HomeMy WebLinkAboutWoodard and Curran Monthly Update 20140502_201502271159298830TOWN OF NANTUCKET, MASSACHUSETTS
Monthly Update
WOODARD & CURRAN 1 of 5
MAY 2, 2014
Projects
223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Coordinating GSA and Town Appraisers for final assessment of land
Continued conversations with MassDEP to provide additional information requested to
obtain a response to Groundwater Discharge Permit Modification and Hydrogeological
evaluation for additional loading to Surfside Discharge Beds
Provided capacity assessment memo with findings and recommendations for Town to
review.
This Month:
Working with appraisers with comps utilized by both Town and GSA in valuation on
FAA site
Will coordinate May 15 delivery to GSA of LandVest appraisal
Working with MassDEP on Groundwater Discharge Permit Modification. MassDEP
has asked for additional tasks relating to hydrogeological work from W&C
Working on energy memo for Surfside Treatment plant
Putting together amendment to scope of work for Town
Schedule Projected completion date – March 2014.
Financial Phase 1 Budget - $348,630 Spent - $ 342,134.15
Town Action (s) Required:
Review and provide comments on the capacity assessment memo.
Address amendment request based on additional tasks
Town of Nantucket, Massachusetts
Project Update
May 2, 2014
WOODARD & CURRAN 2 of 5
225139 CWMP Update
Progress Last Month:
Followed up on BRP WP 83 – Hydrogeological Evaluation for Surfside beds to support
additional loading. Discussions with MassDEP and some additional work will be
coordinated between the Department and W&C on the monitoring plan.
Followed up on BRP WP 11- Surfside Groundwater Discharge Permit Modification to
support additional loading. MassDEP has given a verbal approval to revised permit.
Worked with Town to forecast April 15 opening of Hummock Pond. Based on
recommendations in MEP Report, Pond opening was a success.
Continued to work with SMAST finalizing model runs in Nantucket Harbor
Reviewed of Draft Public Outreach Plan for Fall/Winter 2013 with Town
Continued with report compilation
Continued To evaluate energy efficiency measures.
Reviewed Flows and Loads with DPW Director and SPWG
Met with SPWG via phone call on April 4, 2014
This Month:
Continue to compile and review draft report sections
Develop cost benefit estimates for Energy Efficiency Study and provide memo for
Town review
Receive results of additional models for Nantucket and Polpis Harbor with SMAST
Review Fertilizer Regulation and impact in Nantucket Harbor Watershed For TMDLs
as well as overall Town In Nitrogen sensitive areas
Deliver Town’s final appraisal to GSA to initiate transfer process
Set meetings with MassDEP and MEPA Office on future filings
Meet with Town to discuss CWMP implementation and public outreach
Schedule Projected completion date – July 2014
Financial Budget - $616,000 Spent: $ 521,100.18
Town Action (s) Required:
Review and provide comments on the Energy Efficiency Study memo.
GSA and Town Appraiser process
226494 Jetties Support Update
Progress Last Month:
All Activities on hold until further budgets are approved
Town of Nantucket, Massachusetts
Project Update
May 2, 2014
WOODARD & CURRAN 3 of 5
This Month:
Coordinate efforts with town on public outreach
Coordinate With ACOE on Design Schedule
Schedule Projected Jetties Reconstruction Bid-Winter 2014
Projected Contractor Bid Award early May 2014.
Financial Budget - $20,000 Spent: $ 18,586
Town Action (s) Required:
Meet with Town to discuss further jetties support
224428 Miacomet Pond Watershed Study
Progress Last Month:
Compiled information obtained for Planning Department
Finalized watershed delineation
Conducted interview with owner on Allen Lane
Completed analysis of land use changes
This Month:
Schedule Projected completion date – May 2014. Date extended due to weather impacting field
investigations and to ensure time to meet with stakeholders.
Financial Engineering Budget - $125,800 Spent - $19,839
Town Action (s) Required:
None at this time
Town of Nantucket, Massachusetts
Project Update
May 2, 2014
WOODARD & CURRAN 4 of 5
225140 Phase IIB Sewer and Water Main Rehabilitation Project
Progress Last Month:
South Water Street, sewer stormwater and drainage installation completed.
Sewer main construction continued on Quince Street.
Roadway paving preparations began on South Water Street and Broad Street.
This Month:
Finalize binder paving on South Water Street and Broad Street.
Complete sewer main and service connections on Quince Street.
Complete site cleanup in preparation for Daffodil Days.
Prep roadways for final paving to be completed during Fall 2014.
Schedule Projected completion date – October 2014
Financial Engineering Budget - $1,070,720 Spent - $726,260
Construction Bid - $4,005,467.25 (including change orders executed), Spent - $3,459,552.25
Town Action (s) Required:
Work with Woodard & Curran to coordinate with local businesses and residents during construction
Provide support as needed in field for utility identification
225839 Surfside WWTF Assessment and Upgrades
Progress Last Month:
Provided memo on screenings assessment for Town review.
This Month
Develop plan for additional operational assistance to pilot running the plant with one
train of the advanced treatment system off-line.
Schedule Projected completion date – December 2014
Financial Budget - $110,000 Spent -$100,000
Town Action (s) Required: None
Review and provide comment on the screenings assessment memo
Town of Nantucket, Massachusetts
Project Update
May 2, 2014
WOODARD & CURRAN 5 of 5
What to look for this month:
Construction on Phase II B Water, Sewer and Drainage work on Broad Street