HomeMy WebLinkAboutWoodard and Curran Monthly Update 20141204_201502271159322893TOWN OF NANTUCKET, MASSACHUSETTS
Monthly Update
WOODARD & CURRAN 1 of 2
DECEMBER 4, 2014Projects
223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Final appraisals submitted to GSA. Awaiting call from GSA Director John Kelly for on
Island meeting and discussion of GSA Offer.
MassDEP verbal approval of Groundwater Discharge Permit Modification additional
information on survey submitted.
This Month:
Receive final approval of Groundwater Discharge Permit Modification.
Waiting for meeting with GSA on property
Schedule Projected completion date – December 2014. (This may need to be extended since the GSA
meeting date is yet undetermined)
Financial Phase 1 Budget - $373,630 (including Amendments) Spent - $ 359,467
Town Action (s) Required:
Follow up with GSA and Town Appraiser process.
225139 CWMP Update
Progress Last Month:
Presented CWMP Update to Board of Selectmen
This Month:
Meet with Town to discuss SPWG for implementation and future public outreach
Schedule Projected completion date – November 2014
Financial Budget - $616,000 Spent: $603,639
Town Action (s) Required:
Follow up with GSA and Town Appraiser process.
Town of Nantucket, Massachusetts
Project Update
December 4, 2014
WOODARD & CURRAN 2 of 2
226494 Jetties Support Update
Progress Last Month:
All Activities on hold until further budgets are approved
This Month:
Coordinate efforts with Town on public outreach
Coordinate With ACOE on Design Schedule
Schedule Projected Jetties Reconstruction Bid-Winter 2014
Projected Contractor Bid Award early May 2015.
Financial Budget - $20,000 Spent: $ 18,586
Town Action (s) Required:
Meet with Town to discuss further jetties support
Town Action (s) Required: None
225140 Phase IIB Sewer and Water Main Rehabilitation Project
Progress Last Month:
Fair St. Reconstruction to continue
Lower Broad St. paving to begin
Granite Curbing at Town Hall and Crosswalk paving completed
Quince and Westminster paving completed
This Month:
Fair St. Pavement completed
Broad St. Pavement completed
Begin striping of roads and cleanup and final watertight manhole covers to be installed
Schedule Projected completion date – December 2014 (contract time to be extended to cover one year
warranty period and also record drawings).
Financial Engineering Budget - $1,523,040 Spent - $ 1,237,123
Construction Bid - $4,855,467.25 (including change orders executed), Spent - $4,755,467.25.
Town Action (s) Required:
Coordinate with Residents for disconnection of known inflow sources.