HomeMy WebLinkAboutWoodard and Curran Monthly Update 20140312_201502271154497580TOWN OF NANTUCKET, MASSACHUSETTS
Monthly Update
WOODARD & CURRAN 1 of 5
MARCH 12, 2014
Projects
223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Continued communication with GSA and Town Appraisers
Waiting for MassDEP response to Groundwater Discharge Permit Modification and
Hydrogeological evaluation for additional loading to Surfside Discharge Beds
Prepared cost estimates for additional aeration and modifications to nitrate recycle
system.
Coordinated with Surfside Operations Staff and made the decision to proceed without
the additional process data. Surfside staff does not have the resources at this time to
gather the data.
Finalized capacity assessment memo.
This Month:
Provide capacity assessment memo with findings and recommendations for Town to
review
Schedule Projected completion date – March 2014.
Financial Phase 1 Budget - $348,630 Spent - $ 341,221
Town Action (s) Required:
Set meeting with GSA and Town Appraiser on FAA site
Review and provide comments on the capacity assessment memo.
225139 CWMP Update
Progress Last Month:
Filed BRP WP 83 – Hydrogeological Evaluation for Surfside beds to support additional
loading
Town of Nantucket, Massachusetts
Project Update
March 12, 2014
WOODARD & CURRAN 2 of 5
Filed BRP WP 11- Surfside Groundwater Discharge Permit Modification to support
additional loading
Held SMAST Public Meeting to present results of Hummock Pond MEP Draft
Continued to work with SMAST on model runs in Nantucket Harbor
Reviewed Draft Stormwater Plan for Nantucket Harbor with DPW
Reviewed of Draft Public Outreach Plan for Fall/Winter 2013 with DPW Director
Continued with report compilation
Continued To evaluate energy efficiency measures.
Reviewed Flows and Loads with DPW Director
Reviewed EDUs for each Needs Area with DPW Director
This Month:
Continue to compile and review draft report sections
Develop cost benefit estimates for Energy Efficiency Study and provide memo for
Town review
Run additional models for Nantucket and Polpis Harbor with SMAST
Review Fertilizer Regulation and impact in Nantucket Harbor Watershed For TMDLs
as well as overall Town In Nitrogen sensitive areas
Finalize Hummock Pond MEP
Set meeting with GSA and Town Appraiser in Boston for protocol set
Meet with Town to discuss CWMP implementation and public outreach
Schedule Projected completion date – July 2014
Financial Budget - $616,000 Spent: $ 494,400.73
Town Action (s) Required:
Review and provide comments on the Energy Efficiency Study memo.
Participate in GSA and Town Appraiser Meeting
Town approve amendment for 2014 Town-wide Annual Water Quality Testing Program with SMAST
(based on 2012 contract)
226494 Jetties Support Update
Progress Last Month:
All Activities on hold until further budgets are approved
This Month:
Prepare agenda for meeting with Town, SSA and Hyline to discuss construction
scheduling in late October, early November 2014
Town of Nantucket, Massachusetts
Project Update
March 12, 2014
WOODARD & CURRAN 3 of 5
Coordinate With ACOE on Design Schedule
Schedule Projected Jetties Reconstruction Bid-Winter 2014
Projected Contractor Bid Award early May 2014.
Financial Budget - $20,000 Spent: $ 18,586
Town Action (s) Required:
Meet with Town to discuss further jetties support
224428 Miacomet Pond Watershed Study
Progress Last Month:
Prepared draft watershed delineation plan
Prepared draft land use plan
Prepared draft soils map
Began analysis of land use changes between current and 1990’s
Conducted field visit
Visited island to interview stakeholders including Richard Ray and Dave Fronzuto,
meet with Planning and review Planning Board’s documents, and conduct additional
verification of locations within watershed. Original meetings were canceled in January
and February due to winter storm.
This Month:
Compile information obtained for Planning Department
Finalize watershed delineation
Conduct interview with owner on Allen Lane
Complete analysis of land use changes
Schedule Projected completion date – May 2014. Date extended due to weather impacting field
investigations and to ensure time to meet with stakeholders.
Financial Engineering Budget - $125,800 Spent - $19,839
Town Action (s) Required:
None at this time
Town of Nantucket, Massachusetts
Project Update
March 12, 2014
WOODARD & CURRAN 4 of 5
225140 Phase IIB Sewer and Water Main Rehabilitation Project
Progress Last Month:
Project outreach performed to communicate to business and residents regarding
upcoming Broad Street construction.
Dewatering effort began on Broad Street, and traffic was diverted through truck lane
during construction between Easy Street and South Water Street.
Water construction was completed on lower Broad Street up to South Beach Street.
This Month:
Sewer construction will begin on Broad Street at intersection with South Beach Street,
and move toward North Water Street.
Construction will include replacement of sewer, storm, and water infrastructure.
Roadway shutdowns will be required. Residents and businesses advised to seek
alternate routes.
Schedule Projected completion date – October 2014
Financial Engineering Budget - $1,070,720 Spent - $726,260
Construction Bid - $3,504,911 (including change orders executed), Spent - $3,372,327
Town Action (s) Required:
Work with Woodard & Curran to coordinate with local businesses and residents during construction
Provide support as needed in field for utility identification
225839 Surfside WWTF Assessment and Upgrades
Progress Last Month:
Prepared cost estimate for installation of screening.
This Month
Provide memo on screenings assessment for Town review.
Develop plan for additional operational assistance to pilot running the plant with one
train of the advanced treatment system off-line.
Schedule Projected completion date – December 2014
Financial Budget - $110,000 Spent -$100,000
Town of Nantucket, Massachusetts
Project Update
March 12, 2014
WOODARD & CURRAN 5 of 5
Town Action (s) Required: None
Review and provide comment on the screenings assessment memo
What to look for this month:
Construction on Phase II B Water, Sewer and Drainage work on Broad Street