HomeMy WebLinkAboutWoodard and Curran Monthly Update March 15, 2012_201401230917005107TOWN OF NANTUCKET, MASSACHUSETTS
Monthly Update
WOODARD & CURRAN 1 of 2
MARCH 15, 2012
Projects
223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Continued Endangered Species Monitoring Program.
Received and transmitted Endangered Species Report.
Overlaid located endangered species habitats with archaeological resources to identify
potential treatment and discharge bed locations.
Met with Natural Heritage to discuss potential required mitigation on the FAA site.
This Month:
Continue to discuss mitigation with Natural Heritage and preparation for April GSA
meeting.
Continue work under Madaket Amendment No. 1 to include Surfside WWTP scope of
work consideration and evaluation of Madaket forcemain option(s).
Schedule Projected completion date – December 31, 2012 (Unchanged)
Financial Phase 1 Budget - $348,630 Spent - $82,596
Town Action (s) Required:
Meet on 3/22 to discuss Surfside WWTF staffing, administrative, and operational
objectives.
224386 Wastewater Action Plan
Phases 1 - 4
Progress Last Month:
Continued to negotiate with SMAST staff to clarify information contained in the SMAST
January 4th Final Updated Technical Memorandum (model runs 1 – 4).
Reviewed MEP Updated Technical Memorandum and created cover memo; posted on
website.
Worked with BOH, MassDEP, the Administration and Town Counsel on local ACO
language for failing onsite systems within needs areas.
Town of Nantucket, Massachusetts
Project Update
March 15, 2012
WOODARD & CURRAN 2 of 2
Finalized CWMP Update scope of work.
Reviewed the MassDEP CY 2012 Intended Use Plan (CWMP Update on fundable list)
This Month:
Prepare for 3/31 Annual Town Meeting
Attend Annual Town Meeting
Submit CWMP Update Scope of Work to MassDEP
Prepare CWMP Update CWSRF funding application; submit after ATM vote
certification
Schedule Projected completion date – April 15, 2012
Financial Budget - $186,000 Spent - $186,000
Town Action (s) Required:
Present CWMP Update capital expenditure at Annual Town Meeting.
Execute and submit CWMP Update CWSRF Application.
Newsworthy
Laurentide Environmental LLC has submitted the endangered species survey report.
Annual Town Meeting – Sewer Capital – 3/31/12
What to look for this month:
Meet with GSA (FAA Site)
Finalize CWMP Update scope of work and prepare CWSRF application.
ATM (3/31/12)