HomeMy WebLinkAboutWoodard and Curran Monthly Update 20150121_201502271201011643TOWN OF NANTUCKET, MASSACHUSETTS
Monthly Update
WOODARD & CURRAN 1 of 3
JANUARY 21, 2015Projects
223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Final appraisals submitted to GSA. Awaiting call from GSA Director John Kelly for on
Island meeting and discussion of GSA Offer.
MassDEP verbal approval of Groundwater Discharge Permit Modification additional
information on survey submitted.
This Month:
Receive final approval of Groundwater Discharge Permit Modification.
Waiting for meeting with GSA on property
Schedule Projected completion date – December 2015.
Financial Phase 1 Budget - $373,630 (including Amendments) Spent - $ 366,257
Town Action (s) Required:
Follow up with GSA and Town Appraiser process.
225139 CWMP Update
Progress Last Month:
Presented CWMP Update to Board of Selectmen
This Month:
Meet with Town to discuss SPWG for implementation and future public outreach
Schedule Projected completion date – Completed
Financial Budget - $616,000 Spent: $616,000
Town Action (s) Required:
Next steps are public outreach for CWMP Implementation.
Town of Nantucket, Massachusetts
Project Update
January 21, 2015
WOODARD & CURRAN 2 of 3
226494 Sewer Planning Work Group Support
Progress Last Month:
Attended first of three workshops to present CWMP Recommended plan to workgroup
This Month:
Attend second workshop to present project costs and begin cost recovery discussions
Schedule Project Completion Date June 2015
Financial Budget - $ 20,000 Spent: $ 16,315
Town Action (s) Required:
Schedule final workshop to discuss public education program
226494 Jetties Support Update
Progress Last Month:
All Activities on hold until further budgets are approved
This Month:
Coordinate efforts with Town on public outreach
Coordinate With ACOE on Design Schedule
Schedule Projected Jetties Reconstruction Bid-Winter 2014
Projected Contractor Bid Award early May 2015.
Financial Budget - $20,000 Spent: $ 18,586
Town Action (s) Required:
Meet with Town to discuss further jetties support
Town Action (s) Required: None
225140 Phase IIB Sewer and Water Main Rehabilitation Project
Progress Last Month:
Project Substantial completion December 19, 2014
This Month:
Final Payment Requests
Begin work on Record Drawings
Town of Nantucket, Massachusetts
Project Update
January 21, 2015
WOODARD & CURRAN 3 of 3
Schedule Projected completion date – December 2015 (contract time to be extended to cover one year
warranty period and also record drawings).
Financial Engineering Budget - $1,523,040 Spent - $ 1,279,867
Construction Bid - $5,715,914 (including change orders executed), Spent - $ 5,568,805
Town Action (s) Required:
Coordinate with Residents for disconnection of known inflow sources on Ash St.