Loading...
HomeMy WebLinkAboutWoodard and Curran Monthly Update 20150121_201502271201011643TOWN OF NANTUCKET, MASSACHUSETTS Monthly Update WOODARD & CURRAN 1 of 3 JANUARY 21, 2015Projects 223970 Madaket Wastewater Treatment Facility & Collection System Phase 1 - Preliminary Design Phase Progress Last Month: Final appraisals submitted to GSA. Awaiting call from GSA Director John Kelly for on Island meeting and discussion of GSA Offer. MassDEP verbal approval of Groundwater Discharge Permit Modification additional information on survey submitted. This Month: Receive final approval of Groundwater Discharge Permit Modification. Waiting for meeting with GSA on property Schedule Projected completion date – December 2015. Financial Phase 1 Budget - $373,630 (including Amendments) Spent - $ 366,257 Town Action (s) Required: Follow up with GSA and Town Appraiser process. 225139 CWMP Update Progress Last Month: Presented CWMP Update to Board of Selectmen This Month: Meet with Town to discuss SPWG for implementation and future public outreach Schedule Projected completion date – Completed Financial Budget - $616,000 Spent: $616,000 Town Action (s) Required: Next steps are public outreach for CWMP Implementation. Town of Nantucket, Massachusetts Project Update January 21, 2015 WOODARD & CURRAN 2 of 3 226494 Sewer Planning Work Group Support Progress Last Month: Attended first of three workshops to present CWMP Recommended plan to workgroup This Month: Attend second workshop to present project costs and begin cost recovery discussions Schedule Project Completion Date June 2015 Financial Budget - $ 20,000 Spent: $ 16,315 Town Action (s) Required: Schedule final workshop to discuss public education program 226494 Jetties Support Update Progress Last Month: All Activities on hold until further budgets are approved This Month: Coordinate efforts with Town on public outreach Coordinate With ACOE on Design Schedule Schedule Projected Jetties Reconstruction Bid-Winter 2014 Projected Contractor Bid Award early May 2015. Financial Budget - $20,000 Spent: $ 18,586 Town Action (s) Required: Meet with Town to discuss further jetties support Town Action (s) Required: None 225140 Phase IIB Sewer and Water Main Rehabilitation Project Progress Last Month: Project Substantial completion December 19, 2014 This Month: Final Payment Requests Begin work on Record Drawings Town of Nantucket, Massachusetts Project Update January 21, 2015 WOODARD & CURRAN 3 of 3 Schedule Projected completion date – December 2015 (contract time to be extended to cover one year warranty period and also record drawings). Financial Engineering Budget - $1,523,040 Spent - $ 1,279,867 Construction Bid - $5,715,914 (including change orders executed), Spent - $ 5,568,805 Town Action (s) Required: Coordinate with Residents for disconnection of known inflow sources on Ash St.