HomeMy WebLinkAboutWoodard and Curran Monthly Update August 17, 2012_201401230916591826TOWN OF NANTUCKET, MASSACHUSETTS
Monthly Update
WOODARD & CURRAN 1 of 3
AUGUST 17, 2012
Projects
223970 Madaket Wastewater Treatment Facility & Collection System
Phase 1 - Preliminary Design Phase
Progress Last Month:
Continued under Madaket Amendment No. 1 assessing alternative routes and
identification of construction challenges for each proposed route.
Continued work with Madaket site surveys – Massachusetts Historical Commission
(PAL). Reviewing scope and budget for botanist oversight as required by NHESP.
This Month:
Continue assessing alternative routes
Continue Massachusetts Historical Commission site survey
Schedule Projected completion date – December 31, 2012 (Unchanged)
Financial Phase 1 Budget - $348,630 Spent - $ 131,780
Town Action (s) Required:
DPW Director discussions with consultant and Town Staff on viability of alternative routes,
construction impacts, development and sewer district impacts.
225139 CWMP Update
Progress Last Month:
Developed summer associations/ civic groups/ environmental, etc. organizations
meeting schedule/assign presenters/prepare agendas.
Conducted BOH records review
Conducted UMass Field Station Representative meeting
Attended Hummock Pond Neighborhood Association meeting
Assisted Town in formulating criteria for Sewer Planning work group
Town of Nantucket, Massachusetts
Project Update
August 17, 2012
WOODARD & CURRAN 2 of 3
This Month:
Continue attending and presenting at summer meetings
Finalize maps of needs areas
Submit SMAST Water Quality contract to Town – Sesechacha
Work with BOH to advance Septic ACO template
Schedule Projected completion date – December 2013
Financial Budget - $571,000 Spent: $82,900
Town Action (s) Required:
Develop mission statement with members of CWMP Sewer Planning Work Group,
setup schedule and format for Group and Public meetings, develop list of CWMP
topics for discussion
Town to review and confirm maps of needs areas.
225140 Phase IIB Sewer Rehabilitation Project
Progress Last Month:
Finalized and signed subconsulting contract with Blackwell & Associates Inc. for
survey update.
Began field investigations and survey for design
Drafted Design Basis Report
Began preparation of draft specifications.
Began preparation of Notice of Intent
Met with Street and Sidewalk Committee representative on July 25, 2012
Met with Historical District Agent on July 25, 2012
This Month:
Finalize Design Basis Report
Continue coordination with DPW, Wannacomet Water Company, Streets and
SidewalksCommittee, Conservation Commission and Historic District Commission
Begin development of project plans
Schedule Projected completion date – December 2013
Town of Nantucket, Massachusetts
Project Update
August 17, 2012
WOODARD & CURRAN 3 of 3
Financial Budget - $921,700 Spent - $61,387
Town Action (s) Required:
Review and comment on Design Basis Report
Newsworthy
First meeting of CWMP Sewer Planning Work Group September 12th.
What to look for this month:
Phase IIB survey work along Fair Street, Westminster Ave., Hussey St. and India St.
CWMP Update attendance at summer meetings of taxpayers, civic and association meetings.
Attendance at Board of Health ACO meeting August 30th
Additional Services
Developed an approach to assist DPW Director with Surfside/Siasconset operations
and plant facilities challenges and submitted proposal to the Town.
Executed contract with botanist for Sheep Pond Road for survey and permit.