Monthly Update
WOODARD & CURRAN 1 of 3
JUNE 5, 2012
Projects
223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Attended April GSA meeting
Continued work with Madaket site surveys:
Natural Heritage and Endangered Species Program
Massachusetts Historical Commission
Under Madaket Amendment No. 1 began assessment of Madaket force-main options
and ability of Surfside WWTP to accept Madaket sewer flows. Currently assessing
alternative routes and identification of construction challenges for each proposed
route.
Met with Town at Surfside WWTF to discuss staffing, administrative, and operational
objectives
This Month:
Continue under Madaket Amendment No. 1 assessing alternative routes and
identification of construction challenges for each proposed route.
Continue work with Madaket site surveys
Schedule Projected completion date – December 31, 2012 (Unchanged)
Financial Phase 1 Budget - $348,630 Spent - $112,580
Town Action (s) Required:
Madakat WWTF site visit with GSA
Town of Nantucket, Massachusetts
Project Update
June 5, 2012
WOODARD & CURRAN 2 of 3
224386 Wastewater Action Plan
Phases 1 - 4
Progress Completed
Schedule Projected completion date – completed
Financial Budget - $186,000 Spent - $186,000
Town Action (s) Required:
None
CWMP Update
Progress Last Month:
Worked with BOH, MassDEP, the Administration, and Town Counsel on local ACO
language and new BOH Regulation for failing onsite systems within approved needs
areas.
Assisted the Marine and Coastal Resources Department with an Invitation to Bid for
the Town’s annual water quality sampling and analysis which was completed and a
contract awarded to SMAST. Contract is before the Board of Selectmen for approval
June 6th.
Finalized CWMP Update scope of work and submitted CWSRF application to
MassDEP.
Attended March 31, 2012 Annual Town Meeting. Article 15 – Appropriation: Enterprise
Funds Capital Expenditures included, funding of an increase in Phase IIB sewer
rehabilitation work by $2,000,000 (from 5,000,000 originally approved, to a new total of
$7,000,000) such work to also include improvements to certain portions of the sewers
in Fair Street, and $750,000 for an Update to the 2004 Comprehensive Wastewater
Management Plan - approved.
This Month:
Anticipate receipt of MassDEP Project Approval Certificate which will allow official start
of the Comprehensive Water Management Plan Update.
Town Action (s) Required:
Develop mission statement and select members of CWMP Citizen Advisory Committee
Develop summer associations/ civic groups/ environmental, etc. organizations meeting
schedule/assign presenters/prepare agendas
Town of Nantucket, Massachusetts
Project Update
June 5, 2012
WOODARD & CURRAN 3 of 3
Phase IIB Sewer Rehabilitation Project
Progress Last Month:
Attended meeting with Wannacomet Water Company representatives to discuss
inclusion of water main replacement in project area.
Drafted proposed scope and budget for initial review by the Administration
This Month:
Contract before the Board of Selectmen for approval.
Town Action (s) Required:
Acquire existing survey data for use by Woodard & Curran
Execute Contract for design and construction services phases of engineering
Newsworthy
None
What to look for this month:
MassDEP Project Approval Certificate/Notice to proceed CWMP Update
Execute CWMP Update Agreement w/ Woodard & Curran
Execute SMAST contracts. Hummock Pond MEP, Sesechacha Pond 303 (d) removal
Hold Citizens’ Advisory organizational meeting.