HomeMy WebLinkAboutWoodard and Curran Monthly Update August 9, 2013_201401230916589951TOWN OF NANTUCKET, MASSACHUSETTS
Monthly Update
WOODARD & CURRAN 1 of 4
AUGUST 9, 2013
Projects
223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Surfside Capacity Analysis Completed
Began evaluation of sewer capacity
This Month:
Begin cost estimating for upgrades needed for Surfside WWTF
Submit Scope of Work to MassDEP for re-rating Surfside infiltration bed effluent
loading
Obtain and review Surfside beds monitoring well data
Final review of PAL report on FAA site
Schedule Projected completion date – December 31, 2013
Financial Phase 1 Budget - $348,630 Spent - $ 278,734
Town Action (s) Required:
Continue to support consultants’ investigations of operations and data gathering at
Surfside WWTF for the infiltration bed analysis
225139 CWMP Update
Progress Last Month:
Continued with CWMP Update report writing
Continued working with SMAST on 2103 Water Quality Monitoring Program Continue
working with SMAST on completion of Hummock Pond MEP Study-late August.
Coordinated CY2014 State Revolving Fund (SRF) applications
Continued to support SPWG
Flows and loads completed
Town of Nantucket, Massachusetts
Project Update
August 9, 2013
WOODARD & CURRAN 2 of 4
Conducted field inspection of Nantucket Harbor Watershed to identify potential
stormwater best management practices which could be used to reduce nutrient
loading as part of the overall recommended nutrient removal plan
This Month:
Continue with CWMP Update report writing
Continue coordination with Board of Health
Septage Management Plan – Pumping Program
Tight Tank Policy
ACO Process – Expansion potential
Continue coordination with Natural Resources Department
Fertilizer
Annual Water Quality Program
Review TMDL plans
Hummock Pond MEP Completion
Additional Model Run Scenarios
Evaluate On-Site, I/A and WWTF options
Begin WWTF Energy Study
Amendment No. 1 approved – Public Outreach
Schedule Projected completion date – December 2013
Financial Budget - $571,000 Spent: $ 333,162
Town Action (s) Required:
SPWG to begin contemplating funding for CWMP Update Recommended Plan.
226494 Jetties Support Update
Progress Last Month:
Continued coordination with Army Corps of Engineers (ACOE)
Survey in Nantucket Harbor on-going
This Month:
Continue with ACOE Coordination
Survey completion due early fall 2013
Continue coordination with Dave Fronzuto for local conditions
Town of Nantucket, Massachusetts
Project Update
August 9, 2013
WOODARD & CURRAN 3 of 4
Schedule Projected completion date – fall 2014 (Jetties reconstruction. W&C to continue oversight for
project duration))
Financial Budget - $20,000 Spent: $ 17,959
Town Action (s) Required:
None at this time
225140 Phase IIB Sewer and Water Main Rehabilitation Project
Progress Last Month:
Project on hold for summer.
Managing paperwork associated with Contractor Payment Requests and State
Funding (SRF) Loan Drawdowns.
Prepared proposed construction schedule
This Month:
Schedule meetings for September with impacted businesses, Steamship Authority and
various Town Administration entities.
Finalize construction schedule
Schedule Projected completion date – October 2014
Financial Engineering Budget - $921,700 Spent - $570,513
Construction Bid - $3,494,320.87 Spent - $ 1,883,236
Town Action (s) Required:
Review proposed construction schedule
225839 Surfside WWTF Assessment and Upgrades
Progress Last Month:
Received Corrosion Control Study from sub-consultant
Began assessment and calculations for Headworks upgrades
Worked with Operators to optimize some of the processes at the treatment plant
Conducted Vactor Truck Unloading Alternatives
Town of Nantucket, Massachusetts
Project Update
August 9, 2013
WOODARD & CURRAN 4 of 4
This Month:
Continue assessment and calculations for Headworks upgrades
Begin Aeration Header alternatives assessment
Schedule Projected completion date – December 2014
Financial Budget - $110,000 Spent - $51,162.67
Town Action (s) Required:
Continue to provide support to the Consultant for access to the WWTF and records.
What to look for this month:
Preliminary meetings for Phase IIB to begin second season of sewer and water
replacement in Downtown area.