Loading...
HomeMy WebLinkAboutWoodard and Curran Monthly Update 20141204_201502271159322893TOWN OF NANTUCKET, MASSACHUSETTS Monthly Update WOODARD & CURRAN 1 of 2 DECEMBER 4, 2014Projects 223970 Madaket Wastewater Treatment Facility & Collection System Phase 1 - Preliminary Design Phase Progress Last Month: Final appraisals submitted to GSA. Awaiting call from GSA Director John Kelly for on Island meeting and discussion of GSA Offer. MassDEP verbal approval of Groundwater Discharge Permit Modification additional information on survey submitted. This Month: Receive final approval of Groundwater Discharge Permit Modification. Waiting for meeting with GSA on property Schedule Projected completion date – December 2014. (This may need to be extended since the GSA meeting date is yet undetermined) Financial Phase 1 Budget - $373,630 (including Amendments) Spent - $ 359,467 Town Action (s) Required: Follow up with GSA and Town Appraiser process. 225139 CWMP Update Progress Last Month: Presented CWMP Update to Board of Selectmen This Month: Meet with Town to discuss SPWG for implementation and future public outreach Schedule Projected completion date – November 2014 Financial Budget - $616,000 Spent: $603,639 Town Action (s) Required: Follow up with GSA and Town Appraiser process. Town of Nantucket, Massachusetts Project Update December 4, 2014 WOODARD & CURRAN 2 of 2 226494 Jetties Support Update Progress Last Month: All Activities on hold until further budgets are approved This Month: Coordinate efforts with Town on public outreach Coordinate With ACOE on Design Schedule Schedule Projected Jetties Reconstruction Bid-Winter 2014 Projected Contractor Bid Award early May 2015. Financial Budget - $20,000 Spent: $ 18,586 Town Action (s) Required: Meet with Town to discuss further jetties support Town Action (s) Required: None 225140 Phase IIB Sewer and Water Main Rehabilitation Project Progress Last Month: Fair St. Reconstruction to continue Lower Broad St. paving to begin Granite Curbing at Town Hall and Crosswalk paving completed Quince and Westminster paving completed This Month: Fair St. Pavement completed Broad St. Pavement completed Begin striping of roads and cleanup and final watertight manhole covers to be installed Schedule Projected completion date – December 2014 (contract time to be extended to cover one year warranty period and also record drawings). Financial Engineering Budget - $1,523,040 Spent - $ 1,237,123 Construction Bid - $4,855,467.25 (including change orders executed), Spent - $4,755,467.25. Town Action (s) Required: Coordinate with Residents for disconnection of known inflow sources.