town Action (s) Required: Review and comment on Design Basis Report Newsworthy First meeting of CWMP Sewer Planning Work Group September 12th. What to look for this month: Phase IIB survey work along Fair Street, Westminster Ave., Hussey St. and India St. CWMP Update attendance at summer meetings of taxpayers, civic and association meetings. Attendance at Board of Health ACO meeting August 30th Additional Services Developed an approach to assist DPW Director with Surfside/Siasconset operations and plant facilities challenges and submitted proposal to the Town. Executed contract with botanist for Sheep Pond Road for survey and permit.